SITE SURVEY REPORT Date: 10, 11 &12-11-2019
PROJECT INFORMATION
: AL FATTAN DOWNTOWN DEVELOPMENT 3 TOWERS COMMERCIAL AND
Project Name
RESIDENTIAL DEVELOPMENT
Location : SATWA
Plot No. : 3340109
Client : AL FATTAN PROPERTIES
Consultant : AE7
Main Contractor : AECOM
MEP Contractor : ALI MOUSA & SONS CONTRACTING
MEP Engineer : ENG SHADI/SALIM/GOUDAI/MANSOUR
S/N Level Inspected
1 TOWERS 1, 2 & 3 – SPRINKLER AND FIREFIGHTING SYSTEMS
NOTES:
THIS SITE SURVEY REPORT IS BASED ON SITE CONDITIONS DURING THE
DATE OF INSPECTION.
THE OBSERVATIONS DOCUMENTED WITHIN THIS REPORT DEPICTS THE SITE
INSTALLATION DONE TILL THE DATE OF SITE SURVEY.
ALL AVAILABLE MATERIAL DETAILS SUCH AS CERTIFICATIONS (MATERIAL IS
LISTED/APPROVED), HANDLING & STORAGE CONDITIONS WILL BE THE
RESPONSIBILITY OF THE MEP CONTRACTOR
Reviewed by : NAFFCO NAFFCO Sales
NAFFCO Inspectors
Technical Manager Manager
OMAR ANSAR
MOHAN SHAN
ABED AL MAJEED
Sheet 1 of 12
PROJECT : AL FATTAN DOWNTOWN DEVELOPMENT 3 TOWERS COMMERCIAL
AND RESIDENTIAL DEVELOPMENT
MEP CONTRACTOR : ALI MOUSA & SONS CONTRACTING
INSPECTION COMMENTS
TOWER 1
Site condition:
Ground floor - Breaching inlet installation pending
Site condition:
Ground floor – Fire hydrants installation pending.
Mosque:
Site condition:
Ground floor to level 7 – Fire hose cabinet installation in progress.
Site condition:
Ground floor to Level 7- Wet risers installation completed.
Site condition:
Level basement 02 to Podium 4 – Ramp areas – Sidewall sprinkler branches installation partially completed.
Site condition:
Ground floor – Main reception and lift lobby – Sprinkler system – Final fix – Cross main, branches, droppers and
zone control valve assembly installed. Mosque, etc. Installation pending.
Site condition:
Ground floor to Podium 4 : Sprinkler systems – Zone control valve assemblies installation pending. Cross main
and branches installation in progress.
Site condition:
Level 7 to level 17 - Fire hose, landing valves and accessories installation pending in one shaft
Site condition:
Level 5 to 17 – Sprinkler systems – Final fix installation status- 79 degree upright sprinklers installed above false
ceiling and pendant/sidewall sprinkler droppers completed. Zone control valve installation completed.
Site condition:
Level Ground to 17 – Garbage chute risers and branches installation completed.
Site condition:
Level 18 – Mechanical floor - Sprinkler and fire fighting systems not installed. Fire pump not installed.
Site condition:
Roof, Level 17, Level 6 & Level 5 – Top of risers – Air release valve, pressure gauges and globe valves installation
pending.
Site condition:
Level 32 – Mechanical floor – Sprinkler and firefighting installation pending.
Site condition:
Level 30 & 31 – Sprinkler system – Cross main and branches piping installed. Droppers installation pending.
Site condition:
Level 22 to 29 - Cross main and branches piping installed. Droppers installation pending.
Site condition:
Roof – Special , sprinkler and firefighting systems not installed
Site condition:
Basement 02 to Podium 4 - Sprinkler system – Cross main and branches piping installed. Droppers installation
pending.
Site condition:
Basement 02 - Fire pump set – Suction & discharge piping and equipment with PRV
station done.
TOWER 2
Site condition:
Ground floor - Breaching inlet installation pending
Site condition:
Ground floor – Fire hydrants installation pending.
Site condition:
Level 19 to 32 – Garbage chute riser and branches installed
Site condition:
Roof – Special , sprinkler and firefighting systems not installed
Site condition:
Level 32 – Mechanical floor – Sprinkler and fire fighting systems not installed
Site condition:
Level 19 to 30 – Fire hose, landing valves and accessories installation pending in one shaft
Site condition:
Level 18 – Mechanical floor - Sprinkler and fire fighting systems not installed. Fire pump not installed.
Site condition:
Level 6 to 17 – Sprinkler systems – Final fix installation status- 79 degree upright sprinklers installed above false
ceiling and pendant/sidewall sprinkler droppers completed. Zone control valve installation completed.
Site condition:
Level 7 to 17 - Fire hose, landing valves and accessories installation pending in one shaft
Site condition:
Roof, Level 17, Level 6 & Podium 2 – Top of risers – Air release valve, pressure gauges and globe valves
installation pending.
Site condition:
Level 19 to 31-Sprinkler system – Cross main and branches installation completed. Droppers installation
pending.
Site condition:
Ground floor – Main reception and lift lobby – Sprinkler system – Final fix – Cross main, branches, droppers and
zone control valve assembly installed. Mosque, etc. Installation pending.
Site condition:
Level basement 02 to Podium 4 – Ramp areas – Sidewall sprinkler branches installation partially completed.
Site condition:
Basement 02, Basement 01, Podium 01 & Podium 4 - Sprinkler system – Cross main and branches piping
installed. Droppers installation pending.
Site condition:
Level Ground to 17 – Garbage chute risers and branches installation completed.
Site condition:
Podium 02 & Podium 03 – Sprinkler system installation pending.
TOWER 3
Site condition:
Level 5 to 17 – Garbage chute risers and branches installation completed.
Site condition:
Roof – Special , sprinkler and firefighting systems not installed
Site condition:
Ground floor - Breaching inlet installation pending
Site condition:
Ground floor – Fire hydrants installation pending.
Site condition:
Basement 02 to Podium 4 - Sprinkler system – Cross main and branches piping installed.
Droppers installation pending. Zone control valve installation pending.
Site condition:
Level 20 to 24 – Sprinkler droppers done inside flats. Sprinkler cross main and branches
done in corridors and utility rooms. Zone control valve assemblies installed.
Site condition:
Levels 5 to 17 - Sprinkler systems – Final fix installation status- 79 degree upright
sprinklers installed above false ceiling and pendant/sidewall sprinkler droppers
completed. Zone control valve installation completed.
Site condition:
Levels 5 to 17 – Two Wet risers and one sprinkler riser completed
Site condition:
Levels 5 to 17 – One shaft – Fire hose and accessories installation completed
Site condition:
Level 6 – Wet riser looping completed. Gate valve installation pending.
Site condition:
Level 18 & 32 – Mechanical floor – Sprinkler and fire fighting systems not installed
Site condition:
Level basement 02 to Podium 4 – Ramp areas – Sidewall sprinkler branches installation partially completed.
Site condition:
Level 18 – Fire pump set – Only placed on foundation
Quotation required:
All remaining sprinkler & firefighting system equipment (There is no store at site and
material is scattered all over the place. Get exact quantities from the MEP contractor.).
Reviewed by : NAFFCO Technical Manager NAFFCO Inspectors
MOHAN SHAN
OMAR ANSAR
Sheet 12 of 12