ITP Electrical New MCC

This document outlines the inspection and test plan for certifying a motor control center. It details various inspection activities to be performed at the factory and on-site, including design appraisal, factory acceptance testing, pre-commissioning testing, and commissioning testing. Key activities involve visual inspections, wiring checks, function tests, and high potential dielectric tests. The roles of the contractor, client, and regulatory authority are defined for approving, witnessing, reviewing, or being notified of test points. Required documentation includes specifications, drawings, procedures, test records, manuals, and standards.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
270 views3 pages

ITP Electrical New MCC

This document outlines the inspection and test plan for certifying a motor control center. It details various inspection activities to be performed at the factory and on-site, including design appraisal, factory acceptance testing, pre-commissioning testing, and commissioning testing. Key activities involve visual inspections, wiring checks, function tests, and high potential dielectric tests. The roles of the contractor, client, and regulatory authority are defined for approving, witnessing, reviewing, or being notified of test points. Required documentation includes specifications, drawings, procedures, test records, manuals, and standards.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

INSPECTION AND TEST PLAN FOR MOTOR CONTROL CENTER CERTIFICATION

Project : Motor Control Center Certification


Location :
Owner / User :
Contractor :
PJIT :

A : Approve point SW : Spot witness point R : Review point


H : Hold point S : Surveillance or monitor point P : Provide
W : Witness point V : Verify point N/A : Not applicable / involved

ACTIVITY
DESCRIPTION PROCESS DESCRIPTION INSPECTION DOCUMENTS REFERENCE
Cont / User PJIT MIGAS
Pre-Inspection Meeting Inform the client regarding the Certification  Client specifications
S H H
Agencies scope of work.  Applicable code/standard
Design Appraisal  Drawing S R R  Owner Specification
 General Specifications S R R  Code or Standard
 Calculation S R R
Factory Acceptance Test  Identification of Component, Material and S&A1 V H  Procedure
(FAT) Purchasing Order
 Visual inspection S&A1 W W  Owner specification
 Wiring & Continuity Test S&A1 W W
 MCC Construction Check S&A1 W W
 Small dry-type Distribution Transformer for S&A1 W W
controls
 Primary injection voltage test S&A1 W W
 Electrical & mechanical interlock test S&A1 W W
 Function test S&A1 W W
 Check Ground Bus S&A1 W W
 Metering calibration S&A1 W W
 Automatic Transfer switch test (if required) S&A1 W W
 Insulation Resistance Test S&A1 W W
 Relay test S&A1 W W
 DC-Hi-pot test S&A1 W W
 Current & Potential transformer test S&A1 W W
 Current transducer test S&A1 W W
Pre-Commissioning  Verify nameplate of equipment with the data S&A1 V H  Procedure, Drawing
Test, On-site sheet  Code or Standard
DESCRIPTION PROCESS DESCRIPTION INSPECTION ACTIVITY DOCUMENTS REFERENCE
Cont / User PJIT MIGAS
 Check Equipment Layout based on S&A1 W W  Owner Specification
classification area
 Check Instruction Book / Manual Guidance S&A1 R R
 Inspect for physical damages S&A1 W W
 Contact resistance bus S&A1 W W
 Open the cell doors and with the design S&A1 W W
document, check each cell to ensure the
correct component are installed
 Earthing measurement S&A1 W W
 Check each drawer motor starter or feeder S&A1 W W
breaker assembly properly
 Check mechanism door locking and defeat S&A1 W W
functions properly
 Inspect for the tighten bolts S&A1 W W
 Check cleaning on exterior and interior the S&A1 W W
MCC
 Check the cable feeders termination S&A1 W W
 Check the Power cables are properly colour S&A1 W W
coded
 MCC Wiring Test S&A1 W W
 Function Test S&A1 W W
 Relay Test (as required) S&A1 W W
 Insulation Resistance Test S&A1 W W
 DC-Hi-pot Test S&A1 W W
Commissioning Test, Final  Performance Tests S&A W W  Test Sheet Pre-Commissioning
Inspection & Taking of  Test Procedure
Certificate (TOC)
Documents Required:

1. Owner Specification;
2. Plot plan, General Arrangement Drawings;
3. Hazardous area classification;
4. Design Calculation;
5. Test procedures;
6. Manufacturing Data Record (MDR);
7. Operating & Maintenance Manuals (O&M Manuals);
8. Factory Acceptance Test (FAT) Record;
9. Commissioning data record;
10. Pre-commissioning data record;
11. Standard, Code;
12. Manufacture Standard.

Prepared by : Approved by : Reviewed by :

Contractor Client DITJEN MIGAS

( ) ( ) ( )