CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
1. Solenoid
2. Calibration shim, B**,
ID20mm, OD23.2mm,
Thickness 2.98-3.10mm
3. Armature
4. Ball
5. Nut
6. Valve spacer
7. Spacer
8. Dowel
9. Valve plunger
10. O-ring
11. Injector body
12. Spacer
13. Calibration shim, B23, ID
3.15mm, OD 5.75mm,
thickness 1.0-2.5mm
14. Spring
15. Pin
16. Dowel
17. Spacer
18. Dowel
19. Nozzle
20. Nozzle nut
21. Plastic cap
To measure total 2 calibration shims
2
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – on Nozzle Side
Task 1 – Adjust Needle Opening Pressure (1)
1. Fasten injector on a vise with injector clamping tool.
Loose nozzle nut (20)
2. Remove Calibration shim B23 (13), spring (14), spacer
(12).
3. Install micrometer with extension probe 511012 on
frame 970100. Place platform 511020 on frame 970100.
Adjusting micrometer height by the hand wheel, then
lock the moving beam by the handles. Zero
micrometer on platform 511020.
Caution: Pay close attention when adjusting micrometer
mounting arm downward, to prevent micrometer damage.
3
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – on Nozzle Side
Task 1 – Adjust Needle Opening Pressure (2)
4. Measure the thickness of shim B23 (13).
5. Fasten injector by using the matching holder on
frame 970100.
6. Place spacer(12) and shim B23 (13) in injector cavity.
4
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – on Nozzle Side
Task 1 – Adjust Needle Opening Pressure (3)
7. Place 10mm thickness gauge on the injector.
Adjusting the position of micrometer. Zero
micrometer on the thickness gauge.
8. Remove the thickness gauge. Place spring(14) and
spacer (15) in injector
9. Place 10mm thickness gauge on it. Measure the top
of thickness gauge.
5
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – on Nozzle Side
Task 1 – Adjust Needle Opening Pressure (4)
10. If the measured value does not meet requirement,
replace calibration shim B23 with thickness indicated
on PC screen
11. Fasten nozzle nut with torque 90Nm
6
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – Solenoid Side
Task 2 – Inspect Weariness of Valve Spacer (1)
1. Loose solenoid (1) from injector.
2. Remove calibration shim B44(2), armature(3), and
ball(4)
3. Loose nut (5) by using special tool.
7
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – Solenoid Side
Task 2 – Inspect Weariness of Valve Spacer (2)
4. Remove valve spacer (6). Check the sealing
surface in the center by using the microscope
5. The valve spacer with light weariness is still
usable. Replace the severe worn one with new
part.
8
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – Solenoid Side
Task 2 – Inspect Weariness of Valve Spacer (3)
6. Place The ball (4), with flat surface up, on the
cavity at the end cavity of armature (3 ).
7. It is wrong to place the ball with spherical surface
up.
9
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – Solenoid Side
Task 3 – Adjust Armature Lift (1)
1. Zero micrometer on platform 511020
2. Measure the thickness of shim B44
3. Install injector on the frame 970100 by using
respective holder.
10
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – Solenoid Side
Task 3 – Adjust Armature Lift (2)
4. Extension rod 511011 and sleeve 97039 on
micrometer.
5. Place calibration shim B44 (2) on injector
6. Place 1mm thickness gauge 511015 on shim B44
11
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – Solenoid Side
Task 3 – Adjust Armature Lift (3)
7. Zero micrometer on the thickness gauge
8. Remove the thickness gauge and then measure
injector
9. If the measured value does not meet requirement,
replace calibration shim B44 with thickness
indicated on PC screen..
12
CRM-100 Common Rail Injector Measurement System
http://www.injectronix.com
Working Procedure – Solenoid Side
Task 3 – Adjust Armature Lift (4)
10. Using the shim B44 of correct thickness to assemble
the injector. Fasten solenoid, torque 12-15Nm