HVAC STATIC PRESSURE TEST
ITR No                 H11B
Item/Tag No.           @T                                 System No.        @S
Item/Tag Description   @D                                 Sub System No.    @SS
Sub System Description      @SSD
Location       @L                                         Print Date        @PD
                                             INFORMATION
Lay Out Drawing
No.      Items to be Checked                                           OK    N/A    Punch List no.
      Ensure that the Ductwork installation is in accordance
  1
      with the current GA Drawing(s) and CCN's are closed out.
      Confirm Mechanical Completion Records are all complete
  2
      and no subsequent damage has occurred.
  3   Ensure all blanks have been removed.
      Ensure all dampers are in the open position i.e. control,
  4
      shut off, manual and fire dampers.
  5   Check that all access hatches are closed.
      Test holes (with sealing covers) in ducting for air flow
  6
      measurements provided.
  7   Preservation removed.
                                       COMMENT(S) / ADDITIONAL INFORMATION:
                                   COMPLETED BY CONTRACTOR                  VERIFIED BY PMT/OWNER
           Designation
Company
Name
Signature
Date