0% found this document useful (0 votes)
466 views97 pages

Theodolite Traversing

The document discusses different methods for conducting a traverse survey using a theodolite. It describes the interior angle method, which involves measuring the interior angles of a traverse as the survey proceeds from station to station in a clockwise or counterclockwise direction. Detailed steps are provided for performing the fieldwork using this method, including setting up the theodolite and recording the measured left and right face angles at each station.

Uploaded by

Farisa Zulkifli
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
466 views97 pages

Theodolite Traversing

The document discusses different methods for conducting a traverse survey using a theodolite. It describes the interior angle method, which involves measuring the interior angles of a traverse as the survey proceeds from station to station in a clockwise or counterclockwise direction. Detailed steps are provided for performing the fieldwork using this method, including setting up the theodolite and recording the measured left and right face angles at each station.

Uploaded by

Farisa Zulkifli
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 97

THEODOLITE

TRAVERSING
Assoc. Prof. Sr Hj Muhamad Hj Jaafar
Department of Surveying Science and Geomatics
Universiti Teknologi MARA
Outline

 Introduction
 The Purpose of Traverse
 The Selection of Station
 The Measurement Required
 Linear Measurement
 Angle/Bearing Measurement
Outline

 Interior Angle Method


 Interior Angle Method- Fieldwork Procedure
 Exterior Angle Method
 Exterior Angle Method- Fieldwork Procedure
 Bearing Method
 Bearing Method – Fieldwork Procedure.
 Measurement Distance of Traverse Line
INTRODUCTION

 A traverse consists of a series of consecutive


line related by horizontal angle (bearing) and
lengths (distance).
 Two types of traverse:
 Closed Traverse
 Open Traverse
THE PURPOSE OF TRAVERSE
 Propety surveys to locate or establish
boundaries
 Supplementary horizontal control for
topographic mapping.
 Location and construction layout surveys for
highways, railways and others private and
public work
 Ground control surveys for photogrammetric
mapping.
THE SELECTION OF STATION
 The number of station should be kept to the
minimum
 The line of sight should be as long as possible
 The ground around stations must be stable
 The stations should be positioned so that the
surrounding features and details can be easily be
measured or set out by direct taping
 The stations should be clearly intervisible
 Stations should be selected where the theodolite
is not liable to be damaged or disturbed
 Route should be as direct as possible without
reducing efficiency of positioning control
THE MEASUREMENT REQUIRED

 Linear Measurement
 Angle/Bearing Measurement
Linear Measurement

 Chains
 Tape
 Electromagnetic Distance Measurement
Angle / Bearing Measurement

 Included angle method


 Exterior angle method
 Bearing method
Interior angle method
 The interior angles of a traverse are measured by
applying the method of repetition.
 The traverse is run either clockwise or counter clock
wise
 To reduce mistake in reading, recording and
computing, they should always be turned clockwise
from the back sight station to the fore sight station
Interior Angle Method
Interior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 3 10 00 00
2
(Read) 1
3
2

5
Interior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 3 10 00 00
2
(Read) 1 122 45 50
3
2

5
Interior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 3 10 00 00 190 00 00
2
(Read) 1 122 45 50
3
2

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

(Set) 3 10 00 00 190 00 00
2
(Read) 1 122 45 50 302 46 00
3
2

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2
1 122 45 50 302 46 00
3
(Set) 4 10 00 00
2
3
(Read) 2

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2
1 122 45 50 302 46 00
3
(Set) 4 10 00 00
2
3
(Read) 2 99 34 30

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2
1 122 45 50 302 46 00
3
(Set) 4 10 00 00 190 00 00
2
3
(Read) 2 99 34 30

5
Interior Angle Method- Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2
1 122 45 50 302 46 00
3
(Set) 4 10 00 00 190 00 00
2
3
(Read) 2 99 34 30 279 34 40

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 (Set) 5 10 00 00
4
(Read) 3

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 (Set) 5 10 00 00
4
(Read) 3 116 18 00

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 (Set) 5 10 00 00 190 00 00
4
(Read) 3 116 18 00

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 (Set) 5 10 00 00 190 00 00
4
(Read) 3 116 18 00 296 18 10

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
(Set) 1 10 00 00
5
4
(Read) 4

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
(Set) 1 10 00 00
5
4
(Read) 4 120 09 30

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
(Set) 1 10 00 00 190 00 00
5
4
(Read) 4 120 09 30

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
(Set) 1 10 00 00 190 00 00
5
4
(Read) 4 120 09 30 300 09 40

5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
1 10 00 00 190 00 00
5
4
4 120 09 30 300 09 40
(Set) 2 10 00 00
1
(Read) 5
5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
1 10 00 00 190 00 00
5
4
4 120 09 30 300 09 40
(Set) 2 10 00 00
1
(Read) 5 131 01 50
5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
1 10 00 00 190 00 00
5
4
4 120 09 30 300 09 40
(Set) 2 10 00 00 190 00 00
1
(Read) 5 131 01 50
5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2

3 1 122 45 50 302 46 00

2 4 10 00 00 190 00 00
3
2 99 34 30 279 34 40

1 5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
1 10 00 00 190 00 00
5
4
4 120 09 30 300 09 40
(Set) 2 10 00 00 190 00 00
1
(Read) 5 131 01 50 311 01 40
5
Interior Angle Method -Field Work
Procedure
Station Face Left Face right

3 10 00 00 190 00 00
2
1 122 45 50 302 46 00
4 10 00 00 190 00 00
3
2 99 34 30 279 34 40
5 10 00 00 190 00 00
4
3 116 18 00 296 18 10
1 10 00 00 190 00 00
5
4 120 09 30 300 09 40
2 10 00 00 190 00 00

1
5 131 01 50 311 01 40
Exterior Angle Method
 The exterior angles of a traverse are
measured by applying the method of
repetition.
 The traverse is run either clockwise or
counter clock wise.
 To reduce mistake in reading, recording and
computing, they should always be turned
clockwise from the back sight station to the
fore sight station.
Exterior Angle Method
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00
2

3 (Read) 3

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00
2

3 (Read) 3 257 14 00

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00
3
(Read) 4

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00
3
(Read) 4 280 25 20

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00
4
(Read) 5

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00
4
(Read) 5 263 42 10

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00
5
4
(Read) 1

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00
5
4
(Read) 1 259 50 30

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00 190 00 00
5
4
(Read) 1 259 50 30

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00 190 00 00
5
4
(Read) 1 259 50 30 79 50 10

5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00 190 00 00
5
4
(Read) 1 259 50 30 79 50 10
(Set) 5 10 00 00
1
(Read) 2
5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00 190 00 00
5
4
(Read) 1 259 50 30 79 50 10
(Set) 5 10 00 00
1
(Read) 2 248 58 00
5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00 190 00 00
5
4
(Read) 1 259 50 30 79 50 10
(Set) 5 10 00 00 190 00 00
1
(Read) 2 248 58 00
5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2

3 (Read) 3 257 14 00 77 14 20

2 (Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00

1 (Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00 190 00 00
5
4
(Read) 1 259 50 30 79 50 10
(Set) 5 10 00 00 190 00 00
1
(Read) 2 248 58 00 68 58 20
5
Exterior Angle Method - Field Work
Procedure
Station Face Left Face right

(Set) 1 10 00 00 190 00 00
2
(Read) 3 257 14 00 77 14 20
(Set) 2 10 00 00 190 00 00
3
(Read) 4 280 25 20 100 25 00
(Set) 3 10 00 00 190 00 00
4
(Read) 5 263 42 10 83 42 00
(Set) 4 10 00 00 190 00 00
5
(Read) 1 259 50 30 79 50 10
(Set) 5 10 00 00 190 00 00
1
(Read) 2 248 58 00 68 58 20
BEARING METHOD
 The bearing of all the lines are measured directly with help of a
theodolite.
 Simplest calculation is necessary to deduce these value from the
included angle
 The bearings are measured clockwise from the north end of the
meridian through the angle points.
 This method, instrument is oriented at each setup by sighting on
the previous station
 Then the forward station is sighted
 The resulting reading on horizontal circle will be the forward
bearing
BEARING METHOD

 Before start using bearing method, Datum


should be determine first
 Datum can be:
 Prismatic Compass reading
 Assumed Bearing
 Previous measurement (Certified Plan)
BEARING METHOD
N
N
3

2
N

N 4

5
Bearing Method - Field Work
Procedure
Compass
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1
2
3
(Read) 3
2

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
4 (Set) 5 213 10 35 33 10 35 100 14 50
1
5 (Read) 2 100 14 50 280 15 00
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40
2
3
(Read) 3 190 39 50
2

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40
2
3
(Read) 3 190 39 50
2

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40
2
3
(Read) 3 190 39 50 10 40 00
2

1 Different between Face Left and Face Right


should be not exceed 10”

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 ????
2
3
(Read) 3 190 39 50 10 40 00
2

Bearing 2 -3 (F.L) = 190 39 50


1
Bearing 2 – 3 (F.R) = 10 40 00 + 180
= 190 40 00

Mean = Bearing 2-1 (F.L) + Bearing 2-1 (F.R) / 2

4 = (190 39 50 + 190 40 00)/2


= 190 39 55
5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55
3
(Read) 4
1
(Set) 3
4
(Read) 5
(Set) 4
5
(Read) 1
4 (Set) 5
1
5 (Read) 2
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55
3
(Read) 4
1

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55
3
(Read) 4 264 22 00
1

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55
3
(Read) 4 264 22 00
1

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55
3
(Read) 4 264 22 00 84 22 10
1

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 ????
3
(Read) 4 264 22 00 84 22 10
1

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05
4
(Read) 5

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05
4
(Read) 5

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05
4
(Read) 5 334 12 30

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05
4
(Read) 5 334 12 30

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05
4
(Read) 5 334 12 30 154 12 20

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 ?????
4
(Read) 5 334 12 30 154 12 20

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25
5
(Read) 1
4 (Set) 5
1
5 (Read) 2
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25
5
(Read) 1
4 (Set) 5
1
5 (Read) 2
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25
5
(Read) 1 33 10 40
4

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25
5
(Read) 1 33 10 40
4

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25
5
(Read) 1 33 10 40 213 10 30
4

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 ?????
5
(Read) 1 33 10 40 213 10 30
4

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
4

5
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
4 (Set) 5 213 10 35 33 10 35
1
5 (Read) 2
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1 (Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
4 (Set) 5 213 10 35 33 10 35
1
5 (Read) 2
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1 (Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
4 (Set) 5 213 10 35 33 10 35
1
5 (Read) 2 100 14 50
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1 (Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
4 (Set) 5 213 10 35 33 10 35
1
5 (Read) 2 100 14 50
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1 (Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
4 (Set) 5 213 10 35 33 10 35 ?????
1
5 (Read) 2 100 14 50 280 15 00
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
3
(Read) 3 190 39 50 10 40 00
2 (Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
1 (Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
4 (Set) 5 213 10 35 33 10 35 100 14 55
1
5 (Read) 2 100 14 50 280 15 00
Bearing Method - Field Work
Procedure
Station Face Left Face right Mean
Datum from PC 2 - 1 280 14 40
(Set) 1 280 14 40 100 14 40 190 39 55
2
(Read) 3 190 39 50 10 40 00
(Set) 2 10 39 55 190 39 55 264 22 05
3
(Read) 4 264 22 00 84 22 10
(Set) 3 84 22 05 264 22 05 334 12 25
4
(Read) 5 334 12 30 154 12 20
(Set) 4 154 12 25 334 12 25 33 10 35
5
(Read) 1 33 10 40 213 10 30
(Set) 5 213 10 35 33 10 35 100 14 55
1
(Read) 2 100 14 50 280 15 00
Bearing Method - Field Work
Procedure
Closing Checking =
Mean Bearing of Last Line - Reference Bearing (Datum)
Mean Bearing of Last Line = 100° 14’ 55”
Datum 2 – 1 = 280° 14’ 40” ± 180°
= 100° 14’ 40”
Closing Error = 100° 14’ 55” - 100° 14’ 40”
= +15” (Acceptable)
Closing Error should be not exceed ± 0° 02’ 30”
MEASUREMENT DISTANCE OF
TRAVERSE LINE
 The lengths of each line traverse must be measured.
 Its can be done by simplest method (Tape, Chain or
Electromagnetic Distance Measurement)

HD = SD Cosine Ө
MEASUREMENT DISTANCE OF
TRAVERSE LINE
QUIZ

 Name the different types of traverse. Sketch


to illustrate your answer.
 What are the purposes of the traversing?