0% found this document useful (0 votes)
1K views8 pages

Detailed Estimates: Construction of Welcome Arch New Little Baguio, Brgy. Magsaysay, Infanta, Quezon

The document provides a detailed cost estimate for constructing a welcome arch. It is divided into 4 items: 1) excavation and backfilling works, 2) formworks and scaffolding, 3) concrete and reinforcement materials, and 4) precast works. For each item, it lists materials needed and their quantities, equipment required, labor, and calculates direct, indirect and total estimated costs. The total estimated cost for the entire project is provided at the end.

Uploaded by

Airesh Go
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views8 pages

Detailed Estimates: Construction of Welcome Arch New Little Baguio, Brgy. Magsaysay, Infanta, Quezon

The document provides a detailed cost estimate for constructing a welcome arch. It is divided into 4 items: 1) excavation and backfilling works, 2) formworks and scaffolding, 3) concrete and reinforcement materials, and 4) precast works. For each item, it lists materials needed and their quantities, equipment required, labor, and calculates direct, indirect and total estimated costs. The total estimated cost for the entire project is provided at the end.

Uploaded by

Airesh Go
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

DETAILED ESTIMATES

(In Pesos)
NAME OF PROJECT:
CONSTRUCTION OF WELCOME ARCH
NEW LITTLE BAGUIO, BRGY. MAGSAYSAY, INFANTA, QUEZON
ITEM NO. NAME OF ITEM: QUANTITY AND UNIT
I. EXCAVATION & BACKFILLING WORKS 1 Lumpsum

PRICE
NAME AND SPECIFICATIONS OF MATERIALS QTY. UNIT UNIT RATE (P) COST (P)
NO.
1 . Gravel Fill cu.m.
MATERIALS

2 . Backfill Materials cu.m.

TOTAL for MATERIALS


SEQUENCE OF OPERATIONS:

NO. of NO. of HOURLY


NAME, CAPACITY & HP RATING EQUIPMENT COST (P)
EQUIPMENT

UNITS HOURS RATE (P)


1 . Water pump, 2Ɵ
2 . Plate Compactor

TOTAL for EQUIPMENT


NO. OF HOURLY
DESIGNATION OF PERSONNEL NO. COST (P)
HOURS RATE
1 . Excavation Works L.S.
LABOR

2 . Backfilling Works L.S.

TOTAL for LABOR


ESTIMATED DIRECT COST
OVERHEAD CONTINGENCIES & MISC. 12%
CONTRACTOR'S PROFIT 10%
VALUE ADDED TAX 5%
ESTIMATED INDIRECT COST
TOTAL COST

ADJUSTED TOTAL COST

PREPARED BY:

Contractor
DETAILED ESTIMATES
(In Pesos)
NAME OF PROJECT:
CONSTRUCTION OF WELCOME ARCH
NEW LITTLE BAGUIO, BRGY. MAGSAYSAY, INFANTA, QUEZON
ITEM NO. NAME OF ITEM: QUANTITY AND UNIT
II. FORMWORKS & SCAFFOLDING WORKS 1 Lumpsum

PRICE
NAME AND SPECIFICATIONS OF MATERIALS QTY. UNIT UNIT RATE (P) COST (P)
NO.
1 . 4' x 8' x 1/2" Ordinary Marine Plywood pc.
2 . 2" x 2" x 12' Good Lumber pc.
MATERIALS

3 . 2" x 3" x 12' Good Lumber pc.


4 . 2" x 3" x 12' Coco Lumber pc.
5 . 2" x 4" x 12' Coco Lumber pc.
6 . 2" x 6" x 12' Coco Lumber pc.
7 . Assorted CW Nails kg.

TOTAL for MATERIALS


SEQUENCE OF OPERATIONS:

NO. of NO. of HOURLY


NAME, CAPACITY & HP RATING EQUIPMENT COST (P)
EQUIPMENT

UNITS HOURS RATE (P)

TOTAL for EQUIPMENT -


NO. OF HOURLY
DESIGNATION OF PERSONNEL NO. COST (P)
HOURS RATE
LABOR

1 . Labor (30%) 1 L.S.

TOTAL for LABOR


ESTIMATED DIRECT COST
OVERHEAD CONTINGENCIES & MISC. 12%
CONTRACTOR'S PROFIT 10%
VALUE ADDED TAX 5%
ESTIMATED INDIRECT COST
TOTAL COST

ADJUSTED TOTAL COST

PREPARED BY:

Contractor
DETAILED ESTIMATES
(In Pesos)
NAME OF PROJECT:
CONSTRUCTION OF WELCOME ARCH
NEW LITTLE BAGUIO, BRGY. MAGSAYSAY, INFANTA, QUEZON
ITEM NO. NAME OF ITEM: QUANTITY AND UNIT
III. CONCRETE AND REINFORCEMENT OF MATERIALS 16.9 cu.m.

PRICE
NAME AND SPECIFICATIONS OF MATERIALS QTY. UNIT UNIT RATE (P) COST (P)
NO.
1 . Portland Cement, Type 1 bag
2 . Washed Sand, S1 cu.m.
3 . Screened Gravel, G1 cu.m.
4 . Screened Gravel, 3/4 cu.m.
MATERIALS

5 . 20mm dia. x 9m Deformed Bar pc,


6 . 20mm dia. x 7.5m Deformed Bar pc,
7 . 20mm dia. x 6m Deformed Bar pc,
8 . 16mm dia. x 9m Deformed Bar pc,
9 . 16mm dia. x 7.5m Deformed Bar pc,
10 . 16mm dia. x 6m Deformed Bar pc,
11 . 10mm dia. x 6m Deformed Bar pc,
12 . G.I. Tie Wire, #16 kgs.

TOTAL for MATERIALS


SEQUENCE OF OPERATIONS:

NO. of NO. of HOURLY


NAME, CAPACITY & HP RATING EQUIPMENT COST (P)
EQUIPMENT

UNITS HOURS RATE (P)


1 . Concrete Bagger Mixer
2 . Concrete Vibrator

TOTAL for EQUIPMENT


NO. OF HOURLY
DESIGNATION OF PERSONNEL NO. COST (P)
HOURS RATE
LABOR

1 . Labor (30%) 1 L.S.

TOTAL for LABOR


ESTIMATED DIRECT COST
OVERHEAD CONTINGENCIES & MISC. 12%
CONTRACTOR'S PROFIT 10%
VALUE ADDED TAX 5%
ESTIMATED INDIRECT COST
TOTAL COST
UNIT PER CU.M.
ADJUSTED TOTAL COST

PREPARED BY:

Contractor
DETAILED ESTIMATES
(In Pesos)
NAME OF PROJECT:
CONSTRUCTION OF WELCOME ARCH
NEW LITTLE BAGUIO, BRGY. MAGSAYSAY, INFANTA, QUEZON
ITEM NO. NAME OF ITEM: QUANTITY AND UNIT
IV. PRECAST WORKS 1 Lumpsum

PRICE
NAME AND SPECIFICATIONS OF MATERIALS QTY. UNIT UNIT RATE (P) COST (P)
NO.
1 . Portland Cement, Type 1 bag
2 . Base Moulding m
3 . Mid Moulding m
4 . Bead Moulding m
MATERIALS

5 . Capital Moulding pc.


6 . Top Moulding m
7 . Bottom Moulding m
8 . Precast Panel with Groove m
9 . Bracket pc.
10 . Diamond pc.
11 . Keystone pc.
12 . Deco-Urn pc.
13 . Logo pc.
14 . CHB 5" pc.
TOTAL for MATERIALS
SEQUENCE OF OPERATIONS:

NO. of NO. of HOURLY


EQUIPMENT

NAME, CAPACITY & HP RATING EQUIPMENT COST (P)


UNITS HOURS RATE (P)
1 Electric Grinder

TOTAL for EQUIPMENT


NO. OF HOURLY
DESIGNATION OF PERSONNEL NO. COST (P)
HOURS RATE
LABOR

1 . Labor (30%) 1 L.S.

TOTAL for LABOR


ESTIMATED DIRECT COST
OVERHEAD CONTINGENCIES & MISC. 12%
CONTRACTOR'S PROFIT 10%
VALUE ADDED TAX 5%
ESTIMATED INDIRECT COST
TOTAL COST
UNIT PER
ADJUSTED TOTAL COST

PREPARED BY:

Contractor
DETAILED ESTIMATES
(In Pesos)
NAME OF PROJECT:
CONSTRUCTION OF WELCOME ARCH
NEW LITTLE BAGUIO, BRGY. MAGSAYSAY, INFANTA, QUEZON
ITEM NO. NAME OF ITEM: QUANTITY AND UNIT
V. MASONRY WORKS & MARKER INSTALLATION 1 Lumpsum

PRICE
NAME AND SPECIFICATIONS OF MATERIALS QTY. UNIT UNIT RATE (P) COST (P)
NO.
1 . Stainless Lettering pc.
2 . Memoravilla pc.
3 . Natural Stone sq.m.
MATERIALS

TOTAL for MATERIALS


SEQUENCE OF OPERATIONS:

NO. of NO. of HOURLY


EQUIPMENT

NAME, CAPACITY & HP RATING EQUIPMENT COST (P)


UNITS HOURS RATE (P)

TOTAL for EQUIPMENT -


NO. OF HOURLY
DESIGNATION OF PERSONNEL NO. COST (P)
HOURS RATE
LABOR

1 . Labor (30%) 1 L.S.

TOTAL for LABOR


ESTIMATED DIRECT COST
OVERHEAD CONTINGENCIES & MISC. 12%
CONTRACTOR'S PROFIT 10%
VALUE ADDED TAX 5%
ESTIMATED INDIRECT COST
TOTAL COST
UNIT PER
ADJUSTED TOTAL COST

PREPARED BY:

Contractor
DETAILED ESTIMATES
(In Pesos)
NAME OF PROJECT:
CONSTRUCTION OF WELCOME ARCH
NEW LITTLE BAGUIO, BRGY. MAGSAYSAY, INFANTA, QUEZON
ITEM NO. NAME OF ITEM: QUANTITY AND UNIT
VI. PAINTING WORKS 1 Lumpsum

PRICE
NAME AND SPECIFICATIONS OF MATERIALS QTY. UNIT UNIT RATE (P)
NO.
1 . Flat Latex Paint gal.
2 . Semi-Gloss Latex Paint gal.
MATERIALS

3 . Patching Compound kg.


4 . Masonry Neutralizer lits.
5 . Paint Roller Brush pcs.
6 . Paint Brush pcs.
7 . Sanding Paper pcs.
8 . Acrylic Emulsion Paint gal.

TOTAL for MATERIALS


SEQUENCE OF OPERATIONS:

NO. of NO. of HOURLY


NAME, CAPACITY & HP RATING EQUIPMENT
EQUIPMENT

UNITS HOURS RATE (P)

TOTAL for EQUIPMENT


NO. OF HOURLY
DESIGNATION OF PERSONNEL NO.
HOURS RATE
LABOR

1 . Labor(35%) L.S.

TOTAL for LABOR


ESTIMATED DIRECT COST
OVERHEAD CONTINGENCIES & MISC. 12%
CONTRACTOR'S PROFIT 10%
VALUE ADDED TAX 5%
ESTIMATED INDIRECT COST
TOTAL COST
UNIT PER
ADJUSTED TOTAL COST

PREPARED BY:

Contractor
DETAILED ESTIMATES
(In Pesos)
NAME OF PROJECT:
CONSTRUCTION OF WELCOME ARCH
NEW LITTLE BAGUIO, BRGY. MAGSAYSAY, INFANTA, QUEZON
ITEM NO. NAME OF ITEM: QUANTITY AND UNIT
VII. INFORMATIVE SIGNBOARD 1 Lumpsum

PRICE
NAME AND SPECIFICATIONS OF MATERIALS QTY. UNIT UNIT RATE (P) COST (P)
NO.
1 . Signboard lot
MATERIALS

SEQUENCE OF OPERATIONS:

NO. of NO. of HOURLY


NAME, CAPACITY & HP RATING EQUIPMENT
EQUIPMENT

UNITS HOURS RATE (P)

TOTAL for EQUIPMENT


NO. OF HOURLY
DESIGNATION OF PERSONNEL NO.
HOURS RATE
LABOR

1 Labor L.S.

TOTAL for LABOR


ESTIMATED DIRECT COST
OVERHEAD CONTINGENCIES & MISC. 12%
CONTRACTOR'S PROFIT 10%
VALUE ADDED TAX 5%
ESTIMATED INDIRECT COST
TOTAL COST
UNIT PER
ADJUSTED TOTAL COST

PREPARED BY:

Contractor

You might also like