100% found this document useful (1 vote)
2K views27 pages

Throughput Accounting

Throughput accounting focuses on maximizing throughput, which is defined as sales minus material costs. It prioritizes products that generate the highest throughput per unit of the bottleneck resource. Performance is measured using the throughput accounting ratio, which should be above 1.0 for profitability. The five-step approach involves identifying the bottleneck, exploiting it to maximize throughput, subordinating all other resources, elevating the bottleneck's performance, and repeating the process if the bottleneck shifts. Inventory is discouraged and all costs except materials are considered fixed in the short run.

Uploaded by

Imran Umar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views27 pages

Throughput Accounting

Throughput accounting focuses on maximizing throughput, which is defined as sales minus material costs. It prioritizes products that generate the highest throughput per unit of the bottleneck resource. Performance is measured using the throughput accounting ratio, which should be above 1.0 for profitability. The five-step approach involves identifying the bottleneck, exploiting it to maximize throughput, subordinating all other resources, elevating the bottleneck's performance, and repeating the process if the bottleneck shifts. Inventory is discouraged and all costs except materials are considered fixed in the short run.

Uploaded by

Imran Umar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 27

Throughput accounting

outline
Theory of constraints
Throughput accounting
Performance measures in throughput accounting
Throughput accounting ratio
Theory of constraints
The theory of constraints (TOC) is an approach to
production management and optimising production
performance. It was formulated by Goldratt and Cox in
the US in 1986. Its key financial concept is to turn
materials into sales as quickly as possible, thereby
maximising the net cash generated from sales.
Throughput = Sales – Material costs
Bottleneck factor: the constraint
Time available
Limited selling resource
Lack of quality
Lack of reliable suppliers
Lack of skilled employees
Lack of machinery
Basic assumptions underlying throughput
accounting
 Since there is one bottleneck resource all other sources are not
bottlenecks
 Idle time should be accepted. Since all operational costs are fixed, idle
time is not costing any money.
 Non-bottleneck resources should not be used beyond amount
required to achieve max output. As it is considered wasteful
 No inventory should be built up except buffer inventory.( because
inventory cost you money in terms of space and Throughput
discouraged this.
 Except material all costs are fixed
Increasing throughput: elevating the
bottleneck
 The only way to increase throughput is to increase the
capacity of the bottleneck constraint
For example, time on Machine Type X may be a
bottleneck resource.
Moving from working five days a week to working six
or seven days a week
Moving from working a 12-hour production day to an
18-hour or 24-hour
five-step approach
1. Identify the constraint (bottleneck resource).
2. Decide how to exploit the constraint in order to
maximise throughput.
3. Subordinate and synchronise everything else to the
decisions made in step 2.
4. Elevate the performance of the constraint.
5. If the constraint has shifted during any of the above
steps, go back to step 1
Throughput accounting (TA)
Throughput accounting (TA) is an approach to
production management which aims to maximise sales
revenue less materials cost, while also reducing
inventory and operational expenses.
Throughput accounting concepts
Throughput accounting is based on the following
concepts, all derived from the TOC
1. In the short run, all costs in the factory (with the
exception of materials costs) are fixed costs.
2. In a JIT environment, all inventory is a 'bad thing' and the
ideal inventory level is zero. Products should not be
made unless a customer has ordered them
3. Profitability is determined by the rate at which 'money
comes in at the door' (that is, sales are made) and, in a JIT
environment, this depends on how quickly goods can be
produced to satisfy customer orders.
Difference
Conventional cost accounting Throughput accounting
Inventory is an asset. Inventory is not an asset.
Costs can be classified either as direct or No such classfication
indirect.
Direct labor is a variable cost. Except material all are fixed cost
Profit can be increased by reducing cost Profit is a function of material cost,
elements. total factory cost and throughput. Profit
= throughput minus TFC.
Performance measures in
throughput accounting
Performance measures in throughput accounting are
based around the concept that the aim is to maximise
throughput. This is achieved by maximising the
throughput per unit of bottleneck resource.
When an organisation makes more than one product,
total throughput is maximised by giving priority to
those products that earn the largest throughput per
unit of bottleneck resource. Products should be
ranked in order of priority according to their
throughput per unit of bottleneck resource.
The ratio for ranking products is therefore as follows.
Throughput return per factory hour:

Sales direct material costs


Usage of bottleneck resource in hours (factory hours)
Example:
WR Co manufactures three products, A, B and C.
Product details are as follows.
Product A Product B Product C
Sales 2.8 1.6 2.4
Material cost 1.2 0.6 1.2
Direct lab 1 0.8 0.8
cost
Weekly sales 4000 units 4000 units 5000 units
demand
Machine 0.5 hours 0.2 hours 0.3 hours
hours per
unit
Machine time is a bottleneck resource and maximum
capacity is 4,000 machine hours per week. Operating
costs including direct labour costs are $10,880 per
week
Direct labour workers are not paid overtime and work
a standard 38-hour week
Required???
Determine the optimum production plan for WR Co
and calculate the weekly profit that would arise from the
plan.
Solution
A B C
SP 2.8 1.6 2.4
Mater cost 1.2 0.6 1.2
Throughput 1.6 1 1.2
per unit

Machine hrs 0.5 0.2 0.3


per unit

Throughput $3.2 $5 $4
per machine
hour(w1)

Rank 3rd 1st 2nd


Optimal production plan
Product Units Bottleneck Total hrs Throughpu Total
hrs t per hour throughpu
$ t
$
B 4000 0.2 800 5 4000
C 5000 0.3 1500 4 6000
2300
A(balance) 3400 0.5 1700 3.2 5440
4000 15440
Less (10880)
operating
expenses
profit 4560
Throughput accounting ratio
 The throughput accounting ratio (TA ratio) is the ratio of the
throughput per unit of bottleneck resource to the factory cost per unit
of bottleneck resource. This ratio should be as high as possible, and
certainly more than 1.0.
Formula=
Throughput per unit of bottleneck resource
Factory cost per unit of bottleneck resource

Where Factory cost per unit of bottleneck resource =


Total factory costs
Total units of bottleneck resource

Note. 'Total factory costs' are also described as 'Total operating costs'.
They are all the costs other than material costs, and are regarded as a
fixed cost per period.
example
Selling price=160
Material cost=20
Machine hrs per unit= 2
Machine x limited output capacity=500 per week
Operating cost $30000 per week
requirement?
Calculate TA(Throughput accounting ratio)
Solution
Throughput per machine hr= (160-20)/2=70
Factory cost per machine hr=$30000/500hrs=60
TA ratio= $70/$60=1.17
A TA ratio that is not much higher than 1.0 is barely
profitable.
Interpretation
Total throughput should exceed total factory costs
otherwise the organisation will make a loss. This
means that the TA ratio should exceed 1.0.

(Higher TA ratios should be given priority over lower


TA ratios).
Question
 Corrie Company produces three products, X, Y and Z. The capacity of Corrie's
plant is restricted by process Alpha. Process Alpha is expected to be operational
for eight hours per day and can produce 1,200 units of X per hour, 1,500 units of
Y per hour and 600 units of Z per hour.

Product Selling price Material Throughput


per unit cost per per unit
unit
X 150 80 70
Y 130 40 90
Z 300 100 200

 Operating costs are $720000 per day


Requirement
(a) Calculate the profit per day if daily output achieved
is 6,000 units of X, 4,500 units of Y and 1,200 units of
Z.
(b) Calculate the TA ratio for each product.
Solution (a)
Product Throughput Output achieved Profit per day
contribution
X $70 6000 420000
Y $90 4500 405000
Z $200 1200 240000
total $1065000
Operating costs ($720000)
$345000
Solution (b)
TA ratio = Throughput per factory hour/Operating costs
per factory hour
Operating costs per factory hour = $720,000/8 = $90,000
Product Throughput per Operating cost TA ratio
factory hour per hour

X $70*1200=$84000 $90000 0.93


Y $90*1500=135000 $90000 1.5

Z $200*600=120000 $90000 1.33


Question
 Growler manufactures computer components. Health and safety
regulations mean that one of its processes can only be operated eight
hours a day. The hourly capacity of this process is 500 units per hour.
The selling price of each component is $100 and the unit material cost
is $40. The daily total of all factory costs (conversion costs) is $144,000,
excluding materials. Expected production is 3,600 units per day.
 Required
 Calculate:
 (a) Total profit per day
 (b) Return per factory hour
 (c) Throughput accounting ratio
solution
 Total profit per day = Throughput contribution – Conversion costs =
(3,600 × (100 – 40) – 144,000) = $72,000
 Return per factory hour =
Sales – direct material costs
Usage of bottleneck resource in hours (factory hours)
=100-40
1/500
Throughput accounting ratio =
Re turn per factory hour
Total conversion cost per factory hour
30000
144000/8
1.67
How can a business improve a throughput
accounting ratio?
Increase sales price per unit
Reduce material costs per unit,
Reduce operating expenses
Improve efficiency, and increase the number of units
or product
Elevate the bottleneck, so that there are more hours
available of the bottleneck resource.

You might also like