Contractor Performance Evaluation Questionnaire
Please complete this set of questions prior to starting your evaluation to ensure the evaluation template is
customized to suit your particular project and / or the stage you are at in your project.
Is this the Final Evaluation or an Interim Evaluation?                                          Final
Have there been any Change Orders?                                                              Yes
Have any submittals (other than the baseline schedule) been required from the Contractor yet?   Yes
Have there been any deficiencies?                                                               Yes
Has testing commenced and/or completed?                                                         Yes
Were there any incidents/accidents involving the General Public?                                Yes
Has the Contractor received any written notices?                                                Yes
Have there been any service delivery issues (ie/ complaints, inquiries, claims)?                Yes
Was there a Contractually or Region approved start date the Contractor was to meet?             Yes
Was a Traffic Control Plan Required?                                                            Yes
Were there any Safety Issues?                                                                   Yes
Were any stop work orders issued by the Region, MOL, TSSA, other Agencies?                      Yes
Were there any environmental requirements as part of the work including but not limited         Yes
Conservation Authority, PTTW, MNR, MOE, etc?
Does project close-out require Operations and Maintenance Manuals and / or record documents     Yes
and drawings to be submitted by the Contractor?
After completing these questions please move on to the Contractor Evaluation tab to evaluate your contractor.
Page 3 of 3
Contractor Performance Evaluation
Document Number:                               Contractor Name:
Division:
Description:
(as per document)
Contract Start Date:                                                Substantial Performance Date:
Evaluation Type:        Final
ItemWeight Score Criteria                                                                   Evaluation Guide
    5      0.0   Project Commencement (5%)
1 2        0.0   Did the project commence by the contractually obligated date or
                 Region agreed/revised start date?
2   3         0.0   Was an acceptable baseline schedule (inclusive of key tasks,
                    activities, subs, etc.) provided at the pre-construction meeting (or
                    within the agreed upon timeframe)?
    13        0.0   Project Management (13%)
3   3         0.0   Did the Contractor maintain comprehensive schedule updates and
                    provide updates as required?
4   3         0.0   Did the Contractor meet the project milestones by the contractually
                    obligated date or any other agreed-upon dates?
5   4         0.0   Did the Contractor provide timely notification to appropriate
                    stakeholders, as required (e.g. all Peel Operations, residents, etc)?
6   3         0.0   Did the Contractor submit the required shop drawings and
                    submittals on-time and in the proper formats (e.g. mix designs,
                    commissioning plan, etc.)?
    31        0.0   Workmanship (31%)
7   3         0.0   Did the Contractor comply with all permit requirements and
                    agreements (e.g. Road Occupancy, MTO Encroachment, etc)?
Page 2 of 3
8   3         0.0   Did the Contractor install and maintain all environmental measures
                    as per Contract and Permit requirements (e.g. Conservation
                    Authority, PTTW, MNR, MOE, etc.), and mitigate all identified
                    environmental site issues in a timely manner?
9   2         0.0   Did the Contractor cause any damage to existing facilities,
                    properties (City, Region or private), sites, etc?
10 2          0.0   Did the Contractor comply with the allowable working hours as
                    specified in the Contract or as approved by the Agency?
11 3          0.0   Was the equipment utilized by the Contractor for the completion of
                    the work appropriate for the required work?
12 3          0.0   Did the materials (including equipment to be installed) supplied by
                    the Contractor meet the Contract specifications?
13 3          0.0   Did the Contractor stage the work in an appropriate manner to
                    achieve the Contract requirements?
14 3          0.0   Did the Contractor supply appropriate staff for the required work
                    and / or did the staff have the appropriate skills, training and
                    licenses required?
15 3          0.0   Did the Contractor effectively coordinate with other Contractors,
                    Consultants, Sub-Contractors and Suppliers as applicable?
16 3          0.0   Did the Contractor resolve deficiencies identified during
                    construction in a timely manner and to the satisfaction of the
                    Agency?
17 3          0.0   Did the Contractor pass the minimum testing requirements (e.g.
                    pressure testing, leakage test, FAT, SAT, Compaction, Material
                    Testing, etc.)?
   21         0.0   Safety (21%)
18 3          0.0   Did the Contractor keep the site (and access roads) reasonably
                    clean and organized throughout the duration of the project?
19 2          0.0   Did the Contractor consistently follow the submitted Traffic Control
                    Plan (as amended throughout Contract) which was inclusive of
                    OTM Book 7 Temporary Conditions?
Page 3 of 3
20 1          0.0   Did the Contractor submit a acceptable Safety Plan in a timely
                    manner prior to commencement and keep a copy on-site for the
                    Contract duration?
21 1          0.0   Did the Contractor keep the NOP and Form 1000 for each sub-
                    contractor in an accessible location on site?
22 1          0.0   Did the Contractor keep these notices in an accessible location on
                    site; OH&SA, Construction Regs, Nearest MOL office, First Aid
                    Regs, WSIB Poster (Form 82), H&S Policy, MSDS, Emergency
                    Procedures, etc.?
23 2          0.0   Did the Contractor obtain up to date locates for all utilities and were
                    they kept up to date throughout project duration, while adhering to
                    all locate conditions?
24 2          0.0   Did all Contractor and sub-contractor staff wear the required PPE at
                    all times?
25 3          0.0   Did the Contractor take immediate Action to rectify safety issues?
26 2          0.0   Did the Contractor maintain, as required, clear emergency Routes
                    and control public access?
27 2          0.0   As required, did the Contractor deal with incidents / accidents to the
                    General Public and report to the Region in a timely manner?
28 2          0.0   Did the Contractor comply with any stop work orders issued by the
                    Region, MOL, TSSA, other Agencies?
   16         0.0   Contract Management and Supervision (16%)
29 3          0.0   Did the Contractor submit an unjustifiable number of invalid change
                    order requests?
30 3          0.0   Did the Contractor submit reasonable and competitive quotations
                    for extra work, in a timely manner?
31 2          0.0   Did the Contractor follow the contractual claims procedure?
32 3          0.0   Did the Contractor comply with any written notices by the Agency in
                    a timely manner (e.g. site instructions, change directives, etc.)?
Page 2 of 3
33 2          0.0   Did the Contractor submit payment requests accurately which were
                    inclusive of WSIB and Statutory declaration for each invoice
                    submitted?
34 3          0.0   Did the Contractor have the appropriate authority on site to make
                    decisions and provide continuous on-site supervison to workers?
   6          0.0   Client and Public Relations (6%)
35 3          0.0   Did the Contractor respond appropriately to service delivery issues
                    (complaints, inquiries, third party claims, etc.)?
36 3          0.0   Was the Contractor fair and did they conduct themselves with
                    common courtesy and appropriate business manner when dealing
                    with the Public, Agency staff / representatives, and own employees
                    (including; properly identifing themselves to the Public and Agency
                    staff as required)?
   8          0.0   Project Completion (8%)
37 4          0.0   Did the Contractor submit on schedule complete Operations and
                    Maintenance Manuals as well as accurate and / or complete record
                    documents and drawings?
38 4          0.0   Did the Contractor meet the Substantial Performance by the
                    contractually obligated date or revised agreed-upon date?
Did the Contractor meet             Comments:
Comments:
TOTAL PERCENTAGE 0.00%
Contractor Rating
Approval Required
Region's Project                                                                          Date:
Manager Name:
Region's Project
Manager Signature:
Approval Name:                                                                            Date:
Approval Signature:
Page 3 of 3
    Please send all signed final evaluations to vendorperformance@peelregion.ca
    V-20180305
Page 2 of 3
Comments
Page 3 of 3
Page 2 of 3
Page 3 of 3
This sheet provides a space for project managers to log additional comments, it is recommended to use when there
Item Critiera
1    Did the project commence by the contractually obligated date or Region
     agreed/revised start date?
2    Was an acceptable baseline schedule (inclusive of key tasks, activities,
     subs, etc.) provided at the pre-construction meeting (or within the agreed
     upon timeframe)?
     Project Management
3    Did the Contractor maintain comprehensive schedule updates and provide
     updates as required?
4    Did the Contractor meet the project milestones by the contractually
     obligated date or any other agreed-upon dates?
5    Did the Contractor provide timely notification to appropriate stakeholders,
     as required (e.g. all Peel Operations, residents, etc)?
6    Did the Contractor submit the required shop drawings and submittals on-
     time and in the proper formats (e.g. mix designs, commissioning plan,
     etc.)?
     Workmanship
7    Did the Contractor comply with all permit requirements and agreements
     (eg. Road Occupancy, MTO Encroachment, etc)?
8    Did the Contractor install and maintain all environmental measures as per
     Contract and Permit requirements (e.g. Conservation Authority, PTTW,
     MNR, MOE, etc.), and mitigate all identified environmental site issues in a
     timely manner?
9    Did the Contractor cause any damage to existing facilities, properties (City,
     Region or private), sites, etc?
10   Did the Contractor comply with the allowable working hours as specified in
     the Contract or as approved by the Agency?
11   Was the equipment utilized by the Contractor for the completion of the
     work appropriate for the required work?
12   Did the materials (including equipment to be installed) supplied by the
     Contractor meet the Contract specifications?
13   Did the Contractor stage the work in an appropriate manner to achieve the
     Contract requirements?
14   Did the Contractor supply appropriate staff for the required work and / or
     did the staff have the appropriate skills, training and licenses required?
15   Did the Contractor effectively coordinate with other Contractors,
     Consultants, Sub-Contractors and Suppliers as applicable?
16   Did the Contractor resolve deficiencies identified during construction in
     a timely manner and to the satisfaction of the Agency?
17   Did the Contractor pass the minimum testing requirements (e.g. pressure
     testing, leakage test, FAT, SAT, Compaction, Material Testing, etc.)?
     Safety
18   Did the Contractor keep the site (and access roads) reasonably clean and
     organized throughout the duration of the project?
19   Did the Contractor consistently follow the submitted Traffic Control Plan (as
     amended throughout Contract) which was inclusive of OTM Book 7
20   Temporary Conditions?
     Did the Contractor submit a acceptable Safety Plan in a timely manner
     prior to commencement and keep a copy on-site for the Contract duration?
21   Did the Contractor keep the NOP and Form 1000 for each sub-contractor
     in an accessible location on site?
22   Did the Contractor keep these notices in an accessible location on site;
     OH&SA, Construction Regs, Nearest MOL office, First Aid Regs, WSIB
     Poster (Form 82), H&S Policy, MSDS, Emergency Procedures, etc.?
23   Did the Contractor obtain up to date locates for all utilities and were they
     kept up to date throughout project duration, while adhering to all locate
     conditions?
24   Did all Contractor and sub-contractor staff wear the required PPE at all
     times?
25   Did the Contractor take immediate Action to rectify safety issues?
26   Did the Contractor maintain, as required, clear emergency Routes and
27   control publicdid
     As required,   access?
                       the Contractor deal with incidents / accidents to the
     General Public and report to the Region in a timely manner?
28   Did the Contractor comply with any stop work orders issued by the Region,
     MOL, TSSA, other Agencies?
     Contract Management and Supervision
29   Did the Contractor submit an unjustifiable number of invalid change order
30   requests?
     Did the Contractor submit reasonable and competitive quotations for extra
     work, in a timely manner?
31   Did the Contractor follow the contractual claims procedure?
32   Did the Contractor comply with written notices by the Agency in a timely
     manner (e.g. site instructions, change directives, etc.)?
33   Did the Contractor submit payment requests accurately which were
     inclusive of WSIB and Statutory declaration for each invoice submitted?
34   Did the Contractor have the appropriate authority on site to make decisions
     and provide continuous on-site supervison to workers?
     Client and Public Relations
35   Did the Contractor respond appropriately to service delivery issues
     (complaints, inquiries, third party claims, etc.)?
36   Was the Contractor fair and did they conduct themselves with common
     courtesy and appropriate business manner when dealing with the Public,
     Agency staff / representatives, and own employees (including; properly
     identifing themselves to the Public and Agency staff as required)?
     Project Completion
37   Did the Contractor submit on schedule complete Operations and
     Maintenance Manuals as well as accurate and / or complete record
38   documents  and drawings?
     Did the Contractor meet the Substantial Performance by the contractually
     obligated date or revised agreed-upon date?
nal comments, it is recommended to use when there are performance issues.
          Additional Comments