Ch.2 Lectur 1&2 4in1
Ch.2 Lectur 1&2 4in1
time pLanning
    Lecture-2                                                As we discussed in the previous chapter,
    chapter two - time pLanning                               Time planning may have the following
            project work Breakdown                           process.
            activity duration estimation                       activity definition (using WBS)
            scheduLing                                         duration estimation
            project network anaLysis (modeLing) (cpm,
             pert & pna)                                        schedule development (sequencing, Net working
                                                                 etc.) and
                                                                controlling.
11/7/2017                     Temesgen G.                1    11/7/2017                         Temesgen G.                               2
The project work-breakdown process involves breaking                             Residential Buildings                     Service Buildings                Recreation Centers
 down of the project work into manageable parts arranged                                                                                                                                  Sub projects
in a hierarchical order till the desired level is reached. Educational Buildings Health Centre Shopping centre
 the project. Any work not in the WBS is outside the scope                     Base construction               Footing Con                 Plinth wall Con     Ground floor Con        Work package
 of the project. (Eg…)
It is used to develop or confirm a common understanding                       Earth work                 Base preparation             Blinding
                                                                                                                      Activity Duration
             Project work Breakdown …
                                                                                          Duration of an activity is defined as the
Example, Operation involved in concreting are;                                                expected economical transaction time.
      Cleaning and preparing inner side of the raft for                                       The estimation of time is based upon the
       concreting                                                                              current practices carried out in an
      Pumping concrete                                                                        organized manner under the normal
      Spreading and vibrating concrete                                                        prevailing conditions, and its assessment
                                                                                               is done preferably, by the person
      Finishing of top concrete surface                                                       responsible for its performance.
            per unit of resource x resource earmarked]                            Estimate Activity Resources – estimating the type and quantities of
                                                                                   material, people, equipment, or supplies required to perform each
                                     t=Q/(nXp)                                     activity
                                                                            11/7/2017                            Temesgen G.                             12
                                                                                                                                                          11/7/2017
                        Scheduling Cont…
                                                                                                    Scheduling Techniques
      Scheduling may also Classified as:
            Construction schedule                                                 Line-of-Balance
            Material schedule                                                     bar chart/Gantt charts
            Labor schedule                                                        Net work diagram
            Equipment schedule                                                          Critical Path Method (CPM)
            Expenditure schedule                                                        Program Evaluation and Review Technique
                                                                                          (PERT)
            Eontrol schedule
                                                                                         Precedence diagramming method (PDM)/PNA
11/7/2017                          Temesgen G.                                15   11/7/2017                      Temesgen G.                        16
                                                                                                                                              11/7/2017
LOB LOB
                                                                                            10
 housing, high rise buildings, tunnels, etc.                                                8
                                                                            No. of Houses
A typical LOB diagram is shown in the next slide                                           6
                                                                                            0
                                                                                                 0   50   100          150   200   250
                                                                                                                TIME
                                                           19
                                                                                                                                         20
                                                                                                                                                                                                                                 11/7/2017
1     Simple project/sub
      project                          Bar Chart      Bar Chart                Bar Chart       Bar Chart
      (a)Non-repetitive work
      (b)Repetitive work               LOB            LOB                      LOB             LOB/Bar chart                                              Lecture-3
2     Complex sub-projects             CPM            Time scale                               Bar Chart
      (a)Deterministic                                Network
      (b)Probabilistic                 PERT                                    CPM             >>
                                                      >>
3     Complex Projects                 PNA            Bar Chart                PNA             Bar Chart
      (a)Non-repetitive W.             PNA            LOB                      LOB             Bar Chart/LOB
      (b)Repetitive work               PERT           Time Scale network       PERT            Bar Chart
      (c)Probabilistic
CPM-Critical Path
PERT-Programme Evaluation and Review Techniques       BC-Bar Chart
PNA- Precedence Network Analysis                      TSN-Time Scale Network/Logic Bar Chart
LOB-Line of Balance                                    23                                                            11/7/2017                                        Temesgen G.                                           24
                                                                                                                                                   11/7/2017
20 40 60
D E F D E F
             Event Timings, Activity Timings and                                   • Latest Finish Time of an activity (i,j) [LFT(i,j)]
                      Associated Terms                                                     –the latest time that an activity needs to be
Start and finish times
• Earliest Start Time of an activity (i,j) [EST(i,j)]
                                                                                            completed in order that there is no delay in the
• This is the earliest that the activity (i,j) can be started, i.e., all the
                                                                                            project completion.
  necessary preconditions are met.                                                 • Latest Start Time of an activity (i,j) [LST(i,j)]
• Earliest Finish Time of an activity (i,j) [EFT(i,j)]
                                                                                           –the latest time when an activity must be started, in
• This is the earliest that an activity can be completed. Mathematically,
  the relationship can be expressed as                                                      order that there is no delay in the project
• EFT (i,j)= EST(i,j) + D(i,j)                                                              completion.
                                                                                           LST(i,j) = LFT(i,j) – D(i,j)
11/7/2017                          Temesgen G.                            37   11/7/2017                         Temesgen G.                        38
                                EXAMPLE
                    Task ID         Duration Dependency
                                                                                                               Network of the example
                    A               7                                                                                  C
                    B               3
                                                                                                       A
                                                                                                                   2   6        3                 G
                    C               6                     A                                                    7
                                                                                                                                              3
                                                                                                                                                                     H
                    D               3                     B                                        A
                                                                                                           B                D                 6         E        7        8
                                                                                                1  4
                                                                                                           3
                                                                                                                   4                                                 2
                    E               3                     D,F                                                               3                           3
                                                                                                                                     F
                    F               2                     B                                                                               2
                    G               3                     C                                                                     5
                    H               2                     E,G
  For example, suppose we have two sets of estimate                                In order to measure the uncertainty
   provided by the different estimator for the same                                  associated with the estimate of duration of an
   ‘design foundation’ activity.                                                     activity, the standard deviation (St) and the
  In order of (te, tm,tp), let the first set of estimate (14,                       variance Vt are determined, which in PERT are
   18, 28) and the other set of estimates be (17, 18, 25).                           defined as:
  There is large variability in the estimates of first                             St = (tp-to)/6 and
   estimator compared to the second one, even though                                Vt = (St)2
   the expected or average activity duration turns out to                           The formula for St indicates that it is one sixth
   be 19 in both the cases (verify!!!).                                              of the difference between the two extreme
                                                                                     time estimates.
Further, the greater the uncertainty in time estimates,         For the two sets of estimate used in ‘design activity’,
 the greater the value of (tp-to), and the more spread            the St and Vt would be 2.33 days and 5.44 respectively
 out will be the distribution curve.                              for first set of estimates while 1.33 days and 1.77 are
A high St represents a high degree of uncertainty                the corresponding values of St and Vt for the second
 regarding activity times. In other words there is a              set of estimates.
 greater chance that the actual time required to                 The expected length or duration of project Te is
 complete the activity will differ significantly from the         calculated by summing up the expected duration te’s
 expected time te.                                                of activities on the critical path.
    The critical path is determined following the                       In case, there is more than one critical path in a
     forward pass and backward pass explained                              project network, then the path with the largest
     earlier.                                                              variance is chosen to determine the VT and ST.
    The variance associated with the critical path                        Mathematically,
     is the sum of variances associated with the                         • Te= ∑te
     activities on the critical path.                                    • VT = ∑Vt and
                                                                         • ST= ∑St
                                                                                          Z= (TD- Te)/ ST
     Suppose, it is required to compute the probability of
      completing the project within a target duration of TD                Here Z is the number of standard deviations by which TD exceeds Te. Note
      days.                                                                     that TD might be less than Te, in which case Z is negative. Now the
                                                                                probability measure the originally sought may be obtained by referring to
     Now given the Te of the project it is possible to                         the following table, extracted from a standard normal table:
      calculate the deviation of TD from Te in units of
      standard deviation.                                                                Z     Probability of meeting
                                                                                               Due Date
                                                                                                                                      Z     Probability of meeting
                                                                                                                                            Due Date
     This is calculated from the normal distribution table. To                          3.0   .999                                   1.0   .841
      adopt the table, a ratio called the standardised                                   2.8   .997                                   0.8   .788
                                                                                         2.6   .995
      deviation or more often the normal deviate, Z, is                                  2.4   .992
                                                                                                                                      0.6   .726
                                                                                                                                      0.4   .655
      derived. Z is defined as the ratio of the difference in TD                         2.2   .986
                                                                                                                                      0.2   .579
      and Te to ST. Mathematically, Z= (TD- Te)/ ST,                                     2.0   .977
                                                                                                                                      0.0   .500
                                                                                         1.8   .964
                                                                                         1.6   .945
                                                                                         1.4   .919
11/7/2017                        Temesgen G.                       59   11/7/2017                                       Temesgen G.                                  60
                                                                                         1.2   .885
                                                                                                                                                                                                                                                   11/7/2017
                    Z= (TD- Te)/ ST
                                                                                                                                                       Example: PERT Diagram
                       Z          Probability of meeting                      Z      Probability of meeting
                                  Due Date                                           Due Date
-2.0 .023
            Now, the problem of computing the probability                           In other words, the target duration TD is 1.09
             of meeting target duration (TD), such as 42 days                         standard deviations greater than the expected
             shown in the figure is quite simple. Since the                           time TE=36 days.
             total area under the normal curve is exactly one,                       The equivalent probability P(Z=1.09) can be
             the cross hatched area under the normal curve                            read off a normal probability distribution. This
             is directly the probability that the actual                              corresponds to a probability of 0.862
             completion time, will be equal to, or less than,
                                                                                      (86.2%)which implies that there is a 86.2%
             42 days.
                                                                                      chance that the project will get completed
            In this case Z= (TD- TE)/ ST, = (42-36)/ 5.48 =
                                                                                      within 42 days.
             1.09 standard deviations.
11/7/2017                               Temesgen G.                        65   11/7/2017                          Temesgen G.                           66
                                        36       42                                                                36
                                                                                                                   36
                                     Time - days                                                                Time - days
11/7/2017                               Temesgen G.                        67   11/7/2017                          Temesgen G.                           68
                                                                                                                                                                11/7/2017
                     Meeting a Target Duration TD                                              Assuming that time now is zero, one may expect this
                                                                                                project to end at time 36 days (corresponding
                                                                                                probability of achieving this target being 50%,
                                                   0.55 Standard Deviations                     verify!!! Hint: TD=36, TE=36 ); and the probability
                                                                                                that it will end on or before the target duration of 42,
                     P(t  33 days)                                                             without expediting the project is approximately
                      29.1%                                                                    86.2%.
                                                                                               On the other hand, if one were to schedule towards
                                                                                                TD= 33 days; herein TD<TE; i.e. Z=-0.55 (Note the
                                      33   36                                                   negative sign); the corresponding probability would
                                       Time - days
                                                                                                be 0.291, which is really a very bleak situation.
11/7/2017                                  Temesgen G.                        69   11/7/2017                             Temesgen G.                       70
11/7/2017 Temesgen G. 73