ID         Task      Task Name                   Duration   Start       Finish           Predecessors
Qtr 3, 2017                    Qtr 4, 2017             Qtr 1, 2018
           Mode                                                                                                  Aug     Sep        Oct       Nov   Dec     Jan       Feb   Mar
     1               FORMATION OF        2 days             Mon        Tue 9/19/17
                     GROUP                                  9/18/17
     2               4 STOREY SHOP LOT 40 days              Wed 9/20/17Tue 11/14/171
     3                  FINDING DESIGN 7 days               Wed        Thu 9/28/17 1
                        OF BUILDING                         9/20/17
                        STRUCTURE
     4                  PREPARATION OF 7 days               Fri 9/29/17 Mon          3
                        PROPOSAL                                         10/9/17
     5                  GROUND FLOOR PLAN2 days             Tue 10/10/17Wed 10/11/174
     6                  FIRST FLOOR PLAN 2 days             Thu 10/12/17Fri 10/13/17 5
     7                  SECOND FLOOR PLAN2 days             Mon 10/16/17Tue 10/17/176
     8                  THIRD FLOOR PLAN2 days              Mon 10/16/17Tue 10/17/176
     9                  ROOF PLAN        2 days             Wed 10/18/17Thu 10/19/178
     10                 FRONT ELEVATION 2 days              Fri 10/20/17 Mon         9
                        PLAN                                             10/23/17
     11                 RIGHT ELEVATION 2 days              Fri 10/20/17 Mon         9
                        PLAN                                             10/23/17
     12                 LEFT ELEVATION PLAN
                                         2 days             Fri 10/20/17 Mon 10/23/179
     13                 A-A SECTION VIEW 2 days             Fri 10/20/17 Mon         9
                        PLAN                                             10/23/17
     14                 DESIGN           16 days            Tue 10/24/17Tue 11/14/1713
     15                    BEAM          5 days             Fri 10/27/17 Thu 11/2/17 16
     16                    SLAB          3 days             Tue 10/24/17Thu 10/26/1713
     17                    COLUMN        3 days             Fri 11/3/17 Tue 11/7/17 15
     18                    RC WALL       4 days             Fri 11/3/17 Wed 11/8/1715
                                 Task                                    Inactive Summary                              External Tasks
                                 Split                                   Manual Task                                   External Milestone
                                 Milestone                               Duration-only                                 Deadline
Project: capestone
                                 Summary                                 Manual Summary Rollup                         Progress
Date: Wed 1/17/18
                                 Project Summary                         Manual Summary                                Manual Progress
                                 Inactive Task                           Start-only
                                 Inactive Milestone                      Finish-only
                                                                             Page 1
ID         Task      Task Name                   Duration   Start       Finish           Predecessors
                                                                                                   Qtr 3, 2017                    Qtr 4, 2017             Qtr 1, 2018
           Mode                                                                                                  Aug     Sep        Oct       Nov   Dec     Jan       Feb   Mar
     19                   STAIRCASE     2 days              Tue 10/24/17Wed 10/25/1713
     20                   FOUNDATION 4 days                 Thu 11/9/17 Tue 11/14/1718
     21              2 STOREY OFFICE    39 days             Wed 11/15/17 Mon 1/8/18 20
     22                 GROUND FLOOR 7 days                 Wed          Thu         13
                        PLAN                                11/15/17     11/23/17
     23                 1ST FLOOR PLAN 5 days               Fri 11/24/17 Thu 11/30/1722
     24                 FRONT ELEVATION 3 days              Fri 12/1/17 Tue 12/5/17 23
                        PLAN
     25                 REAR ELEVATION 3 days               Wed         Wed          24
                        PLAN                                12/6/17     12/13/17
     26                 DESIGN          18 days             Thu 12/14/17Mon 1/8/18 25
     27                   BEAM          7 days              Thu 12/21/17Fri 12/29/17 28
     28                   SLAB          5 days              Thu 12/14/17Wed 12/20/1725
     29                   COLUMN        3 days              Mon 1/1/18 Wed 1/3/18 27
     30                   STAIRCASE     3 days              Thu 12/14/17Mon 12/18/1725
     31                   FOUNDATION 3 days                 Thu 1/4/18 Mon 1/8/18 29
                                 Task                                    Inactive Summary                              External Tasks
                                 Split                                   Manual Task                                   External Milestone
                                 Milestone                               Duration-only                                 Deadline
Project: capestone
                                 Summary                                 Manual Summary Rollup                         Progress
Date: Wed 1/17/18