ACTUAL DATES
Uri II HEP
Sr. No. Description Portal Start Date Tunnel Start Dates Tunnel Finish Dates
1 Open Channel Excavation 17/Nov/05
2 Dam Excavation 19/Jun/06 28/Nov/07
3 Dam Concrete 27/Nov/07
3 Diversion Tunnel
a DT Inlet 7/Dec/05 14/Mar/06 31/Aug/06
b DT Outlet 11/Dec/05 14/Jun/06 9/Oct/06
c Benching
Inlet 6/Jul/06 29/Aug/06
Outlet 12/Oct/06 31/Oct/06
d MAT concrete 16/Sep/06 17/Jan/07
e Kerb concrete 16/Sep/06 17/Jan/07
f Overt Concrete 29/Oct/06 20/Jan/07
g Invert Concrete 23/Dec/06 19/Jan/07
h Inlet concrete 18/Oct/06 6/Feb/07
i Outlet concrete
j Grouting
4 Coffer dam
a U/S Cofferdam 22/Jan/07
b D/S Pre Cofferdam 24/Jan/07
5 HRT
a Adit I 2/Dec/05 7/Mar/06 2/Jun/06
HRT U/S
Heading 29/Jun/06 6/Nov/06
Benching 15/Jan/07 14/Feb/07
MAT concrete
Kerb concrete
Overt Concrete 4/May/07 7/Jun/07
Invert Concrete
HRT D/S
Heading 3/Jun/06 2/May/07
Benching 14/Feb/07 5/Aug/07
MAT concrete
Kerb concrete
Overt Concrete 21/Jul/07 19/Jul/08
Invert Concrete
b Adit II 2/Dec/05 21/Feb/06 9/Dec/06
HRT U/S 15/Dec/06 22/Jun/07
Heading 15/Dec/06 22/Jun/07
Benching 9/Aug/07 13/Dec/07
MAT concrete
Kerb concrete
Overt Concrete 19/Jul/08
Invert Concrete
HRT D/S
Heading 15/Dec/06 29/Mar/08
Benching 16/Apr/08 13/Jul/08
MAT concrete
Kerb concrete
Overt Concrete 23/Jul/08
Invert Concrete
a Adit III 20/Dec/05 4/Jul/06 12/Sep/06
HRT U/S
b Heading 13/Sep/06 29/Mar/08
c Benching 19/Apr/08 8/Feb/09
Kerb 4/Feb/09
Overt
HRT D/S
d Heading 13/Sep/06 23/Jan/08
e Benching 4/May/08
6 TRT
a Adit IV 4/Feb/06 31/May/06 6/Dec/06
U/S
b Heading 9/Dec/06 3/Dec/08
c Benching 1/Feb/09
D/S
d Heading 9/Dec/06 6/Nov/07
e Benching 22/Dec/07 18/Jun/08
Kerb 18/Aug/08
Overt 3/Sep/08
Thru DSSG
f Heading 17/Aug/07 3/Dec/08
g Benching 16/Jan/09
Thru ADIT-4 towards DSSG
Overt Concrete 1/Feb/10
Thru DSSG
Overt Concrete
7 PH Complex
ACTUAL DATES
Uri II HEP
Sr. No. Description Portal Start Date Tunnel Start Dates Tunnel Finish Dates
MAT
a MAT up to Jn 11/Aug/06 25/Aug/06 6/Mar/07
b Mat from Jn to PH 3/Jul/07 30/Nov/07
c Mat from PH to MIV 11/Dec/07 26/Jul/08
d Branch tunnel To PH Top 27/Feb/07 2/Jun/07
e Branch Tunnel TC Top 24/Apr/07 7/Jul/07
f D/S Surge Gallery(a-Heading) 24/Oct/06 28/Jul/07
g D/S Surge Gallery(b-Heading) 13/Dec/08 25/Mar/09
h Adit to Draft Tube Gate Hall 14/Jan/07 30/Mar/07
i Draft Tube Gate Hall(Heading ) 28/Mar/07 10/Jun/07
j Draft Tube Gate Hall(Benching)-1 27/Jul/07 12/Aug/07
k Draft Tube Gate Hall(Benching)-2 20/Nov/07 10/Jan/08
l Pilot Tunnel to PH 1/Jun/07 29/Jul/07 58
m Enlargement to PH 4/Jul/07 28/Aug/07 55
n Benching of Power House
1st Stage Benching 18/Sep/07 14/Nov/07 256
2nd Stage Benching 18/Nov/07 10/Jan/08
3rd Stage Benching 11/Jan/08 16/Mar/08
4th Stage Benching 18/Mar/08 13/May/08
5th Stage Benching 14/May/08 27/Jul/08
o Pilot Tunnel to TC 11/Jul/07 22/Jan/08
p Enlargement to TC 17/Aug/07 31/Mar/08
q Benching of TC 29/Nov/07 5/Mar/09
Sevice Bay 19/Oct/08
Handing Over of Unit-1 15/Oct/08
Handing Over of Unit-2 3/Dec/08
Handing Over of Unit-3 25/Apr/09
Handing Over of Unit-4
Casting of Crane Beam at Unit-1 U/S 12/May/09 13/May/09
Casting of Crane Beam at Unit-1 U/S 21/May/09 21/May/09
Casting of Crane Beam at Unit-2 D/S 29/Sep/09 30/Sep/09
Casting of Crane Beam at Unit-2 U/S 10/Oct/09 11/Oct/09
r MIV Gallery 30/Jul/08 22/Feb/09
s Manifold to draft Tube 2/Aug/07 10/Sep/07
t Draft Tube Tunnels(Unit-3) 14/Aug/07 23/Jul/08
u Draft Tube Tunnels(Unit-1) 14/Sep/07 24/Jan/08
v Draft Tube Tunnels(Unit-2) 1/Oct/07 25/Jan/08
w Draft Tube Tunnels(Unit-4) 27/Jan/08 17/May/08
x Bus Duct-1 3/Jan/08 26/Mar/08
y Bus Duct-2 16/Mar/08 30/May/08
z Bus Duct-3 1/Apr/08 31/Aug/08
aa Bus Duct-4 1/Apr/08 3/Oct/08
ab Adit to Bottom of PS 14/Apr/08 9/Sep/08
ac Penstock Unit-1 (up to MIV ) 5/Oct/08 11/Nov/08
ad Penstock Unit-2 (up to MIV) 23/Nov/08 5/Dec/08
ae Penstock Unit-3 (up to MIV) 30/Nov/08 4/Mar/09
af Penstock Unit-4 (up to MIV) 1/Jan/09 4/Mar/09
ag Penstock Unit-1 (up to PH ) 19/Jul/08 24/Nov/08
ah Penstock Unit-2 (up to PH) 25/May/08 20/Mar/09
ai Penstock Unit-3 (up to PH) 20/May/08 18/Apr/09
aj Penstock Unit-4 (up to PH) 20/May/08 18/Apr/09
ak Draft Tube Gate Shaft-3 4/Jul/08 1/Jan/09
al Draft Tube Gate Shaft-4 24/Jun/08 29/Jan/09
am Draft Tube Gate Shaft-2 18/Feb/09 2/Nov/09
an Draft Tube Gate Shaft-1 1/Mar/09 20/Sep/09
Unit -1 PH
Concrete of 3rd Slab U/S 13/May/09
Concrete of 3rd Slab D/S 21/May/09
Unit -2 PH
Concrete of 3rd Slab U/S 11/Oct/09
Concrete of 3rd Slab D/S 30/Sep/09
Unit -3 PH
Concrete of 3rd Slab U/S 15/Jan/10
Concrete of 3rd Slab D/S 29/Jan/10
8 Pressure Shaft
Actual Adit completed on
a Adit to Top of Pressure Shaft 18/Sep/06 7/Feb/07
11th Jan 2007.
b Vertical Pressure Shaft-2 31/May/07 15/Mar/08
c Vertical Pressure Shaft-1 9/Aug/07 3/Jul/08
d Upper Horizontal-PS2 30/Jan/08 25/Mar/08
e Upper Horizontal-PS1 9/May/08 31/Aug/08
f Cable and Ventilation Tunnel 1/Sep/08
g Surge Shaft-Open 6/Mar/07 3/Jan/08
h Surge Shaft (Full Face) 12/Mar/08
i Surge Shaft (Pilot) 12/Mar/08 2/Aug/08
ACTUAL DATES
Uri II HEP
Sr. No. Description Portal Start Date Tunnel Start Dates Tunnel Finish Dates
1 Open Channel Excavation 17/Nov/05
2 Dam Excavation 19/Jun/06 28/Nov/07
3 Dam Concrete 27/Nov/07
3 Diversion Tunnel
a DT Inlet 7/Dec/05 14/Mar/06 31/Aug/06
b DT Outlet 11/Dec/05 14/Jun/06 9/Oct/06
c Benching
Inlet 6/Jul/06 29/Aug/06
Outlet 12/Oct/06 31/Oct/06
d MAT concrete 16/Sep/06 17/Jan/07
e Kerb concrete 16/Sep/06 17/Jan/07
f Overt Concrete 29/Oct/06 20/Jan/07
g Invert Concrete 23/Dec/06 19/Jan/07
h Inlet concrete 18/Oct/06 6/Feb/07
i Outlet concrete
j Grouting
4 Coffer dam
a U/S Cofferdam 22/Jan/07
b D/S Pre Cofferdam 24/Jan/07
5 HRT
a Adit I 2/Dec/05 7/Mar/06 2/Jun/06
HRT U/S
Heading 29/Jun/06 6/Nov/06
Benching
MAT concrete
Kerb concrete
Overt Concrete 4/May/07
Invert Concrete
HRT D/S
Heading 3/Jun/06 2/May/07
Benching
MAT concrete
Kerb concrete
Overt Concrete 21/Jul/07
Invert Concrete
b Adit II 2/Dec/05 21/Feb/06 9/Dec/06
HRT U/S 15/Dec/06 22/Jun/07
Heading 15/Dec/06 22/Jun/07
Benching
MAT concrete
Kerb concrete
Overt Concrete
Invert Concrete
HRT D/S
Heading 15/Dec/06 29/Mar/08
Benching
MAT concrete
Kerb concrete
Overt Concrete
Invert Concrete
a Adit III 20/Dec/05 4/Jul/06 12/Sep/06
HRT U/S
b Heading 13/Sep/06 29/Mar/08
c Benching 19/Apr/08
Kerb
Overt
HRT D/S
d Heading 13/Sep/06 23/Jan/08
e Benching 4/May/08
6 TRT
a Adit IV 4/Feb/06 31/May/06 6/Dec/06
U/S
b Heading 9/Dec/06 3/Dec/08
c Benching
D/S
d Heading 9/Dec/06 6/Nov/07
e Benching 22/Dec/07 18/Jun/08
Kerb
Overt
Thru DSSG
f Heading 17/Aug/07 3/Dec/08
g Benching
7 PH Complex
MAT
a MAT up to Jn 11/Aug/06 25/Aug/06 6/Mar/07
b Mat from Jn to PH 3/Jul/07 30/Nov/07
c Mat from PH to MIV 11/Dec/07 26/Jul/08
ACTUAL DATES
Uri II HEP
Sr. No. Description Portal Start Date Tunnel Start Dates Tunnel Finish Dates
d Branch tunnel To PH Top 27/Feb/07 2/Jun/07
e Branch Tunnel TC Top 24/Apr/07 7/Jul/07
f D/S Surge Gallery(a-Heading) 24/Oct/06 28/Jul/07
g Adit to Draft Tube Gate Hall 14/Jan/07 30/Mar/07
h Draft Tube Gate Hall(Heading ) 28/Mar/07 10/Jun/07
i Draft Tube Gate Hall(Benching)-1 27/Jul/07 12/Aug/07
j Draft Tube Gate Hall(Benching)-2 20/Nov/07 10/Jan/08
k Pilot Tunnel to PH 1/Jun/07 29/Jul/07 58
l Enlargement to PH 4/Jul/07 28/Aug/07 55
m Benching of Power House
1st Stage Benching 18/Sep/07 14/Nov/07 256
2nd Stage Benching 18/Nov/07 10/Jan/08
3rd Stage Benching 11/Jan/08 16/Mar/08
4th Stage Benching 18/Mar/08 13/May/08
5th Stage Benching 14/May/08
n Pilot Tunnel to TC 11/Jul/07 22/Jan/08
o Enlargement to TC 17/Aug/07 31/Mar/08
p Benching of TC 29/Nov/07
q Manifold to draft Tube 2/Aug/07 10/Sep/07
r Draft Tube Tunnels(Unit-3) 14/Aug/07 23/Jul/08
s Draft Tube Tunnels(Unit-1) 14/Sep/07 24/Jan/08
t Draft Tube Tunnels(Unit-2) 1/Oct/07 25/Jan/08
u Draft Tube Tunnels(Unit-4) 27/Jan/08 17/May/08
v Bus Duct-1 3/Jan/08 26/Mar/08
w Bus Duct-2 16/Mar/08 30/May/08
x Bus Duct-3 1/Apr/08 31/Aug/08
y Bus Duct-4 1/Apr/08 3/Oct/08
z Adit to Bottom of PS 14/Apr/08 9/Sep/08
aa Penstock Unit-1 (up to MIV ) 5/Oct/08 11/Nov/08
ab Penstock Unit-2 (up to MIV) 23/Nov/08 5/Dec/08
ac Penstock Unit-3 (up to MIV) 30/Nov/08
ad Penstock Unit-4 (up to MIV) 1/Jan/09
ae Penstock Unit-1 (up to PH ) 19/Jul/08 24/Nov/08
af Penstock Unit-2 (up to PH) 25/May/08
ag Penstock Unit-3 (up to PH) 20/May/08
ah Penstock Unit-4 (up to PH) 20/May/08
ae Draft Tube Gate Shaft-3 4/Jul/08
af Draft Tube Gate Shaft-4 24/Jun/08
8 Pressure Shaft
Actual Adit completed on
a Adit to Top of Pressure Shaft 18/Sep/06 7/Feb/07
11th Jan 2007.
b Vertical Pressure Shaft-2 31/May/07 15/Mar/08
c Vertical Pressure Shaft-1 9/Aug/07 3/Jul/08
d Upper Horizontal-PS2 30/Jan/08 25/Mar/08
e Upper Horizontal-PS1 9/May/08 31/Aug/08
f Surge Shaft-Open 6/Mar/07 3/Jan/08
g Surge Shaft (Full Face) 12/Mar/08