Cost of Projects - Erode

The document outlines the total projected costs in crores for various smart city projects proposed for the city of Erode, India. Projects include canal restoration, amenities along canals, solar lighting, cycling and walking paths, footpaths, market modernization, shelters for migrant workers, water supply networks, sewer systems, storm drains, solid waste management, toilets, street lighting, healthcare centers, education infrastructure, solar power, power distribution, housing, bus stands, bus shelters, underground utilities, parking, road work, signage, staffing, advisory costs, and more. The total projected cost for all projects listed is 1,543.52 crores.

Uploaded by

Jatin Thakkar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views1 page

Cost of Projects - Erode

The document outlines the total projected costs in crores for various smart city projects proposed for the city of Erode, India. Projects include canal restoration, amenities along canals, solar lighting, cycling and walking paths, footpaths, market modernization, shelters for migrant workers, water supply networks, sewer systems, storm drains, solid waste management, toilets, street lighting, healthcare centers, education infrastructure, solar power, power distribution, housing, bus stands, bus shelters, underground utilities, parking, road work, signage, staffing, advisory costs, and more. The total projected cost for all projects listed is 1,543.52 crores.

Uploaded by

Jatin Thakkar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Total SCP Cost (in

City Name S.No Project Crores)


Erode 1 Canal Restoration Perumpattam Canal 250.00
Canal front amenities and recreation facilities including
Smart Censor of pollution measure 15.00
Solar panelled lighting 6.00
NMT Tracks with cycling, walkways, landscaping incr. 9.00
Foot path, Cycle Tracks and landscaping with
greenery (Arterial Roads) 50.00
Foot path, Cycle Tracks and landscaping with
greenery (Other Roads) 33.75
Erode 3 Market Modernisation of Textile hub 50.00
Erode 4 Shelter for Migrantss worker/Homeless 2.50
Erode 5 Water Supply - 210 km distribution network 180.00
Erode 6 Sewerage -Collection & Pumping, TTRO other works 102.00
Erode 7 Storm water drain 17.00
Erode 8 Solid Waste Management 17.56
Access to toilets - individual / community toilets 6.00
Public conveniences / E- Toilets / Mobile Toilets 0.60
Street Lighting Arterial Roads 4.55
Erode Street Lighting Other Roads 5.60
Erode Health care & Primary health centres 120.00
Erode Education-Infrastructure 30.00
Erode Solar Power generation 15.00
Power Distribution - Substations and other
developments 10.00
Erode Power Distribution - Cabling & Others 19.50
Erode Housing for all and Social Infrastructure 36.00
Bus-stand modernisation - Smart components 25.00
Erode Bus shelters (Arterial Roads) 2.60
Providing Underground Utilities (Arterial Roads) 30.00
Erode Providing Underground Utilities (Other Roads) 36.00
Off-street parking and MLCPs (Arterial Roads) 10.00
Erode Street-side parking (Other Roads) 1.13
Road re-surfacing & Signages including lane marking
(Arterial Roads) 20.00
Erode Road re-surfacing & Signages including lane marking 67.50
Erode SPV Staffing/PMU, Project Preparation, Advisory 58.61
Erode A&OE (MOUD) and related 23.45
Erode E-health 250.00
CCTV points- cameras, poles, server, junction switch
& Field component with ANPR,- Especially Traffic
Management 6.00
Other CCTV points - 11.25
Erode Command Centre 3.00
SPV Staffing/PMU, Project Preparation, Advisory 13.51
Erode A&OE (MOUD) and related 5.41
Total 1543.52

Note- This only indicates cost of individual projects given in the SCP. The total value of SCP may additionally include other
costs such as DPR preparation, PMC, O&M etc.