This document provides a cost estimate for an 11kV HT service connection for a load of 70kVA to 1000kVA with a DP structure arrangement. The total cost is estimated to be Rs. 3,13,110. The estimate includes costs for items like the DP structure, isolating switches, 11kV metering equipment, 11kV XLPE underground cable, line arrestors and earthing materials. Additional costs include storage and handling charges, contingencies on materials, labour and transport charges, GST and establishment charges.

Uploaded by

BADRI VENKATESH
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
150 views1 page

SOR

This document provides a cost estimate for an 11kV HT service connection for a load of 70kVA to 1000kVA with a DP structure arrangement. The total cost is estimated to be Rs. 3,13,110. The estimate includes costs for items like the DP structure, isolating switches, 11kV metering equipment, 11kV XLPE underground cable, line arrestors and earthing materials. Additional costs include storage and handling charges, contingencies on materials, labour and transport charges, GST and establishment charges.

Uploaded by

BADRI VENKATESH
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

67.

COST DATA FOR 11KV HT SERVICE CONNECTION OF LOAD 70KVA TO 1000KVA WITH DP STRUCTURE
ARRANGEMENT
Sl. Rate Amount
SAP Code Particulars Qty. Per Unit
No. in Rs. in Rs.
1 DP Structure with 9.1Mts PSCC Poles 2 30485 Each 60970
PLS00004 a) 9.1 mts PSCC poles 4 13098
FBR10013 b) DP Structure Material Total Set 2 15647
FBR10010 c) MS Stay sets Complete with base plate 4 1504
FBR00004 d) MS Stay Clamps 4 235
2 Isolating Switches 2 18377 Each 36754
ABS10004 a) 11 KV,200A Horizontal AB Switch 2 14826
HGF10002 b) 11 KV HG Fuse set 2 3552
3 11 KV Metering Equipment (HT Metering) 1 59896 Each 59896
ITR10030 a) 11 KV CT PT 10-20/5 A 1 42841
MHT10003 b) HT Trivector Meter (Class 0.2 S) 1 4589
OMT10049 c) AMR Unit with modem for communication 1 5994
BXS00004 d) Special type HT meter box 1 4515
CBP00002 e) Coper control cable 4 x 2.5 sqmm for wiring 30 1957
4 11 KV 3 Core XLPE UG Cable 1 51154 Each 51154
CBX10005 a) 11 KV upto 3x95 sqmm XLPE UG Cable 30 19841
b) End termination kits suitable for 95 sq.mm XLPE UG Cable
SCB10037 2 19799
(outdoor type)
c) End termination kits suitable for 95 sq.mm XLPE UG Cable
SCB10038 2 11514
(indoor type)
5 11 KV LAS & Earthing 1 2672 Each 2672
LAS00001 a) 11 KV metal oxide 5 KA Las (line type) 3 1037
EMT00020 b) GI Earth pipe 40 mm (2.5 mts. Length) 3 1635

6 Misc. items viz. link clips,wooden box, bolts & nuts, bends etc LS 605 LS 605
Total 211446 2,12,051
3% storage & handling charges on items (1) to (5) 6,343
3% Contingencies on Materials 6362
Labour & Transport 52,862
GST @ 18% on Labour & Transport 9515
1% Cess 2649
11% Estt. & Genl. Charges 23,326
Total Cost in Rs. 3,13,107
Or say : 3,13,110