Specifications
Outlines
• Definition of specification
• Essentials of Specifications
• Specifications for building works
 Earthwork excavation.
 PCC in bed concrete
 UCRM in footings
 DPC
 Ashlar Masonry
 BBM
 RCC work
 Plastering
 Painting
 Flooring
 Wood work
 Definition of Specification and Essentials
• Description for execution of a particular
  engineering work /manufacture/purchase of
  product.
• Essentials Title of work/product, materials
  list and quality, list of Tools and Plants (T & P),
  workmanship procedure, method of curing,
  protection and dimensioning.
 Specifications for Building Works
 Earth work excavation in Ordinary soil
 Materials: N/A
T& P: Earth movers, trimmers, chisel, boxes,
 marking tools, axe, sheet piles, Hauling vehicles
 (if any)
 Workmanship Procedure (WP):
 Clearance of vegetation in the excavation site,
 loose top soil removed, excavation area top is
 compacted and levelled.
 Line out marking using marking tools
 Excavation executed manually or using earth
  movers and depth of excavation inspected
  frequently till required quantity is reached,
  lead=50m, lift=1.5m
 Dewatering, if required, is carried out before
  start of excavation.
 After the end of excavation, the sides of trenches
  trimmed and made orthogonal.
 Bed of trenches, compacted to remove loose
 soil
 Protection: To avoid collapse of trench, sheet
 piles or shores are given for lateral protection
 of trenches                       TRENCH DEPTH
                                 Sheet
                                 Piles
                                         Bed of Trench
                          Trench width
  Dimensioning: N,L,B,D
 PCC in bed concrete in CC 1:4:8
 Materials: Cement (OPC, Blended), sand (F.M
 2.36, dust and soil free), Coarse Aggregates (CA)
 basalt, angular, 40mm down, water- potable
 quality, admixtures-plasticizers, air entraining
 agents (if any)
 T & P: Trowels, mixers, tarpaulin sheets, boxes,
 guaging boxes 30cm X 45cm X 40cm , steel or
 wooden forms, Tamping steel rod 25mm dia,
 WP:
 Materials are guaged as per mix proportion
  and mixed in dry state thoroughly. CA are
  guaged in guaging boxes, sand guaged in
  boxes WRT 1 bag of cement.
 Water added to dry mix as per W/C ratio
 Mixing time 15 min to 30 min (hand or
  machine mix)
 Steel or timber Forms are fixed in position,
  concrete applied in layers (each layer depth= 1/3 of
  total depth of bed concrete) , each layer is tamped
  25 times using steel tamping rod of diameter
  25mm and length=1.5m, thorughly and uniformly.
 Forms removed after 7 days of application of
  concrete.
Curing; 8 days using wet jute sheets
Protection: No load applied on conc for 21 days
 Dimesioning: N,L,B,D
 UCR masonry in footings in CM 1:6
 Materials: stone (trap, sand stone),cement –
 OPC, Blended, sand: FM 2.36mm, water –
 potable, plasticizers (if any)
 T & P: Line out marking tools, trowels, chisel,
 boxes, tarpualin sheets, Plumb for vertical
 alignment.
 WP:
 Top Surface of bed concrete cleaned and The line
  out for laying stones marked with marking tools.
 Stones are dressed atleast on one face using chisels
 Stones are laid such that height of each layer ht not
  more than 20cm, no vertical joints formed
 English bond adopted for laying
 Through stones are used at every 1/3 rd height.
 Stone chips not used and joint thickness not
  exceeds 15mm
 Raking back adopted for work progress.
 Curing: 8 days
Protection; No load applied on footings for next 15
  days
Dimensions; physical meas of N, L , B, D (C/S
  dimensions)
 2.5cm thick D.P.C in CC 1:1.5:3
 Materials: cement, sand, CA (10mm down),
 impermo or damp proofing agent of approved
 quality , admixtures (plasticizers, air entraining
 agents of approved quality), potable water.
 T & P; Trowels, guaging boxes, mixers, boxes,
 steel tray, tamping rod, forms, sand paper, wire
 brush
 WP: The top surface of footings are cleaned
If required sand paper and wire brush used.
 Joints of footings top are filled with 12mm thick
   cement sand mortar, 1;6 throughout and the
   footing surface made plain
 Forms are fixed and plugged.
 Mixing of materials done in dry state as per mix
   proportion, mixing duration 15min, DPC agent
   added @ rate of 3.5kg/cement bag, for mixing,
   trowels, tray and boxes used.
 Water added as per W/C ratio
 DPC applied to full width of plinth in 3 layers
  and each layer tamped 25 times using tamping
  rod.
 Curing: 8 days, wet jute sheets used
 Protection: DPC coat covered with water
  proof sheets for 15 days and no load applied
 Dimensiong: N, L,B (plinth width)
 Ashlar Masonry : Same as UCRM, but height of each
 layer not exceed 15cm in any case and all faces of
 stone are dressed orthogonal and joint thickness not
 exceed 5mm.
 BBM in CM 1:6
 Materials: Burnt bricks of size 200mm X 100mm X
 100mm (brick strength not less than 3.5 N/mm 2 ,
 cherry red colour, free from defects, ringing sound,
 water abs % <15%, adequate frog depth) cement,
 sand , water
T& P: scaffolding materials (wood or steel
  type), trowels, tarpaulin sheets, plumb, neils,
 WP;
 Soaking of bricks in potable water for 48
  hours before put for use.
 Soaked bricks laid in English bond , vertical
  alignment obtained through plumb
 Broken bricks not used
Each layer laid such that, Vertical joints not formed. Joint
 thickness less than 6mm.
Scaffolding provided for masonry height more than 1.5m
Curing: Done with potable water for 8 days
Protection: Scaffolds used for protection for next 15 days
 and no load applied in this period.
Dimesioning: N,L,B (Wall thcikness) ,D (ht of SS),
•
 RCC work in Slab in CC 1:2;4
 Materials; Cement (OPC, Blended), CA (basalt,
 angular, less than 10mm size), Sand (FM 2.36, dust
 free, organic matters free, soil free), potable water,
 tor steel as per approved quality , binding wires,
 linseed or mustard oil
 T & P: Mixers (min 35 liters capacity), needle
 vibrator equipment, bar bending and cutting tools,
 drillers, forms, scaffolds of approved
 quality, neils, tamping rod, guaging box, box
 WP:
 Form work of approved quality is provided (form
  work plate thk not less than 40mm, props dia not
  less than 10cm, props supported on wedges 0.45m X
  0.45m , diagonal braces provided), neils used to
  connect forms
 Reinforcement provided with tor steel with threads
  bars, with appropriate bent, lap, hook lengths and
  spacing (As per drawing). Bar bending done as per
  drawing, using tools.
 Bars are tied using binding wires.
 Appropriate clear cover, joints and side covers
  provided. (CC-15mm for slab, 30mm for beam)
 Gauging of materials as per mix proportion, in
  dry state, mixed thorougly and filled in mixer,
  mixing period not less than 20min, water
  added as per W/C ratio, admixtures are added
  as per requirement
 Concrete mix poured in the forms in layers and each
 layer compacted using vibrators for 10mins, and then
 tamped for 25 times
 Curing: 28 days , impounding curing techniq
Protection: Form work not remove until 28 days of
 casting, no load applied in this period, to remove form
 work oil is used to avoid hitting of edges, shuttering
 plates removed first, followed by removal of centring
 plates.
Dimesioning: L,BD (slab depth)
 Plastering 25mm thick in CM 1;6
 Materials: cement, sand, air entraining agents,
  water (potable)
 T & P; Floats, trowels, steel brush, sand paper,
 WP;
 Rough coat: The joints of brick masonry are raked
  to 2cm depth, full surface cleaned and made wet.
  Dubbing out done and dots formed on the
  surface for plastering
 cement and sand mixed as per mix proportion, if
  required admixtures added, 30 min mixing, water
  added as per W/C
 Mortar applied b/w dots and on dots and spread,
  pressed with floats, trowels and levelled
 Ist coat allowed to dry for 3 days (8mm thk)
 2nd coat (Brown coat) applied after dashing and
  cleaning first coat. Dots formed and plaster coat
  applied and rubbed with floats ( 6mm thk)
 Float coat (5mm thk) Applied after 2nd coat
 dries up , using trowels and float.
 Finishing coat (4mm thk) Applied after float
 coat dries up and rubbed with pumice stone
 to give finished surface.
 White Washing: Materials; Primer white, thinner,
 T & P: Approved quality brush, scaffolds, ladder,
  paint roller
 WP: Primer mixed with thinner as per
  requirement , applied on plaster surface which is
  prepared (plastered surface cleaned and dried)
  using paint brushes in H & V directions, allowed
  to dry, 2nd coat applied subsequently after the 1st
  coat dries and then rolled.
 Protection: Surface protected from external
 contact for 15 days after application
 Dimensioning: Length X height, Breadth X
 height. Breadth X Length (ceiling white wash)
 20mm thick granite (natural red) tiled Flooring
  polished and laid on 7.5cm thick bed concrete in
  CC 1:4:8;
 Materials: Granite tiles (natural red), cement,
  sand, CA, polishing powder, potable water
 T & P: Polishing machine, tile cutter, trowel, tray,
  box , guaging boxes, Mixer
 WP: Guaging of materials as per mix proportion
  of bed concrete, mixing of materials
Section of Granite Tiled Flooring
                             20mm thk
                             Granite Tiles
                                6mm thk
                                mortar bed in
                                CM 1:4
                           Concrete bed
                           7.5cm thick cc
                           1:4:8
                           Plinth with
                           earth fill
 Application of concrete (bed conc) in 3 layers
  on the earth filled plinth surface and tamping
  for 25 times, each layer
 Application of 6mm thick mortar bed on the
  levelled bed concrete surface
 Cutting of granite tiles each of size 0.45m X
  0.45m , thickness=0.02m and placing the tiles
  on the mortar bed
• For ceramic tiled flooring, white cement putty
  will be used.
• For grill work in windows or doors, the steel
  frame is fixed into wooden frame of doors or
  windows wherein, using drilling machines the
  holes are drilled in the wooden frame and the
  steel frame is fastened to the wooden frame
  using washers, nuts and bolts.
 Application of polishing agent on the granite tiled
  surface, followed by rubbing with polishing
  machine.
 Curing: 10 days curing is done with wet jute bags
 Protection: Load not applied on the floor upto
  15 days after laying of floor
 Dimensions: LRoom length, BRoom
  breadth, area of room
 0.63mm thick corrugated tin sheet roofing on
  rooms
                 Corrugations
        Corrugations
        Materials: Tin sheet roof of size 2.1m X 1m size,
         thickness =0.63mm, limpet washers, nuts,
         bolts, steel angle sections, base plate, gusset
         plates, cement, CA, Sand, hollow circular steel
         sections of thcikness 2mm and diameter
         50mm , height=2.5m, Metal paint
 T & P: Drilling machine with drill bits, welding
  machine, trowels, axe, measurement and
  marking devices, screw drivers, paint brush
 WP: Marking of positions for erection of steel
  circular sections of height 2.5m
 Earthwork excavation in ordinary soil, laying of
  bed concrete and erection of concrete
  pedestal of height 0.2m AGL
 Fixing of circular sections on concrete pedestrals
  using rivets, nuts, bolts
 Fixing of angle sections to the circuclar sections to
  form common rafters and welding of angle sections
  in lateral directions to form purlins
 Fixing of tin sheet to the common rafter using
  washers, nuts and bolts, such that each tin sheet
  overlaps another tin sheet by 30% sides. Follwed by
  fixing of crown head covers at the central portion.
 This is followed by painting with 2 coats of
 metallic paint
 Curing:1 week curing for concrete pedestrals
Protection: No load applied, and side tin
 sheets provided and to avoid detachment of
 tin sheet from wind current
 Dimensioning: L (Span+ wall thk+proj length)X
 secθ X Longer span