Parsons Document Number EGP3-07-SP-040-403-030
CHEVRON NIGERIA LIMITED
      ESCRAVOS GAS PROJECT – PHASE 3 DEVELOPMENT - ONSHORE
                       SPECIFICATION NUMBER EGP3–02.01
                            CATHODIC PROTECTION
REV             DATE               REVISION                BY      CL/APPR
 0         Oct. 24,2002          Issued for ITB            EJ
 1      January 22, 2004        Revised for ITB3           RBM      DAP
January, 2004                   Specification EGP3-02.01              1 OF 30
                                    REVISION RECORD SHEET
Notes
i.) Revisions numbers shall be A, B, C, etc. up through the issue for Invitation to Bid.
ii.) The issue for Invitation to Bid shall be Revision 0.
iii.) Revisions after the issue for Invitation to Bid shall be 1, 2, 3, etc. Any revisions made after
      Revision 0 shall be denoted by a vertical line in the left hand margin against the revised text.
iv.) A brief description of the key changes made in each revision shall be included on this page.
 REVISION         DESCRIPTION OF REVISION
 A                Based on Chevron Specification 02.01
 B                   Updated for EGP3 standards and definitions.
                     Removed cathodic protection for piles thoughout spec
                     Changed from zone to division type area classification.
                     Changed oil filled transformers to dry type.
                     Issued for Parsons Review/CNL Review and Comments
 0                Issued for ITB
 1                Revised for ITB3 – no changes
January, 2004                          Specification EGP3-02.01                              2 OF 30
                                   TABLE OF CONTENTS
                                                                   PAGE
1.0    SCOPE & DEFINITIONS                                             6
       1.1      Scope                                                  6
       1.2      Definitions                                            6
2.0    REFERENCES                                                      6
       2.1      Industry Codes                                         6
       2.2      Project Specifications                                 7
       2.3      Standard Drawings                                      7
3.0    RESPONSIBILITIES AND PRECEDENCE                                 8
       3.1      Responsibilities                                       8
       3.2      Precedence                                             8
4.0    GENERAL DESIGN PHILOSOPHY                                       8
       4.1      General                                                8
       4.2      Protection Method                                      9
       4.3      Temporary Protection                                  10
       4.4      Protection Criteria                                   11
5.0    SURVEYS                                                        12
       5.1      General                                               12
       5.2      Soil Surveys                                          12
       5.3      Water Circulation and Storage Systems                 13
6.0    DESIGN CONSIDERATIONS                                          14
       6.1      Electrical Isolation                                  14
       6.2      Design of Electrical Isolation for Pipework           14
January, 2004                         Specification EGP3-02.01   3 OF 30
       6.3      Continuity                                           15
       6.4      Monitoring Facilities                                15
7.0    ELECTRICAL CABLING AND CONNECTIONS                            17
       7.1      Cable Requirements                                   17
       7.2      Junction Boxes                                       18
       7.3      Cable Connection Requirements                        18
8.0    SPECIFIC REQUIREMENTS FOR IMPRESSED CURRENT SYSTEMS           19
       8.1      Anodes                                               19
       8.2      Backfill Material                                    20
       8.3      Transformer-Rectifiers                               20
       8.4      Installation Requirements                            21
9.0    SPECIFIC REQUIREMENTS FOR SACRIFICIAL ANODE SYSTEMS           22
       9.1      Anodes                                               22
       9.2      Installation                                         23
10.0   AVOIDANCE OF ELECTRICAL INTERFERENCE AFFECTS                  24
11.0   INSPECTION AND TESTING OF EQUIPMENT                           24
       11.1     General                                              24
       11.2     Impressed Current Anodes                             24
       11.3     Sacrificial Anodes                                   25
       11.4     Transformer – Rectifiers                             25
       11.5     Isolation Joints                                     25
       11.6     Cabling                                              26
       11.7     Junction Boxes and Surge Arrestors                   26
12.0   SITE ACCEPTANCE TESTING AND COMMISSIONING                     26
       12.1     General                                              26
January, 2004                        Specification EGP3-02.01   4 OF 30
       12.2     Transformer – Rectifiers                            26
       12.3     Isolation Joints                                    26
       12.4     Cable Connections                                   27
       12.5     Pipe Sleeves                                        27
       12.6     Buried Structures                                   27
13.0   DOCUMENTATION                                                28
       13.1     Design Specification                                28
       13.2     Installation and Commissioning Procedures           30
       13.3     Operating and Maintenance Manuals                   30
January, 2004                       Specification EGP3-02.01   5 OF 30
1.0    SCOPE & DEFINITIONS
       1.1      Scope
                The purpose of this Engineering standard is to define the minimum requirements
                for the design, manufacturing, inspection, testing, installation and commissioning
                of the cathodic protection systems for the ESCRAVOS Gas EGP3 Project.
                This Engineering Standard covers the following items:
          ● All direct buried or immersed metallic pipework
          ● All direct buried metallic vessels and tanks
          ● All above ground, storage tank base plates in direct contact with backfill materials
          ● Internal surfaces of water tanks
                Exceptions to the scope on the basis of high soil resistivities or other factors that
                indicate corrosion rates would be minimal, and/or cathodic protection would not
                be economical, and alternative corrosion protection systems would provide
                adequate life shall be subject to COMPANY review and approval on a case-by-
                case basis.
                CONTRACTOR shall notify COMPANY of any conflicts between this specification
                and other project documents or referenced industry standards.
       1.2      Definitions
                Definitions used in this specification are as follows:
                "COMPANY" is defined as CNL
                "CONTRACTOR" is defined as EPC Contractor
                "SUPPLIER or SUB-CONTRACTOR" is defined as companies supplying material,
                equipment or services to the CONTRACTOR.
                "FEED CONTRACTOR" is defined as Parsons
                "PROJECT" is defined as the EGP3 Onshore Project
2.0    REFERENCES
       The following documents are hereby referenced and are considered part of this
       specification:
       2.1      Industry Codes
                NACE RP0169            Control of External Corrosion on           Underground      or
                                       Submerged Metallic Piping Systems
January, 2004                         Specification EGP3-02.01                              6 OF 30
                NACE RP0177          Mitigation of Alternating Current and Lightning Effects on
                                     Metallic Structures and Corrosion Control Systems
                NACE RP0193          External Cathodic Protection of On-Grade Metallic Storage
                                     Tank Bottoms.
                NACE RP0196          Galvanic Anode Cathodic Protection of Internal
                                     Submerged Surfaces of Steel Water Storage Tanks
                NACE RP0285          Corrosion Control of Underground Storage Tank Systems
                                     by Cathodic Protection
                NACE RP0286          The Electrical Isolation of Cathodically Protected Pipelines
                NACE RP0388          Impressed Current Cathodic Protection of Internal
                                     Submerged Surfaces of Steel Water Storage Tanks
                NACE RP0572          Design, Installation, Operation and        Maintenance    of
                                     Impressed Current Deep Groundbeds
                ASTM B265            Standard Specification for Titanium and Titanium Alloy
                                     Strip, Sheet and Plate.
                API RP0651           Cathodic Protection of Aboveground Petroleum Storage
                                     Tanks.
                API RP1632           Cathodic Protection of Underground Petroleum Storage
                                     Tanks and Piping Systems.EGP3-12.01     General
                                     Electrical
       2.2      Project Specifications
                EGP3-12.01 “General Electrical Specification”
                EGP3-12.16 “DC Supply”
                EGP3-12.13.1 “Wire and Cable”
                EGP3-15.00 “Loss Prevention Design Basis”
       2.3      Standard Drawings
                Not applicable
January, 2004                        Specification EGP3-02.01                            7 OF 30
3.0    RESPONSIBILITIES AND PRECEDENCE
       3.1      Responsibilities
                CONTRACTOR shall be responsible for verifying the final scope of cathodic
                protection and for the final detailed design in accordance with the requirements
                of this Engineering Standard and industry codes and standards. CONTRACTOR
                shall identify all metallic, direct buried pipes and pipelines where failure would
                result in risk to health, safety or the environment and/or plant operability and
                submit a detailed scope for COMPANY review and approval. As a minimum, all
                hydrocarbon and closed drains shall be included.
                CONTRACTOR shall ensure that the requirements specified herein are
                incorporated into any procurement specifications, material or sub-contract
                requisitions and/or other purchase documentation produced by, or on behalf of,
                CONTRACTOR.
       3.2      Precedence
                Any conflict between this Engineering Standard, other COMPANY
                documentation, industry codes and standards and local regulations shall be
                referred to COMPANY for clarification prior to proceeding.
                Any deviations to the requirements of this Engineering Standard shall be subject
                to COMPANY review and approval before proceeding.
4.0    GENERAL DESIGN PHILOSOPHY
       4.1      General
                4.1.1    The cathodic protection system shall be designed in accordance with the
                         requirements of this Engineering Standard and the applicable sections of
                         the following:
                             Component                            Referenced Standards(1)(2)
             Onshore buried pipework                      NACE RP0169, NACE RP0177, BS
                                                          7361, Pt.1
             Onshore buried vessels and tanks             NACE RP0285,           API    RP1632,
                                                          BS7361, Pt.1
             Internals of water storage tanks             NACE RP0196
             Aboveground, storage tank base plates        NACE RP0193, API RP651
                Notes:
                1.       Standards and other documents referenced within the text of the above
                         standards shall also apply to the design of the cathodic protection system
                         as applicable and shall form part of the CONTRACTOR’s design
                         submission for COMPANY review and approval.
January, 2004                          Specification EGP3-02.01                                8 OF 30
                2.      Where the text of the above referenced standards uses the word ”should”,
                        this shall be replaced by “shall” to indicate a mandatory requirement. Any
                        deviation to this shall be subject to COMPANY review and approval.
                4.1.2   The cathodic protection system shall be designed to protect each of the
                        structures in paragraph 4.1.1 continuously for a minimum period of 30
                        years.
                4.1.3   CONTRACTOR shall ensure that the design of the cathodic protection
                        system is performed by a competent, experienced person, holding
                        certification by NACE International as a Cathodic Protection Specialist, or
                        equivalent national or international certification. CONTRACTOR shall
                        submit such evidence to COMPANY for review.
                4.1.4   Equipment and materials shall be selected, designed and manufactured
                        for continual operation under the applicable site conditions.
                        CONTRACTOR shall ensure that due consideration is taken of the
                        tropical, marine environment with potentially corrosive saline conditions,
                        in the design and specification of the cathodic protection system.
                4.1.5   CONTRACTOR shall ensure that the impact of the electrical grounding
                        system is included in the design of the cathodic protection system.
                        Positioning of electrical ground rods in the immediate vicinity of
                        cathodically protected structures should be minimized as much as
                        possible. Ground rods that will be electrically continuous with a cathodic
                        protected structure shall be hot-dipped galvanized steel.
                4.1.6   Unless otherwise agreed with COMPANY, the following shall apply:
                        ● For cathodic protection of above ground storage tank base plates,
                           10% of the base plate area shall be considered to have no external
                           coating to allow for coating damage during base plate installation and
                           welding. The operating temperature of the tank shall determine the
                           appropriate current density to be used.
                        ● For cathodic protection of other buried structures, the calculated
                           current requirement shall be increased by an additional 25% to allow
                           for current leakage
                        ● For cathodic protection of the internal surface of water tanks and
                           vessels, the anode sizing and number shall satisfy both the weight
                           requirement to achieve the design life and the current requirement
                           (i.e. the current demand necessary to achieve and maintain
                           protection).
       4.2      Protection Method
                4.2.1   An impressed current system shall be designed and installed for the
                        following:-
                        ● Buried metallic vessels and tanks
January, 2004                         Specification EGP3-02.01                            9 OF 30
                        ● Aboveground storage tank bottom plates; firewater and condensate
                           storage tanks, as a minimum, shall be included unless the tank is
                           constructed on a concrete pad. Anodes and header cables shall be
                           installed during the construction of the foundation. Use the largest
                           depth of clean “washed” sand fill as practical - allowing anodes to be
                           placed farther from the tank bottom and requiring fewer anodes. Sand
                           shall be considered “clean” if testing shows that it has a maximum of
                           50 ppm of chlorides.
                4.2.2   As an exception to the above requirements, sacrificial anodes may be
                        permitted for the following, subject to COMPANY review and approval:
                        ● Buried metallic vessels and tanks
                        ● Short, buried sections of normally aboveground metallic pipework,
                           such as at road crossings, piping through bund walls etc.
                        ● To locally supplement impressed current systems in areas of shielding
                           or current drainage
                4.2.3   Sacrificial anodes shall be installed for the following. The use of an
                        impressed current system in these instances shall be subject to
                        COMPANY review and approval:-
                        ● The internal surfaces of the firewater tank
                        ● The internal surfaces of sumps and other vessels which will contain
                           water
                        ● Coated metallic buried or immersed pipework
                4.2.4   The number, location, and type of anodes shall be sufficient to ensure the
                        required current density is applied in a uniform manner throughout the
                        structure under protection. Details of all positions where anodes are
                        placed shall be indicated on drawings and submitted for COMPANY
                        review.
                4.2.5   The use of more specialized cathodic protection techniques shall be
                        subject to COMPANY review and approval.
       4.3      Temporary Protection
                4.3.1   Temporary cathodic protection is required for impressed current systems
                        when the period between installation and commissioning of the system
                        exceeds six months and may be obtained either by installing temporary
                        power to the transformer-rectifier and gradually energizing the impressed
                        current system or by installation of temporary sacrificial anodes.
                4.3.2   CONTRACTOR shall advise COMPANY of its proposed method of
                        temporary protection and ensure that suitable provision is made for the
                        installation, operation, and monitoring of this temporary protection prior to
                        commissioning of the permanent impressed current system. The facility
January, 2004                         Specification EGP3-02.01                             10 OF 30
                          for final isolation of temporary sacrificial anodes shall be provided.
       4.4       Protection Criteria
                 4.4.1    CONTRACTOR shall advise COMPANY of the protection potentials,
                          coating breakdown factors, and current densities used for the design of
                          the cathodic protection systems. The values shall take into account
                          metallurgy, protective coatings applied, process conditions, and the
                          surrounding environment.
                 4.4.2    The cathodic protection systems shall be designed so that the measured
                          structure-to-electrolyte potentials fall within the following recommended
                          ranges:-
                    Application/ Environment             Protection    Protection         Reference
                                                         Potential     Potential
                                                         Less –ve      Most –ve               Cell
                                                           (mV)          (mV)
             Onshore, aerated                                                             Cu/CuSO4
                                                           -850          -1200
                                                                                         (instant “off”)
             Onshore, anaerobic                                                           Cu/CuSO4
                                                           -950          -1200
                                                                                         (instant “off”)
             Aerated raw water, firewater                                                 Cu/CuSO4
                                                           -850          -1200
                                                                                         (instant “off”)
          Notes:-
             1. The above values are based upon protection of iron and steel materials.
             2. CONTRACTOR shall check the values against the coating systems chosen and
                submit for COMPANY review.
                 4.4.3    The following current density values are the minimum recommended
                          values for design of cathodic protection systems for buried or immersed
                          metallic pipework, vessels, internal surfaces of water tanks,       and
                          aboveground storage tank bottom plates:
                                    Protective Coating                     Minimum
                                                                       Current Density
                                                                           (mA/m2)
                     Bare Steel                                               20
                     3 layer Polyethylene (PE)
                                                                             0.01
                     3 layer Polypropylene (PP)
                     Fusion bonded epoxy (FBE)
                     Liquid applied epoxy
                                                                              0.1
                     Polyurethane
                     Coal tar enamel
                     Bitumen                                                  0.3
January, 2004                               Specification EGP3-02.01                                  11 OF 30
                                 Protective Coating                  Minimum
                                                                  Current Density
                                                                     (mA/m2)
                    Tape wrap
          Notes:-
                1. The above values of current density do not account for coating breakdown
                   during the design life.
                2. CONTRACTOR shall check minimum values against the coating systems
                   chosen and soil resistivity and submit for COMPANY review.
                4.4.4   For marine steel structures, coating breakdown factors and current
                        densities shall be per DNV RP B401. CONTRACTOR shall clearly
                        specify coating breakdown factors and the initial, mean, and final current
                        density values and submit for COMPANY review and approval.
                4.4.5   CONTRACTOR may recommend lower values of current density where
                        they are supported by established data from systems of similar design,
                        coating system, and environment, and offer economic advantage in the
                        design. Any recommended values shall be submitted to COMPANY for
                        review and approval.
                4.4.6   CONTRACTOR shall handle and install materials in such a manner that
                        coating damage is minimized. CONTRACTOR shall ensure that any
                        anticipated coating damage because of handling and installation is
                        included in the design of the cathodic protection system as bare metal
                        surface.
5.0    SURVEYS
       5.1      General
                CONTRACTOR shall perform surveys in those areas where the protected
                structures and cathodic protection systems are to be situated.
                The surveys shall be performed such that the most severe environmental,
                seasonal, and tidal conditions are accounted for.
       5.2      Soil Surveys
                5.2.1   For buried equipment and aboveground storage tanks, the soil surveys
                        shall be performed per ASTM G57, and include the following
                        measurements as a minimum:
                        ● Soil resistivity
                        ● Soil pH
                        ● Soil chloride levels
January, 2004                          Specification EGP3-02.01                         12 OF 30
                ● Soil sulfate levels
January, 2004                 Specification EGP3-02.01   13 OF 30
                5.2.2   CONTRACTOR shall conduct soil surveys over a representative sample
                        of the anode installation locations. If a remote surface anode bed design
                        is proposed, soil surveys at 10m intervals over the full length of the
                        proposed location shall be performed.
                5.2.3   For aboveground storage tanks that have a flexible membrane installed
                        as part of the foundation design, resistivity measurements of the sand
                        foundation fill shall be performed to support calculations regarding
                        impressed current systems. CONTRACTOR shall ensure that these
                        resistivity measurements are performed sufficiently well in advance of the
                        installation of the foundation fill to permit design of the impressed current
                        system and shall be re-confirmed once the cathodic protection system is
                        installed and the foundation backfilled but prior to installation of the tank
                        base plates.
                5.2.4   Resistivity measurements shall be made using a non-contact
                        electromagnetic instrument (e.g. Geonics), to a depth commensurate with
                        the burial depth, for soil resistivities in excess of 1000 ohm-cm and the
                        Wenner 4-pin method for soil resistivities of 1000 ohm-cm or less.
                5.2.5   Where it is suspected that conditions may support microbial activity, then
                        the design should be based upon anaerobic conditions. In this case,
                        further detailed investigation is not required. Any further soil investigations
                        to justify a design based upon aerobic conditions (no microbial activity)
                        shall be subject to COMPANY review and approval.
                5.2.6   Any specialized soil surveys that may be required shall be performed by a
                        specialist SUB-CONTRACTOR, appointed by CONTRACTOR and
                        subject to COMPANY review and approval. The appointed specialist
                        shall define and supervise any necessary measurements to assess the
                        nature and likelihood of the particular concern. Specialized surveys
                        include investigation of the likelihood and effect of microbial activity and
                        soil conditions that may contribute to the deterioration of concrete. These
                        surveys may include measurement of in-situ soil redox potentials,
                        sulphates, sulphides, carbonate, total dissolved solids, and dissolved
                        oxygen content.
                5.2.7   CONTRACTOR shall ensure that any changes to the soil conditions in the
                        areas subject to survey are accounted for in determining the
                        measurements.
       5.3      Water Circulation and Storage Systems
                For onshore water based systems, water samples shall be taken to measure the
                following as a minimum:
                ● Conductivity
                ● Dissolved oxygen content
                ● pH
January, 2004                          Specification EGP3-02.01                             14 OF 30
6.0    DESIGN CONSIDERATIONS
       6.1      Electrical Isolation
                6.1.1   Installation of isolating devices shall be minimized within the plant
                        facilities due to the risk of arcing and interference problems and shall only
                        be installed where necessary to limit flow of current from cathodically
                        protected structures. Isolating devices shall not be installed in Class 1,
                        Division 1 hazardous areas.
                6.1.2   Electrical isolation shall be achieved by use of either monobloc isolating
                        joints, isolating spools, or isolating flanges in accordance with NACE
                        RP0286, and the rules described here within. Pre-assembled and pre-
                        tested joints should be provided where possible. Any work involving
                        electrical connections should be performed with the cathodic protection
                        power source turned off.
                6.1.3   CONTRACTOR shall review the need for electrical isolation at the
                        following locations in its design submission:
                        ● Between buried pipework or equipment and aboveground pipework or
                           equipment
                        ● Between buried pipework and equipment with different external
                           protective coatings
                        ● Between aboveground storage tank nozzles and aboveground
                           pipework
                        ● At the connection to structures protected by a separate cathodic
                           protection system
                        ● Electrical and instrument cable conduit and/or cable armour or lead
                           sheathing
                        ● Reinforcing steel in concrete
                        ● Steel casings at road crossings
                        ● Steel supports
                        ● Electrical earthing systems
                6.1.4   There may be circumstances where the isolation requirements above
                        may not apply. CONTRACTOR shall clearly define where electrical
                        isolation is to be applied.
       6.2      Design of Electrical Isolation for Pipework
                6.2.1   Isolating joints/flanges shall not be direct buried, but shall be installed
                        either aboveground or in a dry inspection pit, for ease of inspection and
                        maintenance.
January, 2004                          Specification EGP3-02.01                            15 OF 30
                6.2.2   High voltage protection shall be provided by installing zinc earthing cells
                        across isolating joints. These shall be included where there is a risk that
                        the protected structures offer a path for high voltages, sources of which
                        include; local power systems, risk of lightening strikes, and process fluid
                        static build up.
                6.2.3   All isolation flanges shall have non-metallic flange covers to protect
                        against ingress of dirt and moisture. The covers shall be of a contrasting
                        color and include a suitable warning sign to identify it as a cathodic
                        protection isolation joint.
                6.2.4   All isolation joints shall be provided with test stations. These may include
                        bond boxes and/or resistive bonds depending on the purpose of the joint.
       6.3      Continuity
                6.3.1   Bonding connections shall be used as far as practicable to interconnect
                        isolated metallic structures within the scope of a given cathodic protection
                        system.
                6.3.2   Bonds shall be applied across all non-welded joints to ensure electrical
                        continuity of pipes and pipelines.
                6.3.3   Bond boxes shall be provided between parallel underground pipelines.
                6.3.4   Bond boxes shall be provided between adjacent structures with separate
                        cathodically protected systems.
                6.3.5   Bond boxes shall also be provided at isolation joints that are used for
                        separation of adjacent cathodic protection systems or in the management
                        of interference effects.
       6.4      Monitoring Facilities
                6.4.1   Permanent potential test boxes shall be installed at the following
                        locations, as a minimum, to verify the effectiveness of the cathodic
                        protection system:
                        ● Locations as defined in paragraph 4.5 of NACE RP0169
                        ● Every 500m (or less) for on-plot buried pipework
                        ● At each buried vessel or tank
                        ● At each aboveground storage tank
                        ● At each water tank, if internally cathodically protected
                6.4.2   Permanent test points shall be installed at each isolating joint in
                        accordance with the requirements of Section 7.4 of NACE Standard
                        RP0286.
January, 2004                         Specification EGP3-02.01                            16 OF 30
                6.4.3   At least one permanent reference electrode shall be installed for each
                        protected structure. This is in order to provide an easily accessible
                        potential measurement reading. For aboveground storage tanks, the
                        number of permanent reference electrodes shall be in accordance with
                        paragraph 11.2.4 of NACE RP0193.
                6.4.4   Additional permanent reference electrodes shall be provided with the
                        potential monitoring stations, where high soil IR drops are encountered,
                        and/or representative protection measurements by portable reference
                        electrode cannot be easily made.
                6.4.5   Buried reference electrodes shall be installed in a backfill material, such
                        as gypsum, that provides a stable, uniform environment, capable of
                        retaining moisture.
                6.4.6   Separate test polarization coupons should be combined with buried
                        permanent reference electrodes in the following circumstances:-
                        ● High soil IR drop
                        ● Possibility of stray currents
                        ● Monitoring of buried sacrificial anodes
                6.4.7   Copper/copper sulphate reference electrode combinations shall be used
                        in combination with soil and fresh water unless otherwise agreed with
                        COMPANY.
                6.4.8   The use of alternative reference electrodes shall be subject to COMPANY
                        review and approval.
                6.4.9   Each monitoring station shall be given a unique tag number for future
                        identification and reference against monitoring records.
                6.4.10 In addition to the permanent reference electrodes for aboveground
                       storage tanks, slotted pipes (50mm diameter) shall be installed across the
                       diameter of the tank foundation. The slotted pipe material shall be
                       suitable for the normal operational temperature of the tank and shall be
                       wrapped with a low weight, water permeable textile to prevent sand
                       entering the pipe during compaction. Permanent access points for the
                       temporary installation of portable reference electrodes beneath the tank
                       periphery shall be installed through the ring wall. CONTRACTOR shall
                       ensure that the slotted pipes and access tubes are installed during the
                       ring wall construction and do not clash or interfere with other structures,
                       pipes etc. and that adequate access is provided for insertion/pulling of the
                       reference electrodes during monitoring activities.
January, 2004                         Specification EGP3-02.01                           17 OF 30
7.0    ELECTRICAL CABLING AND CONNECTIONS
       7.1      Cable Requirements
                7.1.1   Cables shall be copper, sized to minimize the voltage drop throughout the
                        system to less than 2V. The minimum cable sizes shall be as follows:
                        ● AWG #4 or 25mm² for DC power and bonding cables
                        ● AWG #6 or 16mm2 for anode cables
                        ● AWG #10 or 6mm2 for test cables
                7.1.2   Cable insulation shall be suitable for the environment in which it is
                        installed. All cable insulation shall have a 100V rating, as a minimum. DC
                        power cable insulation shall be rated for 600V minimum. The following
                        requirements shall also be met:
                        ● For onshore buried cables, insulation shall be either double layer
                           polyvinylchloride (PVC/PVC), polyethylene (PE/PE), or cross-linked
                           polyethylene-polyvinylchloride (XLPE/PVC)     as   a    minimum.
                           CONTRACTOR shall provide additional protective sheathing for rocky
                           or aggressive soil conditions
                        ● For cables installed in a marine environment, insulating materials shall
                           be resistant to both water and chlorides. Cables shall be either double
                           layer polypropylene (PP/PP), ethylene propylene rubber/chloro-
                           sulphonated polyethylene (EPR/CSP), neoprene or chloroprene, and
                           shall be completely waterproofed. Protection shall be provided
                        ● Where cable is buried in congested areas or areas potentially subject to
                           frequent excavation or damage, the cables shall be either run in a
                           conduit, be armored, or be protected by other suitable method
                7.1.3   All buried cables shall be installed at least 600mm below grade and
                        without splices. Cable connections shall only be made aboveground and
                        be tagged with identification labels. CONTRACTOR shall install route
                        markers to identify the presence of buried cables at intervals of not more
                        than 100m. Buried cables shall be installed with at least one relief loop
                        underground.
                7.1.4   Where underground cable splice joints are unavoidable, then a
                        “Scotchcast” epoxy resin kit, or similar, shall be used for sealing the joint.
                7.1.5   All above ground cables shall be encased in armored cable and/or cable
                        trays. If armored cable is used, this shall be isolated from any earthing
                        system.
January, 2004                         Specification EGP3-02.01                             18 OF 30
       7.2      Junction Boxes
                7.2.1   All connections, including anode cables, above ground splices, test leads,
                        surge arrestors, bonding, reference electrodes, and negative connections,
                        shall be made in junction/test/bond boxes, certified for the hazardous
                        area classification in which they are installed.
                7.2.2   Weatherproofing of junction boxes shall meet the minimum degree of
                        protection NEMA 4X/IP56 in accordance with EGP3-12.01.
                7.2.3   Junction boxes for plants containing hazardous areas, shall meet the
                        requirements of EGP3-12.01. Junction boxes shall not be installed in
                        Class 1, Division 1 areas.
                7.2.4   All junction/test/bond boxes shall be identified by a unique number, shall
                        be accessible at all times, and shall be constructed to prevent
                        unauthorized entry, vandalism or damage.
                7.2.5   All cables being brought above ground shall enter a junction box via a
                        buried conduit or other suitable protective shroud, and entrance shall be
                        by a COMPANY approved fitting/gland.
                7.2.6   All cables inside junction/test/bond boxes shall be identified with suitable
                        tags or labels to indicate the structures to which they are connected.
       7.3      Cable Connection Requirements
                7.3.1   Connection of cables to structures shall ensure that an electrically
                        conductive and mechanically secure bond is made. The following are
                        acceptable methods of connection:-
                        ● Fusion welded metal plate with welded stud bolt connection
                        ● Stud welded bolt
                        ● Thermite brazed copper connection
                        ● Pin brazed connection
                7.3.2   The minimum welded plate size shall be 50mm x 50mm x 6mm.
                7.3.3   All connections shall be made a minimum of 50mm from other welded
                        joints.
                7.3.4   Thermite brazed connections shall be limited to 15gramme cartridge size
                        with a maximum cable size of AWG #6 or 16mm². Multiple cable
                        connections will be necessary for negative connections. Thermite brazing
                        shall not be used with austenitic stainless of duplex steels.
                7.3.5   The connection method shall take into account metallurgical, welding, and
                        inspection requirements for the base material. Specific attention shall be
                        paid to satisfying the base metal hardness limits.
January, 2004                         Specification EGP3-02.01                            19 OF 30
                7.3.6   Connections shall be made prior to testing of pipe, as far as practically
                        allowed by the pipe spool fabrication method and testing sequence.
                7.3.7   Where connections are to be made to internally lined piping, they shall be
                        made prior to the installation of the internal protective coating/lining, or by
                        low heat input methods that ensure no damage occurs to the internal
                        lining. Alternative methods shall be submitted to COMPANY for review
                        and approval.
                7.3.8   Coating repairs to structures after installation of cable connections shall
                        be performed in accordance with the original protective coating
                        specification. Epoxy resin cast seals may be an acceptable alternative
                        method to repair coating damage. All alternative methods shall be subject
                        to COMPANY review and approval.
8.0    SPECIFIC REQUIREMENTS FOR IMPRESSED CURRENT SYSTEMS
       8.1      Anodes
                8.1.1   Anodes shall be selected from the following types:-
                        ● High silicon cast iron, with chromium
                        ● Mixed metal oxide (MMO)on a noble metal (such as titanium or
                           platinum),
                        ● Platinized titanium or niobium
                8.1.2   For aboveground storage tanks that have a flexible membrane installed
                        as part of the foundation design, MMO/Ti anode systems shall be
                        installed with the following requirements:
                        ● For MMO/Ti systems, all titanium ribbon, conductor bars and connector
                           assemblies shall be manufactured from ASTM B265, Ti, Gr.1 or
                           COMPANY approved equivalent. The titanium ribbon anode, with the
                           exception of the titanium conductor bar, shall be coated with a mixed
                           metal oxide layer.      CONTRACTOR shall confirm the minimum
                           dimensions of the ribbon and conductor bar during detailed design.
                        ● Multiple power feed cables from the anode junction box to the central
                           conductor bar shall be provided and the central conductor bar shall be
                           interconnected to the other conductor bars. The connections between
                           the cables and the central conductor bar shall be factory made, tested
                           and epoxy encapsulated for water tightness. No field joints/splices
                           shall be permitted below the tank base plates.
                        ● A secondary, complete, redundant MMO/Ti anode grid with power feed
                           cables shall be installed during foundation construction.
January, 2004                           Specification EGP3-02.01                            20 OF 30
                8.1.3   The number, size and spacing of MMO/Ti grid anodes shall ensure a
                        sufficient structure-to-soil potential is met over the entire surface area of
                        the base plates. Maximum spacing between the ribbon anodes shall not
                        exceed three times the actual distance between the anode grid and the
                        tank base plates or 1.75m, whichever is less, unless otherwise
                        recommended by the anode manufacturer and agreed with COMPANY.
                8.1.4   Alternative anode selections shall be subject to COMPANY review and
                        approval.
                8.1.5   Anode lead wires shall be one continuous length with no breaks. Splicing
                        shall be avoided.
       8.2      Backfill Material
                8.2.1   Backfill for anode beds shall be calcined petroleum coke breeze, with a
                        low sulphur content (4% or less).
                8.2.2   For deep groundbeds, calcined fluid petroleum coke breeze in
                        accordance with the minimum requirements of NACE RP0572 shall be
                        used.
                8.2.3   Other low resistivity back fill materials may be proposed for COMPANY
                        review and approval, where the ground conditions dictate.
                8.2.4   Pre-packaged anodes, where used, shall be supplied with pre-compacted
                        calcined fluid petroleum type coke breeze.
                8.2.5   Backfill under aboveground storage tanks shall be clean, “washed” sand
                        with a maximum of 50 ppm of chlorides.
       8.3      Transformer-Rectifiers
                8.3.1   Transformer-rectifiers (T/R’s) shall be specifically designed for cathodic
                        protection duties, and shall meet the minimum requirements of this
                        Engineering Standard.
                8.3.2   The T/R shall be dry type for outdoor applications, with double wound
                        transformer and silicon diode rectifier, and supplied with sunshade for
                        outdoor installations. Dry type T/R’s may be used for indoor installations.
                        Electronic switched mode T/R’s shall be subject to COMPANY review and
                        approval.
                8.3.3   T/R’s shall be installed in non-hazardous areas wherever possible. If this
                        is not practicable, the T/R shall be an oil immersed type and shall meet all
                        hazardous area classification requirements for the area into which it is
                        installed. T/R’s shall not be installed into Class 1, Division 1 areas. The
                        T/R shall have a minimum degree of protection of NEMA 4X/IP56 in
                        accordance with EGP3-12.01. In all cases, T/R’s shall be protected from
                        damage by vehicular traffic by four concrete-filled steel posts or
                        COMPANY approved alternative.
                8.3.4   The rectifier shall comply with the requirements of EGP3-12.16.
January, 2004                         Specification EGP3-02.01                             21 OF 30
                8.3.5   The T/R shall be sized to provide a minimum 25% spare capacity of both
                        voltage and current requirement determined during detailed design of the
                        cathodic protection system.
                8.3.6   The T/R unit shall be designed to withstand power surges, lightning
                        strikes, and short circuits of up to 15 seconds duration.
                8.3.7   The rectifier output current RMS ripple shall be limited to less than 5% of
                        the DC output current, through the range 5% to 100% of the full rated
                        current output.
                8.3.8   The current rating of silicon diodes shall be at least 1.25 times the full
                        current rating of the rectifier.
                8.3.9   The T/R shall be provided with continuous reading, flush-mounted DC
                        voltmeter and ammeter for displaying the measured output voltage and
                        current. Meters shall be accurate to within 2% of full scale value and
                        shall be linear from zero to full scale value. Digital meters are also
                        acceptable.
                8.3.10 Control switches and meters shall be accessible and mounted as close as
                       possible to eye level.
                8.3.11 Stepless adjustment should be used where practical. Stepped manual
                       control may be used for onshore buried structures where a low variation
                       in output current is expected. Where stepped control is used, then this
                       shall be by front mounted switches with a maximum step size of 5% of the
                       full rated voltage. Detachable links or jumps shall not be used. For the
                       T/R of the system for the internal surfaces of the firewater storage tank ,
                       the output voltage shall be controlled to provide a constant structure-to-
                       electrolyte potential using an electrical or electronic automatic control
                       circuit.
                8.3.12 The T/R shall be provided with an “ON/OFF” timer unit and circuit
                       interrupter on the DC output capable of switching the full output current
                       for 2 minutes ON and 3 minutes OFF. If the system is protected by more
                       than one T/R, then the timer units shall be provided with synchronous
                       switching. The timer unit shall be provided with a bypass for normal
                       operation.
                8.3.13 A power failure signal shall be provided from the T/R for feed back to a
                       centralized control room.
       8.4      Installation Requirements
                8.4.1   Impressed current systems shall be installed in accordance with the
                        requirements of the standards referenced in this specification.
                8.4.2   Groundbeds may be either shallow or deep. Deep groundbeds shall be
                        installed in accordance with the requirements of NACE RP0572.
                8.4.3   For deep groundbeds, the fluidized calcined petroleum coke breeze shall
                        be pumped from the bottom of the hole, and not gravity fed from the top.
January, 2004                         Specification EGP3-02.01                           22 OF 30
                8.4.4   Groundbed anodes shall be centered within the coke breeze envelope.
                8.4.5   For deep groundbeds, the following additional requirements shall be met:
                        ● Subsurface strata shall be logged at 1500mm intervals and at all
                           formation changes.     CONTRACTOR shall note the type of rock or
                           sediment.
                        ● Before installing anodes, each hole shall be electrically logged at
                           1500mm intervals, and anodes placed to minimize ground resistance
                           whilst maintaining a balance with the other anodes.
                        ● Surface casings shall be installed and sealed with a bentonite or
                           cement seal plug after loading and testing is completed.
                        ● Each hole shall have a vent tube installed concurrently with the first
                           anode in order to vent dangerous gases that may form due to anode
                           reactions. The vent tube shall be resistant to chlorides and shall be
                           perforated from the top of the bottom anode to 5m above the top
                           anode. It shall extend a sufficient height aboveground to prevent
                           ingress of water and dirt and have a filter and breather cap installed.
9.0    SPECIFIC REQUIREMENTS FOR SACRIFICIAL ANODE SYSTEMS
       9.1      Anodes
                9.1.1   Sacrificial anodes shall be selected from the following types. Untried or
                        special alloy compositions and/or applications shall require COMPANY
                        review and approval:-
                        ● High purity zinc (99.9% Zn or greater),
                        ● Zinc to US Military Specification MIL-A-18001.
                        ● Magnesium-Aluminum-Zinc alloy
                        ● Magnesium-Manganese alloy
                9.1.2   Additions of elements that have a detrimental affect on the anode output,
                        (e.g. iron, copper, nickel) or that are potential carcinogens (e.g. mercury,
                        cadmium, tin) shall not be permitted.
                9.1.3   The application of Zinc anodes shall be limited to resistivities less than
                        2000ohm-cm.
                9.1.4   The anode selection shall take into account cost, number of anodes
                        required, ease of installation, lifespan, service temperature, and the risk
                        of any other detrimental effects due to environmental conditions.
                9.1.5   CONTRACTOR shall submit full details of anode compositions and
                        proposed inspection and test procedures, for COMPANY review and
                        approval prior to installation.
January, 2004                         Specification EGP3-02.01                            23 OF 30
                9.1.6   Cast anodes shall be free from through body and surface inclusions,
                        pores, and longitudinal cracks. Transverse cooling cracks may be
                        permitted. Casting acceptance criteria shall be submitted to COMPANY
                        for review and approval.
                9.1.7   Anode steel cores shall be blast cleaned to a near-white metal finish and
                        shall have this finish at the time of casting. Zinc anode inserts may be
                        galvanized. The core shall be centered in the anode and shall extend a
                        minimum of 75% of the length of the anode.
                9.1.8   The net mass of each anode shall not be less than 95% of the specified
                        nominal mass.
                9.1.9   The anode material shall be bonded to the steel core over a minimum of
                        90% of the total surface. No individual discontinuity shall exceed 35mm
                        in length.
                9.1.10 Dimensions and positions of inserts shall be within +/-2% tolerance of the
                       defined dimensions.
                9.1.11 Fabricated inserts shall be subject to 20% MPI inspection of completed
                       welds.
                9.1.12 For direct buried anodes, lead wires shall be attached to the core by
                       brazing or silver soldered and sealed with a water repellent, electrically
                       insulating material such as epoxy resin with a heat shrinkable sleeve. The
                       lead wire connection shall have a breaking strength equal to or greater
                       than the anode cable and shall be capable of supporting the full weight of
                       the anode. The lead wire shall be a minimum of 10m in length.
                9.1.13 Direct buried anodes shall be pre-packaged with a chemical back-fill of
                       gypsum, bentonite and sodium sulphate, the composition of which shall
                       be suitable for the specific soil resistivities and ground water encountered.
                9.1.14 For anodes with a net weight in excess of 100kg, a destructive test shall
                       be performed on one anode to check the strength of the bond between
                       the steel insert and the anode, and the result recorded.
       9.2      Installation
                9.2.1   Anodes shall be installed in accordance with the standards referenced in
                        this specification.
                9.2.2   Pre-packaged sacrificial anodes for onshore buried structures shall be
                        installed no closer than 1m from the structure to be protected, and for
                        buried pipes and pipelines, the top of the anode shall be below the pipe
                        centerline.
January, 2004                         Specification EGP3-02.01                            24 OF 30
10.0   AVOIDANCE OF ELECTRICAL INTERFERENCE AFFECTS
       The following general requirements shall be noted
       1.       CONTRACTOR shall ensure that the design of the cathodic protection system
                avoids stray currents and other electrical interference effects, such as from direct
                current, AC power cables, train traction power supplies, foreign pipelines, other
                secondary metallic structures, and neighboring cathodic protection systems.
       2.       Where CONTRACTOR can show that avoidance is not practicable, it shall
                propose mitigating measures to be adopted to minimize the effects on the
                cathodic protection system for COMPANY review.
       3.       The measures adopted by CONTRACTOR shall consider in the first place,
                maintaining independence of the cathodic protection systems and structures.
                This should include the selection of high standard/high integrity coating systems.
                Where this is considered inadequate or impracticable, then consideration may
                also be given to the following:-
                        Resistive bonding
                       Localized sacrificial anodes or impressed current cathodic protection system
                        Zinc grounding cells
                        Decoupling devices (specific to AC or DC power sources)
11.0   INSPECTION AND TESTING OF EQUIPMENT
       11.1     General
                11.1.1 CONTRACTOR shall propose the minimum inspection and testing
                       requirements for all cathodic protection equipment and materials for
                       COMPANY review and approval. Inspection and testing shall ensure that
                       the material requirements of this specification and referenced
                       specifications are satisfied prior to dispatch from manufacturers’ works.
                       The following requirements are in addition to any site inspection activities.
                11.1.2 All electrical equipment shall be inspected against the relevant
                       requirements of EGP3-12.01.
                11.1.3 Final inspection of all equipment described within this section shall
                       include visual checks to confirm compliance with the specified design
                       drawings and details.
       11.2     Impressed Current Anodes
                Inspection and testing of impressed current anodes shall include the following
                activities:
January, 2004                           Specification EGP3-02.01                           25 OF 30
                ● Agreed manufacturer standard tests
                ● Chemical analysis per heat for cast anodes (at least two samples)
                ● Review of all material certificates for plating materials, substrates, inserts,
                   cables, and any other sub-supplied materials integral to the anode construction
                ● Visual inspection and measurement of cracking and shrinkage of cast anodes
                ● Measurement of overall dimensions, thicknesses, weights, and positions on at
                   least a 5% sample basis
       11.3     Sacrificial Anodes
                Inspection and testing of sacrificial anodes shall include the following activities:-
                ● Agreed manufacturer standard tests
                ● Chemical analysis per heat (at least two samples)
                ● Review of all material certificates for inserts and cables, and any other sub-
                   supplied materials integral to the anode construction
                ● Visual inspection of steel inserts’ surface preparation and dimensions, on at
                   least a 5% sample basis
                ● Visual inspection and measurement of cracking and shrinkage
                ● Measurement of overall dimensions, thicknesses, weights, and positions on at
                   least a 5% sample basis
       11.4     Transformer – Rectifiers
                11.4.1 A manufacturer’s standard Factory Acceptance Test shall be performed
                       to demonstrate the capacity and functionality of the transformer –
                       rectifiers. This procedure shall be submitted by CONTRACTOR for
                       COMPANY review and approval.
                11.4.2 Enclosure certification shall be reviewed to confirm compliance with the
                       specified enclosure protection and hazardous classification ratings.
       11.5     Isolation Joints
                11.5.1 Monobloc type isolation joints and isolation spool pieces shall be
                       hydrostatically tested at the manufacturer’s works in accordance with the
                       applicable piping code.
                11.5.2 The electrical resistance and resistance to sparking of pre-assembled
                       isolation joints shall be checked using the following tests:-
                       ● Apply 1500V 50Hz AC across the joint for at least 5 minutes without
                           sparking or insulation breakdown.
January, 2004                          Specification EGP3-02.01                             26 OF 30
                       ● Apply 1000V DC across the joint and measure the resistance. The
                           resistance shall be greater than 1mega-ohm.
       11.6     Cabling
                Jun Cabling certificates shall be reviewed prior to shipping to confirm compliance
                with the specified size, type, rating, and quantity.
       11.7     Junction Boxes and Surge Arrestors
                Certification for junction boxes / monitoring stations / bond boxes and surge
                arrestors shall be reviewed prior to shipping to confirm compliance with the
                specified enclosure protection and hazardous classification ratings.
12.0   SITE ACCEPTANCE TESTING AND COMMISSIONING
       12.1     General
                12.1.1 Site acceptance testing and commissioning of the cathodic protection
                       systems shall be undertaken in accordance with the standards referenced
                       in this specification and this section, as a minimum.
                12.1.2 CONTRACTOR shall ensure that commissioning of the cathodic
                       protection system is integrated into the overall construction and
                       commissioning activities and schedules.
                12.1.3 Stable, effective operation of onshore cathodic protection systems shall
                       be achieved within 2-4 weeks of the start of commissioning. Ineffective
                       operation beyond this time shall be investigated and resolved by
                       CONTRACTOR to COMPANY satisfaction. Any necessary remedial
                       measures shall be proposed by CONTRACTOR for COMPANY review
                       and approval.
                12.1.4 All measurements, readings, and pertinent data shall be recorded within
                       the final operating and maintenance documentation described in Section
                       15.
       12.2     Transformer – Rectifiers
                Each transformer-rectifier shall undergo a load test prior to initial system
                energizing. The T/R shall be run continuously for a minimum of 24 hours at the
                maximum current and DC voltage rating. During this test, calibration checks of
                the ammeters, voltmeters, and any other instrumentation shall be performed.
       12.3     Isolation Joints
                12.3.1 All monobloc type isolation joints shall be retested immediately prior to
                       welding into the pipeline.
January, 2004                        Specification EGP3-02.01                           27 OF 30
                12.3.2 Insulating flanges and spools should be pre-assembled and tested
                       immediately prior to welding into the pipeline. Where this is not possible,
                       the following checks shall be made to ensure adequate performance of
                       the joint:-
                       ● The individual bolt to flange resistance’s shall be measured prior to
                           energizing the system for the first time,
                       ● After energizing, the current through the joint shall be measured using
                           an ammeter, and recorded.
       12.4     Cable Connections
                12.4.1 Thermite and pin brazing cable connection procedures shall be pre-
                       qualified by CONTRACTOR by a minimum of three representative
                       connections on a sample plate of the same type and class of material as
                       the actual pipe. Fusion and stud welded connections shall be performed
                       to prequalified welding procedures. The test procedures shall be
                       submitted by CONTRACTOR for COMPANY review and approval.
                       Brazing test welds shall be witnessed by COMPANY.
                12.4.2 The following test requirements apply specifically to thermite brazing:-
                       ● A single hammer blow using a 1kg hammer shall be applied without
                           visible cracking or breakage.
                       ● The penetration of the copper joints into the base metal shall be
                           inspected metallographically. Copper penetration into the base metal
                           shall not exceed 0.5mm.
                       ● Transverse Vickers hardness checks shall be made to confirm the
                           relevant base material requirements are satisfied.
       12.5     Pipe Sleeves
                The electrically isolation of pipe sleeves from the protected pipe is critical. Visual
                checks shall be made during installation to ensure satisfactory separation and
                prevention of accidental in-fills into the sleeve. Measurements shall be made
                before backfill and after completion and recorded, to ensure satisfactory isolation.
       12.6     Buried Structures
                12.6.1 Prior to energizing the cathodic protection system, the “native” structure
                       to soil potentials shall be measured at the following locations, as a
                       minimum:-
                       ● All test stations
                       ● Locations where buried structures protrude above ground
January, 2004                         Specification EGP3-02.01                             28 OF 30
                12.6.2 The cathodic protection system shall be energized and preliminary
                       adjustments made to balance the distribution of current and satisfy the
                       structure to soil protection potential criteria. “On” and “Instant Off”
                       potential measurements shall be made at the same locations as the
                       “native” potentials, when the system is first energized and then switched
                       off.
                12.6.3 The current output and potential of the transformer – rectifier shall be
                       measured and recorded.
                12.6.4 The current output from individual impressed current and sacrificial
                       anodes shall be measured and recorded.
                12.6.5 Any effects due to stray current and interference between the cathodically
                       protected structures, secondary structures, and neighboring cathodic
                       protection systems shall be determined and corrected as necessary.
                12.6.6 Where permanent reference electrodes are installed, the readings shall
                       be compared with measurements obtained using the portable reference
                       electrode, in order to validate the permanent reference electrodes.
                12.6.7 After a minimum period of two weeks, but no more than four weeks, the
                       initial polarization testing shall be repeated and system adjustments made
                       as necessary. Both “On” and “Instant Off” potential measurements shall
                       be recorded before and after any adjustments.
                12.6.8 For aboveground storage tanks, “native”, “On” and “Instant Off” potential
                       measurements shall be taken utilizing the permanent reference
                       electrodes.
                12.6.9 For water tanks, “native” and “On” potential measurements shall be taken
                       using a portable copper/copper sulphate reference electrode.
                       Measurements shall be taken at minimum of three depths, as follows:
                       ● At the tank floor,
                       ● 500mm below the water surface, and
                       ● At a point midway between the two.
13.0   DOCUMENTATION
       13.1     Design Specification
                13.1.1 CONTRACTOR shall submit a basic design specification for each
                       cathodic protection system. This shall propose the design philosophies
                       and outline the selected cathodic protection systems for COMPANY
                       review and approval before detailed design proceeds. The specifications
                       shall include the following, as a minimum:
                       ● Design philosophy, including protection criteria, design life, and
                           referenced codes and standards
January, 2004                        Specification EGP3-02.01                          29 OF 30
                       ● Results and assessment of site surveys
                       ● Outline description of the chosen cathodic protection systems, including
                           the size, number, and location of anodes / groundbeds, transformer –
                           rectifiers, as well as control and measurement features, with basic
                           calculations and economic justifications
                       ● Evaluation of any potential stray current and interference effects, and
                           also impact from and to any neighboring secondary structures and
                           other cathodic protection systems
                       ● Definition of the type of isolating joints to be used
                       ● Definition of the type and number of monitoring stations to be used
                13.1.2 CONTRACTOR shall provide a detailed design specification for each
                       cathodic protection system as part of its detailed engineering
                       deliverables. This final specification shall contain, but not be limited to,
                       the following:
                       ● Design philosophy, including protection criteria, design life, and
                           referenced codes and standards
                       ● Results and assessment of site surveys
                       ● Definition of the chosen cathodic protection systems (including
                           temporary systems), including selection, sizing, and placement with all
                           necessary calculations and economic justifications
                       ● Evaluation of any potential stray current and interference effects, and
                           also impact from and to any neighboring secondary structures and
                           other cathodic protection systems
                       ● List of all structures to be protected, including identification numbers,
                           locations, and dimensions
                       ● List of all piping and pipelines to be protected, including identification
                           numbers, length, nominal diameter, coating and lining systems, pipe
                           specification, and service
                       ● List of all isolating joints, including associated piping identification
                           numbers, service, type of joint, and calculations for sizing isolating
                           spool pieces
                       ● List of all monitoring stations and junction boxes, including identification
                           numbers, location, and purpose
                       ● List of all negative connection points, including identification numbers
                           and location
January, 2004                         Specification EGP3-02.01                             30 OF 30
                       ● Detailed system layout drawings, indicating the location of anodes and
                           ground beds, transformer – rectifiers, cable routings, monitoring
                           stations, reference electrodes, negative connection points, and
                           adjacent secondary structures and neighboring cathodic protection
                           systems
                       ● Definition of assigned IP ratings and Hazardous area classifications
                13.1.3 The basic and detailed design specifications shall be produced by a
                       specialist cathodic protection engineer.
       13.2     Installation and Commissioning Procedures
                13.2.1 CONTRACTOR shall ensure that full installation and commissioning
                       procedures are submitted by the cathodic protection system design
                       CONTRACTOR, and that they are in accordance with the requirements of
                       this Project Specification and CONTRACTOR’s instructions.
                13.2.2 Commissioning procedures shall contain, but not be limited to, the
                       information necessary to perform the tests and system balancing required
                       in this specification. CONTRACTOR shall submit these procedures for
                       COMPANY review and approval.
       13.3     Operating and Maintenance Manuals
                CONTRACTOR shall submit operating and maintenance manuals to COMPANY
                as part of the hand-over documentation. These manuals shall contain, but not be
                limited to, the following:
                ● A full description of each cathodic protection system as-installed, including as-
                   built drawings of the system layouts.
                ● Commissioning report, including a record of all measurements required.
                ● Maintenance procedures for all equipment items with recommended
                   schedules.
                ● Monitoring schedules and procedures for each monitoring station.
                ● Safe operating guidelines for the cathodic protection system.
                ● Schedule of recommended spares.
January, 2004                         Specification EGP3-02.01                           31 OF 30