NISHIN METAL CORPORATION
DATE ISSUED : 12 APRIL 2018 SHEET NO. 1
DATE START : 15 MAY 2018 PREPARED BY :
DATE FINISH : 29 JUNE 2018 Construction of NIPPON PREMIUM BAKERY PROJECT Santo Tomas Project Kenneth Bryan M. Umadhay, C.E.
REFERENCE NO. : NN-17-048-8 CHECKED BY :
CLIENT : TPCI LOT 10, BLOCK 2, FPIP II - SEZ, SAN RAFAEL, STO. TOMAS, BATANGAS Chester Mark E. Balisme, C.E.
INDEX
WORK DESCRIPTION MAY 2018 JUNE 2018 JULY 2018 REMARKS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7
I. PROJECT DURATION
(MOBILIZATION)
MOBILIZATION, PREPARATION &
II. (PREPARATION)
MACHINE/MATERIALS DELIVERY
(STAGING)
III. SCOPE OF WORKS BY OTHERS
a Purlin Checking, Alignment & Markings
b Rollforming & Fabrication Works
c Installation of Chicken Wiremesh
d Installation of Clips
Installation of Aluminum Foils &
e
Glasswool Insulations
f Installation of Roof Panels
g Installation of Gutter
Installation of Flashings & Other Bended
h
Accessories
i Installation of Eaves & End Closers
j Installation of Metal Sidings
k Installation of Mouldings
l Housekeeping
n Inspection / Punchlist
NOTE: OFFICE AREA
PRODUCTION AREA A
PRODUCTION AREA B1
PRODUCTION AREA B2