INSPECTION AND TEST PLAN FOR MOTOR CONTROL CENTER CERTIFICATION
Project : Motor Control Center Certification
Location :
Owner / User :
Contractor :
PJIT :
A : Approve point SW : Spot witness point R : Review point
H : Hold point S : Surveillance or monitor point P : Provide
W : Witness point V : Verify point N/A : Not applicable / involved
ACTIVITY
DESCRIPTION PROCESS DESCRIPTION INSPECTION DOCUMENTS REFERENCE
Cont / User PJIT MIGAS
Pre-Inspection Meeting Inform the client regarding the Certification Client specifications
S H H
Agencies scope of work. Applicable code/standard
Design Appraisal Drawing S R R Owner Specification
General Specifications S R R Code or Standard
Calculation S R R
Factory Acceptance Test Identification of Component, Material and S&A1 V H Procedure
(FAT) Purchasing Order
Visual inspection S&A1 W W Owner specification
Wiring & Continuity Test S&A1 W W
MCC Construction Check S&A1 W W
Small dry-type Distribution Transformer for S&A1 W W
controls
Primary injection voltage test S&A1 W W
Electrical & mechanical interlock test S&A1 W W
Function test S&A1 W W
Check Ground Bus S&A1 W W
Metering calibration S&A1 W W
Automatic Transfer switch test (if required) S&A1 W W
Insulation Resistance Test S&A1 W W
Relay test S&A1 W W
DC-Hi-pot test S&A1 W W
Current & Potential transformer test S&A1 W W
Current transducer test S&A1 W W
Pre-Commissioning Verify nameplate of equipment with the data S&A1 V H Procedure, Drawing
Test, On-site sheet Code or Standard
DESCRIPTION PROCESS DESCRIPTION INSPECTION ACTIVITY DOCUMENTS REFERENCE
Cont / User PJIT MIGAS
Check Equipment Layout based on S&A1 W W Owner Specification
classification area
Check Instruction Book / Manual Guidance S&A1 R R
Inspect for physical damages S&A1 W W
Contact resistance bus S&A1 W W
Open the cell doors and with the design S&A1 W W
document, check each cell to ensure the
correct component are installed
Earthing measurement S&A1 W W
Check each drawer motor starter or feeder S&A1 W W
breaker assembly properly
Check mechanism door locking and defeat S&A1 W W
functions properly
Inspect for the tighten bolts S&A1 W W
Check cleaning on exterior and interior the S&A1 W W
MCC
Check the cable feeders termination S&A1 W W
Check the Power cables are properly colour S&A1 W W
coded
MCC Wiring Test S&A1 W W
Function Test S&A1 W W
Relay Test (as required) S&A1 W W
Insulation Resistance Test S&A1 W W
DC-Hi-pot Test S&A1 W W
Commissioning Test, Final Performance Tests S&A W W Test Sheet Pre-Commissioning
Inspection & Taking of Test Procedure
Certificate (TOC)
Documents Required:
1. Owner Specification;
2. Plot plan, General Arrangement Drawings;
3. Hazardous area classification;
4. Design Calculation;
5. Test procedures;
6. Manufacturing Data Record (MDR);
7. Operating & Maintenance Manuals (O&M Manuals);
8. Factory Acceptance Test (FAT) Record;
9. Commissioning data record;
10. Pre-commissioning data record;
11. Standard, Code;
12. Manufacture Standard.
Prepared by : Approved by : Reviewed by :
Contractor Client DITJEN MIGAS
( ) ( ) ( )