Supply and Demand
SCAP101
Lesson 9
Master Production Schedule
Attainment
Shop Floor Control
1 SCM 5001
Agenda – Supply & Demand
Check in
Master Production Scheduling
Attainment
Capacity Planning
2 SCM 5001
Learning Objectives
Describe master production scheduling (MPS) process
Describe purpose for time fences
Describe purpose and activities associated with Shop Floor Control
Describe KPIs used to measure shop floor performance
Define capacity, design capacity, effective capacity
Define and calculate utilization, efficiency
Calculate effective capacities
Define capacity planning and describe techniques
Discuss strategies for adding capacity
3 SCM 5001
The Big Picture ... Inventory Management
Production Distribution
Aggregate Plan
S&OP Process
Master Production Schedule Independent Demand:
(MPS) Re-Order Point Systems
Material Requirements EOQ
Planning (MRP) Safety Stock
Shop Floor Control; e.g., Dependent Demand:
kanban Distribution Requirements
Planning (DRP)
4 SCM 5001
Master Production Schedule (MPS)
Schedule of planned production in the near term:
Defines what needs to be manufactured over a near term horizon,
generally 6-8 weeks out.
Consistent with the constraints of the Aggregate Plan (S&OP).
The MPS contains item level data in either weekly or daily buckets:
Forecasted demand
Production
Projected on-hand inventory
The requirements from DRP become Forecasted Demand for the MPS.
Item-level schedules need to be summed to assess availability of
materials, labour, machine capacity, other constraints…..“finite scheduling”
produces a “feasible MPS”, one that is expected to be attainable.
5 SCM 5001
A sample MPS
Master Production Schedule for Make-to-Stock (MTS) Item - Dining Room Table
Week Starting Nov.2 Nov. 9 Nov.16 Nov.23 Nov.30 Dec. 7 Dec. 14 Dec. 21 Dec. 28
DEMAND 30 30 35 35 35 40 40 30 30
PRODUCTION 48 48 0 48 48 48 0
PAB (INVENTORY) 44 62 80 45 58 71 79 39
ATP 62 80 45 58 71 79 39
BACKLOG 0 0 0 0 0 0 0
TARGET MINIMUM
STOCK LEVEL 6 FDS 37 42 42 43 48 46 36
Working Days/Week 5
Lot Size 48 Demand Time Fence Planning Time Fence
Opening Inventory
FROZEN ZONE (FIXED)
SLUSHY ZONE (FLEXIBLE)
LIQUID ZONE (PLAN) Positions of time fences vary with flexibility of operation, leadtimes of raw materials.
PAB - Projected Available Balance
master production schedule.xls
6 SCM 5001
Where are we?
Production
Requirements
Aggregate Plan From Tactical to Operational
Master Production Schedule From Family to Item
(MPS)
From Medium term to Short
Shop Floor Control (SFC) Term
7 SCM 5001
What is Shop Floor Control (SFC)?
SFC can be considered short term scheduling. Its objective:
Allow MPS to be met.
Keep labour costs low.
Ensure effective utilization of equipment, people, facilities, etc. » load leveling
Prioritize orders: production orders, rework, salvage, engineering samples (all consume
resources)
SFC is the interface between planning and execution systems in near-term; it includes
feedback loop.
SFC manages resources:
Machine capacity and Tooling
Labour and Materials
Information (for example, time standards)
Routing and alternate routings…sequencing and resources
Rescheduling as a result of expedites, problems
8 SCM 5001
How we measure SFC: Schedule Attainment
Schedule Attainment KPI is a measure of shop floor effectiveness
Schedule Attainment = Orders Completed on Time /
Orders Scheduled
Quantity tolerance…plus and minus small percentages
Non-compliance requires Corrective Action Plan (CAP)
Why is schedule attainment important?
9 SCM 5001
Schedule Attainment Example
Production Week: 10 Workcentre #8
Tolerance: Plus 2%
Minus 3%
Upper Qty Lower Qty. Schedule
Order Sched. QTY. Allowed Allowed Transferred QTY. Attained
108 1800 1836 1746 1850 N
110 1400 1428 1358 1402 Y
105 900 918 873 890 Y
109 160 163 155 160 Y
117 800 816 776 800 Y
114 720 734 698 680 N
120 480 490 466 480 Y
107 2400 2448 2328 2360 Y
115 3600 3672 3492 3580 Y
104 400 408 388 0 N
12660 12202
Schedule Attainment 70%
Target 90%
In Compliance No
Consecutive Weeks not in
Compliance (Max.3) 4
CAP Required Yes
Example: Sa.xls
10 SCM 5001
Other Key Performance Measures for Shop
Floor Control
Raw material inventory accuracy
BOM accuracy
Schedule changes within fixed (frozen) zone
11 SCM 5001
Capacity Planning
12 SCM 5001
13 SCM 5001
Capacity defined …
The capability of a system to perform its expected function.
(APICS – See citation in Appendix)
For a production environment, in quantitative terms, it is the
amount of product that can be produced in a given period of time.
For planning purposes we use EFFECTIVE CAPACITY
Capacity concepts apply in other areas of the
supply chain: automation, equipment, docks, …
14 SCM 5001
Design Capacity versus Effective Capacity
Design Capacity
Loss of capacity because not
fully utilized..maintenance, lunch
breaks, planned setups (Utilization)
Loss of capacity because of
quality problems, breakdowns,
interruptions (Efficiency)
Effective or Rated Capacity
15 SCM 5001
Measuring Capacity – Design Capacity
What is the maximum throughput we can achieve?
NxHxSxD
Design Capacity (for interval) =
T
Where N = number of resources (machines, operators)
H = hours worked per shift
S = shifts per day
D = days worked (in interval..days, weeks, months, or year
T = time in hours to make one unit of product
based on machine or operator speed (cycletime)
Design Capacity also known as Maximum Capacity.
16 SCM 5001
Example – Design Capacity
NxHxSxD
Design Capacity (for interval) =
T
17 SCM 5001
Example – Utilization in a 7/24 Operation
18 SCM 5001
Example - Efficiency
19 SCM 5001
Example – Effective Capacity
What is the effective throughput we can achieve, allowing for
utilization and efficiency?
Using data from our previous calculations:
Effective Capacity = Design Capacity x Utilization(%) x Efficiency(%)
= 16,320 x 87% x 75%
= 10,649 Units/Year
Also known as Rated Capacity.
Why is effective capacity important?
20 SCM 5001
Capacity Planning
The process of determining the amount of capacity
required to produce in the future.
(APICS – See citation in Appendix)
Objective:
Match available capacity to forecasted demand over
the long, medium, and short terms.
Context:
Feasibility of the MPS and the MRP plans …
21 SCM 5001
Levels of capacity planning:
Strategic Capacity Planning
Strategic Decisions
Facility expansion, closure
Technology change
Major equipment acquisition
Long time horizon
Large expenditures
Sales forecasts are critical
This long range or strategic planning is sometimes called
resource planning or resource requirements planning (RRP).
22 SCM 5001
Levels of capacity planning:
Tactical and Operational
Typical Decisions required:
Number of shifts per day, length of shifts, number of
scheduled days per week
Overtime…when, number of extra hours, full or partial
crews
Equipment purchases…when, output rate
Sub-contracting…which products, how long to set up,
additional administrative and transportation costs
Rough Cut Capacity Planning (RCCP), driven from the MPS, tends
toward medium term, tactical view.
Capacity Requirements Planning (CRP), driven from MRP, tends
toward short term, operational view.
23 SCM 5001
Where does Capacity Planning fit?
Long Range Resource Sales and operations Demand
planning planning management
Resource planning
Master production
Rough-cut capacity
scheduling
planning
Medium Range
Detailed material
Capacity requirement planning
planning
Material and
Short Range
capacity plans
Finite Loading
Input/output analysis Shop-floor Supplier
systems systems
Vollmann, Thomas E. et al. (2005). Manufacturing Planning and Control Systems for Supply
Chain Management, 5th Edition. New York, NY: McGraw-Hill.
24 SCM 5001
Strategies for Adding Capacity
Decisions about Timing:
Lead the Demand
Match the Demand
Lag the Demand
Decisions about the Amount to Add:
Large
Small
Considerations:
Lost sales
Inefficient operations
Overtime costs
Disruptions to operations while capacity added
Cost of capital
Risk
25 SCM 5001
Recap
The MPS is the link between production (supply) and the
demand of our distribution network.
Through the MPS, item level production requirements are
specified.
Shop Floor Control is the short term scheduling of
production requirements.
In addition to materials, capacity must be planned in
order to meet our production requirements.
Capacity planning is essential to ensure a feasible MPS.
26 SCM 5001
Appendix
References: