MURK 7 Metric
(06/08) English
DAILY WORK REPORT - STRUCTURAL STEEL PAINTING: FIELD APPLIED
JOB STAMP
Date:
Day of Week: S M T W T F S
Sheet No. of DWR No.
CONTRACTOR WORK HOURS: TO
DESCRIPTION OF WORK AND MATERIAL USED FOR EACH OPERATION, INCLUDING CONTRACTOR/SUB NAME, ITEM NO. AND LOCATION
WEATHER & ATMOSPHERIC CONDITIONS*
WORK OPERATION TIME AIR TEMP STEEL TEMP DEW POINT % HUMIDITY PAINT TEMP (FROM STORAGE)
*VALUES SHALL BE MEASURED AND RECORDED JUST PRIOR TO WORK OPERATIONS
SURFACE PREPARATION
PRESSURE WASHING ABRASIVE BLASTING
OPERATING PRESSURE START TIME END TIME AREA BLASTED # OF NOZZLES SUPPLY HOSE LENGTH
(m ²) PRESSURE(kPa) (m)
FLOW RATE
WATER TEMPERATURE
WATER SOURCE
ABRASIVE STEEL GRIT CLEANLINESS - SSPC AB2 - TOTAL REMOVAL ONLY
ABRASIVE MIX NON-ABRASIVE RESIDUE TEST (% BY WT. OF WORK MIX SAMPLE)
ABRASIVE ADDED
(AMOUNT & TYPE) WATER-SOLUABLE CONTAMINANTS (microns/cm - ASTM D4940)
CLEANING STANDARD VERIFIED OIL CONTENT VISIBLE? YES NO
(§573-03.02C & § 574-03.02C)
BLAST PROFILE - ATTACH ADDITIONAL LEAD CONTENT (% BY WEIGHT- WEEKLY TEST)
PROFILE DATA IF NECESSARY
MEASUREMENT PROFILE CONDITION BEFORE & AFTER SURFACE PREP - SSPC VIS 1 OR VIS 3
LOCATIONS (ATTACH REPLICA TAPE)
CONDITION BEFORE SURFACE PREP A B C D E F G1 G2 G3
CONDITION AFTER SURFACE PREP SP10 SP11 UNACCEPTABLE
CONTRACT INTERIM FINAL QTY CEES
FS ES QUANTITY UNITS QUANTITY CHK LOCATION OF WORK ENT CHK
PAY ITEM NO
I certify that the work described in this report was incorporated into this contract on the date of this DWR, unless otherwise noted.
Inspector's Signature: Date Prepared:
Engineer-in-Charge
Reviewed by: Date Reviewed:
Resident Engineer
MURK 7-1 CONTINUATION attached for additional DFT measurements MURK 1-1 CONTINUATION attached for additional narrative.
MURK 7 REVERSE
(04/08)
COATING
MANUFACTURE THINNER RESULTANT SPECIFIED SPECIFIED
NAME OF PAINT BATCH NUMBER AMOUNT
MM/DD/YYYY USED VOC LEVEL* DFT RANGE* PROFILE*
USED (L)
* FROM MANUFACTURER'S TECHNICAL DATA SHEETS
DRY FILM THICKNESS (DFT) - SSPC PA-2
DRY FILM THICKNESS GAUGE CALIBRATED DAILY PRIOR TO TAKING MEASUREMENTS? YES NO
LOCATION OF AREA MEASURED:
DFT FOR PREVIOUS COAT(S) RECORDED IN APPLICATION AREA:
GAUGE READINGS SPOT MEASUREMENT AVERAGE OF SPOT MEASUREMENTS
LABOR EQUIPMENT
CLASSIFICATION OP 1 OP 2 OP 3 OP 4 TYPE ID # OP 1 OP 2 OP 3 OP 4
FOREPERSON
PAINTERS
LABORER
EQUIP OPERATOR
TRUCK DRIVERS
OWNER OPERATORS
OP 1: OP 2: OP 3: OP 4:
Print Form