1.0 Remove the intermediate nodes from staad file.
2.0 Change bracing pattern in elevation on grid A & B.
3.0 Assign LY/LZ correctly for these members.
4.0 Plan @ EL 107, to be updted-add cable tray supporting members @ every 2m in transvere direction.
5.0 change marked beam in longitudinal direction to IPEA240, check if it works, As the ration is very less
in UB Members.
6.0 Increase column height @ top tear to accommodate Moment connection bolt & plate-check
connection plate size as per standard drawings.
7.0 Remove releases for this beams.
8.0 Update anchor load -check calculations applied.
9.0 Provide calculation back up for this Load-Also provide basis for 20% increase in load.
10. Calculation back for wind intensities Required.