Melukote Village Irrigation Project
Melukote Village Irrigation Project
CHAPTER: 1
1.3 INTRODUCTION
1.3.1 GENERAL:
       India is basically an agricultural country. Majority of the people live in village and have agriculture
as their profession. The resources of our country mainly depend on the agricultural output.
       Water is evidently the most vital element in the plant life. Water is normally available to the plants
by rain. However the total rain fall in a particular area may be insufficient are ill termed but in order to get
minimum yield it is very essential to supply optimum quantity of water in the correct time and this can be
achieved by systematic development of an irrigation system that by collecting water during the period of
excess rain fall and distributing the stored water when required to irrigation by distribution system forms the
back bone of agriculture and agriculture is the back bone of our country irrigation systems should be
properly organized and development.
Irrigation is the process of artificially supplying water to soil for raising crops it aims to planning and
designing an effect low cost economical irrigation system to fit natural condition.
       Irrigation engineering includes the study and design of works in connection with river control
drainage of water logged area at generation of hydroelectric power.
Irrigation is an engineering of controlling and harnessing the various natural resources of water with the
constructions of dams reservoirs canals headwork and finally distribution of water to the agricultural field.
   2. The reservoir site should be such that the quantity of leakage through that is minimum.
   3. Suitable dam site should exist it should founded on sound watertight rock base and the percolation
       below the dam should minimum.
   4. The reservoir basin should have a narrow opening in the valley so that the length of the dam is less.
   5. The topography of the reservoir site should that the submerging land must be minimum.
   6. The reservoir should be such that it avoids or excludes water from those distributaries, which carry a
       high percentage of silts in water.
   7. The reservoir site should store maximum quantity of water with minimum submergence of land area
       that the depth of water storage should be maximum.
   8. The soil or rock mass at the reservoir site should not contain any objectionable minerals and salts.
   9. The cost of the reservoirs including road, levelling, relocation etc. must be as less as possible.
   10. The site should have a natural drain on downstream to take off the surplus water.
The site for the new tank project is selected at MELUKOTE village by taking into account all the above
consideration.
       ascertain the centre line alignment of the main bund and also to locate the feasible site for waste
       weir ,tank sluice etc .It is necessary to inspect the project are prior to detailed survey because it is
       very useful in selecting the proper location.
               The plan and design of various works related to the new tank project. On arriving at the site,
       the whole area was examined carefully in order to decide upon the best possible arrangement of
       survey work and for these purpose the minor instruments such as hand level through compass etc.,
       were used to achieve good results a key plan of the area to be surveyed indicating the various
       information’s relating to the site was prepared
   c. Geological Investigation: For any major civil engineering project geological investigation is most
       essential with details. Information like water tightness of reservoir basin suitability of foundation for
       dam. Geological structural features such as folds, faults, fissures etc. From the rock basin type and
       depth of over burden, location of permeable or soluble rocks if any ground water conditions in the
       region and location of quarry site for materials required for the dam are available in this
       investigation.
   d. Engineering Survey: The area of the dam site is surveyed and details and contains plans are
       prepared from the plans. These physical characteristics are prepared such as area from elevation
       curves storage capacity from elevated curve map of the area to indicate the land property to be
       submerged and suitable site selection for the dam.
The following aspects were considered while surveying the area for selecting the proper sites for the various
works related to the project:
   1. The length and height of dam should be less as possible.
   2. The presence of natural diversion channel to carry the surplus water from the main road.
   3. The length and height of waste weir should be as less as possible to achieve economy in its
       constructions.
   4. The presence of hard formation soil for construction of main bund as well as waste weir and tank
        sluice.
   5. Presence of sufficient irrigable land at downstream, and the nature of crops to grown in that area
   6. Existence of good transportation facility for men and materials to the construction site.
   7. The cost of protective works should be minimum.
   8. The labour and material used for construction should be easily available and economical.
   f. Downstream Drainage: Filter zones are invariably provided in all earthen dams. They are
       constructed of materials appreciably more previous than the embankment soil. It helps in reducing
       the pore water pressure in the D/S portion of the dam and also checks the piping.
1.6 ESTABLISHMENT OF BENCHMARK AT SITE:
       Since it is a very long distance to carry a fly level from a bench mark at Pandupura railway station to
the site, the top of Culvert is taken as a arbitrary B.M of RL-966.965 was established using GPS instrument
(Garman GPS72H).The fly level is carried from the arbitrary benchmark to top of the rock boulders
available at both right and left bank of proposed temporary B.M is used to carry out leveling operations for
all the connected survey work for project.
PROCEDURE:
   The following operations are to be carried out in the survey works:
   •   Leveling is started from bench mark established near the bund and point on the centerline of the
       bund is fixed by using theodolite at convenient elevation, then fore bearing of centerline of bund is
       then observed with a prismatic compass and recorded.
   •   Starting from the point on the bund, pegs are driven at every 10m intervals on the (opposite bank)
       centerline bund until the same elevation is reached on the opposite bank and staff readings are taken
       at every peg point on the C.L of bund.
   •   Staff readings are also taken along centerline of the bund at every 30m. Levels on the c/s are taken at
       intervals of 2m to a distance of 20m on the U/S and D/S.
   •   The staff reading chainages, traverse measurements for sections is methodically entered in the
       leveling book.
DRAWINGS SUBMITTED:
   1. Longitudinal section and plan
   2. Cross section at every 5m chainage interval
   3. Typical cross section of earthen bund.
PLOTTING ON SHEET:
      The north line marked on the sheet by the bearing taken on the north direction.
      The centreline is marked on the sheet by the bearing taken with respect to north line.
      The scale is so assumed that all the points are carried in a single sheet.
A ray is drawn from the previous point marked the sheet by the measure bearing and as once of 30m to scale
to cut on the ray and the point is obtained continue the same procedure till all the entered bearing marked on
the sheet.
CALCULATION:
       The reservoir capacities are calculated below:
  Sl. No.                     Contour                 Area (m2)
  1                           TBL                     19588.9361
  2                           MWL                     17463.0362
  3                           FTL                     14161.9701
The area of contour may be estimated by using “AUTO CAD”
POINTS TO BE KEPT IN THE VIEW WHILE SELECTING A SITE FOR WASTE WEIR:
VIT, BENGALURU                                                              DEPT. OF CIVIL ENGINEERING.   10
EXTENSIVE SURVEY PROJECT                                                                             BATCH-5
      A weir should be aligned at right angles to the direction of the river flow, which ensures lesser length
       of the weir and better discharge capacity.
      The site must be ensuring a good foundation.
      It should be as natural diversion channel top carry the surplus water.
      The length and height of the body wall should be minimum.
      The cost of protective works should be minimum.
INSTRUMENTS REQUIRED:
   1. Dumpy level with tripod
   2. Levelling staff
   3. Chain and tape
   4. Cross staff with stand
   5. Ranging rods
   6. Wooden pegs
   7. Arrows
PROCEDURE:
      Block levels are taken at the waste weir at an interval of 5m for a length of 40m.
      Fix the direction of centre line of waste weir with the reference of centrline of bund.
      Construct a block level at 5 square sizes along the centerline of waste weir for a length of 40m on
       U/S side and 30m on D/S side up to a length of 40m.
      Levelling work is started from the established of temporary BM and staff readings are taken at
       established points of blocks.
      Staff readings are entered in the field book and reduced levels are calculated.
      Assuming suitable scale blocks are drawn on the sheet and contours at different level with contour
       interval are drawn.
1.8.3 SLUICE:
   A sluice is provided for carrying the water stored below FTL up to DSL the water discharged from the
sluice is carried out through canal further.
   \
1.8.3.1 TYPES OF SLUICE:
      Tower head with-pipe sluice /arched sluice /slab barrel
PROCEDURE:
      Centre line of the tank sluice is established at right angles to the centerline of the main bund at the
       canal take off point on the bund for a distance of 30m on U/S and D/S sides.
      For a distance of 40m at 5m intervals on the centre line of the bund 5m squares is established on
       either side of centre line.
      Staff readings are taken on each point of established square and the RL of each point is calculated.
   Canal is distribution system, which water flows from the sluice to the irrigation land. This phase includes
the design and construction of canal system, regulators, canal drops etc and also cross drainage works where
ever necessary canals are generally trapezoidal in the shape to carry water to the irrigation field and as far as
possible canal should be in cutting for economy.
1.8.6 CLASSIFICATION OF CANALS:
      Water Shed Canal: A water shed canal can be considered to have an ideal alignment. In this case
       the alignment runs along the ridge line so that flow occurs by gravity on both sides of canal. In
       addition such as alignment does not intercept natural drain so that expensive cross drainage works
       are eliminated?
      Contour Canal: Watershed canal is not practical in hill area where the ridge line is situated at very
       high level. In such a situation contour canal is usually provided. In this case alignment runs approx
       parallel to contours to given area it is common that canal alignment crosses natural drain. Therefore
       cross drainage works cannot be avoided.
      Side Slope Canal: A side canal may be defined as one whose alignment runs almost perpendicular
       to the contours of the given area and therefore it is very rightly known as side slope canal. In this
       case alignment runs parallel to natural drain so that problem of cross drainage works does not rise.
       Less rainfall:
When the total rainfall is less than that needed for the crop, artificial supply of water is necessary. In such a
case, irrigation system should be developed at the place where more water is available and then, the means
to convey water to the area where there is deficiency.
       Non-uniform rainfall:
        The rainfall in a particular area may not be uniform throughout the crop period. During the early
        periods of the crop rains may be there, but no water may be available at the end, with the result, that
        either, the yield may be less or the crop may wither. But the accumulated or stored water during the
        excess rainfall period may be supplied to the crop during the period when there may be no rainfall,
        but there is a need for watering.
       Commercial crop with additional water:
The rainfall in a particular area may be just sufficient to raise the usual crops, but more water may be
necessary for raising commercial or cash crops, in addition to increasing the annual output by adopting
multiple cropping patterns distributed throughout the year.
       Controlled water supply:
By constructing a proper distribution system, the yield of crop may be increased. Application of water to the
soil by modern methods of irrigation increases the efficiency of growth of crops.
For example, if 3 cumecs of water supply is required for a crop sown in an area of 5100 hectares, the duty of
irrigation water will be 5100/3 = 1700 hectares/cumec, and the discharge of 3 cumecs will be required
throughout the base period.
Delta:
Delta is the total depth of water required by a crop during the entire period from the day of sowing to
harvesting.
For example, if a crop requires about 12 watering at an interval of 10 days and a water depth of 10 cm in
every watering then the delta for that crop will be 12x10 = 120 cm = 1.2 m. If the area under that crop is A
hectares, the total quantity will be 1.2 x A = 1.2A hectare-meters in a period of 120 days.
Crop period:
         Crop period is the time, in days, that a crop takes from the instant of its sowing to its harvesting
Base period:
Base period for a crop refers to the whole period of cultivation from the time of first watering for sowing the
crop, to the last watering before harvesting.
The duty of water is reckoned in the following four ways:
1. By the number of hectares that 1 cumec of water can irrigate during the base period. i.e., 1700 hectares
per cumecs.
3. By number of hectares that can be irrigated by a million cubic meter of stored water. This system is also
used for tank irrigation.
4. By the number of hectare meters expended per hectare irrigated. This is also used in tank irrigation.
Where,
Δ - Delta of the crop in m
B– Base period of the crop in days
D – Duty of the water in hectare/cumec
Consumptive use:
Consumptive use of water by a crop is the depth of water consumed by evaporation & transpiration during
the crop growth, including water consumed by accompanying weed growth
.
   5. Cross staff
   6. Arrows and pegs
   7. Prismatic compass with stand
PROCEDURE:
      Starting from BM (i.e. DSL+ 0.75) level is carried out until the required elevation of the canal is
       obtained for a distance of 30m.
      According to fall staff readings are calculated and required staff reading is searched along the 15m
       from the previously established point.
      At each established point a perpendicular line to that point for a distance of 1.5m on either side is
       establishment and the points are marked at an interval of 0.5m on the established.
      Bearings are taken on the gradient lines established simultaneously.
      Staff readings are taken at each established point and RL of each is calculated
      From obtained bearings the alignment of canal has been plotted in drawing sheet to a suitable scale.
DESIGN A TANK SURPLUS WEIR FOR A MAJOR TANK CONNECTED WITH TANK IN
SERIES:
1) Field data:
The ground level below the proposed surplus slopes off till it reaches +10.00m in about 6m distance.
2) Construction details:
3) Other details:
Making a provision to store water up to MWL proper abutment, wingwalls and return are to be designed.
Assume on hydraulic gradient of 4:1 with 1m c/c covers and Rye’s co-efficient=9.
VIT, BENGALURU                                                         DEPT. OF CIVIL ENGINEERING.      19
EXTENSIVE SURVEY PROJECT                                                                  BATCH-5
DESIGN:
Q=CM2/3-cm2/3
Therefore,
Q=9*25.892/3-1.5*20.712/3
=78.77-11.32
=67.45km3
2) Surplus weir:
a) Length:
Q=2/3*Cd*SQRT (2g)*L*H3/2
67.54=2/3*(0.6)*sqrt(2*9.81)*L*(0.75)3/2
L=67.45*3/(2*0.6*sqrt(2*9.81)*0.753/2)
L=202.35/3.45=58.61m=59m
The dam stones are fixed at 1m clear interval at FTL and the number of opening will be 59.
Size of the dam stones 15cm*15cm and the protecting length above crest will be 75cm.
Therefore, the overall length of surplus weir between the abutments is 59+(58*0.15)=67.7m
Taking foundation about 0.5m deeper into hard soil the foundation level can be fixed at 9.00.       The
foundation may be usually 0.60m thick.
=2.40m
a=0.55(sqrt(H)+sqrt(h))
Where,
H=height of weir=2.40m
Therefore,
a=0.55(sqrt(2.4)+sqrt(0.75))
=1.3m
1/12[{(s+1.5)*H+2.5*h}b2+a(SH-Hh)b-1/2a2(H+3h)]=[(H+h)3/6]
Where,
1/12[{(2.25+1.5)*2.40+2.5(0.75)}*b2+1.3(2.25*2.4-2.4-0.7)b-1/2(1.3)2(2.4+3*0.75)]=[(2.40+0.75)3/6]
Therefore,b=2.2m =2.3m
a) Abutment:
Portion AB is called the abutment. It has its top level same as that bund of +14.50 and has its width at top
same as that bund of +14.50 and has its width at top same as that of the top width of bund i.e.2m
b) Wing wall:
This wing wall start sloping down from B till it reaches about 30cm above MWL i.e.a level of
12.75+0.30=13.05at C.
Therefore, the portion of wing wall BC will be having its top sloping down from +14.50 to +13.05 at a splay
of 2:1 .
Since, The level wing and return walls i.e, portions CD and DE have to be throughout 30cms above MWL
the same section of wall at C can be adopted.
In order to give an easy approach the u/s using wall may be splayed 3:1 as shown in the diagram.
     As the water after passing over the weir goes down to d/s side the wings and return walls need not so
strong as on the u/s side. The wing wall to F will slope down till the top reaches the ground level at F. The
dimensions of wing wall at “A” will be the same as that of the abutment.
The top of wing wall at F may be fixed at 11.00 same as ground level.
So the height of the wing wall at F may be fixed at 11.00 same ground level.
So, the height of the wing wall and return walls junction and the return walls.
The d/s side wings are given a splay of 1:5 as shown in figure.
g) U/S aprons:
     Generally, number aprons are required on the u/s side of the weir. It is desirable to provide a puddle
apron as shown in the figure.
h) D/S aprons:
             Since, the ground level is falling down to +10.00 in a distance at about 6m. It is desirable to
provide a stepped apron. The stepping may be in 2.
           Maximum uplift pressure are experienced on the d/s aprons of dam stone level in the tank is upto
bottom of dam stone level i.e.to +12.75 with no water on the d/s side.
The lowest level of the solid apron on the d/s side is +10.00
If the residual uplift gradient is to be limited 1 in 5 then we required aprons to total length of 2.00*5 =10m
           The U/S water has to be percolate under the foundation of the weir if it has to establish any uplift
under the apron. The possible path of percolation is shown in the sketch.
            Assuming the puddle apron provided on the U/S stream side is not impervious the water is start
percolating from A to a level at +11.00 and reach B and C. Then it will follow the least path from D to E
under the end cut-off and then appear at F.
i.e, AB+BC+CD+DE+EF
=1.40+0.60+3.00+DE+1.00
=DE+6.00
Therefore, DE=7.75m~4m
      Therefore, provide solid apron of total length 4m on the D/S side where the first apron would be of 1m
and apron of 3m.
The maximum uplift on the apron floor is felt immediately above point D in the sketch.
Total creep length from point A on the U/S side up to the point above D under the solid apron is,
AB+BC+CD+1.20
=1.40+0.60+3.00+1.20
=6.20
Therefore, head lost in percolation along the path up to the point =6.20/5=1.24m
Each meter depth of concrete can withstand a head of 2.25m by selfcut of the apron above. Allowing an
extra 20% thickness to withstand any variation the thickness of the apron required is
=1.51/2.25 + [(1.51/2.25)*(20/100)]
= 0.805m ~ 80cm
The solid apron can be similarly checked and a thickness of 50cm will be suffecient.
At the end of second apron retaining wall of the D/S side apron a nominal 3-5m length of talus with a
thickness of 50cm may be provided for safety.
(NOTE: Assume the length of wing wall on the U/S side to be 6m)
NOTE:
1) Delta=8.64B/D
  B=Base period
  D=Duty
2) Area=Intensity*CCA
3) Discharge=Area/Duty
4) 1 m3/s=86400 m3/day
5) Volume=discharge*base period
1) Silt factor=1.76√md
md=mean diameter of silt particles
           1.5/1.76=√md
                 md=0.7263mm
                                 140
                   V=0.3225m/sec
                 Rt=2.5*(V2/f)
                 Rt= 2.5* 0.32252
                        1.5
              Rt=0.1738
Both the values of R should be same, this will provide a numerical check hence checked.
Data:
CCA=200 hectares
Duty=1000ha/m3/sec
Side slope=2:1
Ground level=+12.50
Foundation level=+11.50
MWL=+17.00
FTL=+16.00
Bed level=+8.00
Bed width=1.25m
DESIGN:
   (2) VENTWAY:
      Area of the vent way from the sluice must be such that it can draw normal supplies of water when the
      tank is at low water level.
      The level of the water in the tank (a) given as+24.00
      Sill of the sluice =+9.00
      Head of water available= (09-08) =1m
      But sluice opening is designed to draw the driving head from normal requirements=0.25m=h
      Therefore to calculate area of vent way
      Q=cdA√ (2gh)
      0.2=0.6(A)√(2*9.81*0.25)
      A=0.151m2
      For circular opening A=0.151m2=πd4/4
      d=0.45m=45cm
      But the minimum vent way to be adopted for sluice barrels is about 75cm*60cm so as to allow room
      repairs etc.
      Therefore insert diaphragm stone of 45cm.
      (3)SLUICEBARREL:
      (A) Sluice barrel is buried under the tank bund.
          The barrel will have masonry side walls.
          Roof can either be of RC slab laid insitu.
      (B) The foundation of two side walls is continuous in concrete 60cm
      And wearing coat 100.
          Thickness of foundation serves as floor barrel in between the side
      Walls.
Self weight=[24,000*0.15*1]
=3600 N/m3
22400*5.1*1=114240 N/m3
Maximum BM,Mu=wl2/8
=176760*(0.75)2/8
=12428.4375 N-m
VIT, BENGALURU                                                            DEPT. OF CIVIL ENGINEERING.   30
EXTENSIVE SURVEY PROJECT                                                                        BATCH-5
Mulim=0.36fck*(xumax/d)*(1-0.42*xumax/d)b*d2
Take b=1000mm,d=120mm
Mulim=39733.493 N-m
Mu<Mulim
Hence OK.
Side walls act like abutments. They take the side thrust due to the earth pressure and also the super-
incumbent weight of the surcharged earth standing directly on the wall and roof slab.
(6)EARTH PRESSURE:
A=(1-SinØ)/(1+SinØ)*22400*10
A=1/3*22400*10
Ẋ = ((73920*0.9/3)+(38080*2/3*0.9))/(73920+38080)
Ẋ =0.402m
(b) Weight of the earth on top side of the wall beyond the slab:
P2 = 0.375*22400*5.1=42840N/m
 Let force be P2. This acts vertically on the side walls at a distance of (37.5/2) cm + 7.5cm = 26.25cm =
0.2625m
(1.) The force representing the weight of earth of the rectangular portion.
BB│CD = 5.1*0.55*22400=62832N
Let P3 the force acting at a distance of ; (0.55/2)+0.45=0.725m from the top face.
(2.) The force representing the weight of earth standing on the sloping portion AB│D = P4
(1/2)*0.9*0.55*22400 =5544N=P4
P5=( (0.45+1)/2)*0.9*24000
P5 =15660N
Ẏ = (0.9*0.45)*(0.45/2)+(1/2*0.55*0.9)*(0.45+[1/3]*0.55)
(0.9*0.45)+(1/2*0.55*0.9)
Ẏ = 0.379m
STABILITY ANALYSIS:
Ẋ = ∑M/∑V
Ẋ = 56725.326/206508 = 0.27m
TOWER HEAD:
   Tower head consists of Masonry well as shown below. The shutter operating arrangements are fixed so
   that it can be operated from a slab on the top of the well.
Assume thickness of shell of the well=0.45m upto the level of 10.5m from the top.(17.30m)
CISTERN:
   The dimensions of cistern are fixed arbitrarily to suit the earth connections of the channel and tank
   bund. Cistern enables us to take off more than one channel through separate openings in its side walls.
   The cistern also functions as a stilling basin for the outrushing water through the barrel and reduces any
   possible scours in the channel.
ESTIMATION:
    Chainag
              Average   TBL   Depth    Mean     Central   Side      Side      Total    Length   Quality A x L
    e
                                       Depth    Area
    (m)       GL (m)    (m)   (m)                         Area      Area      Area     (m)      (m3)
                                       (m)      (m2)
                                                BxD       S1 (m2)   S2 (m2)   A (m2)            Embankment      Cutting
                                        CHAPTER : 2
                                    OLD TANK PROJECT
2.1 INTRODUCTION
2.1.1 GENERAL:
Tanks are very important means to conserve precious water resources in a semi-arid area. These are very
small storage reservoir created on the upstream of a small earthen dam, construction across a stream. The
depth of water in a tank is usually less than 4m. However, in exceptional cases, it may be more than but not
greater than 12m. When the depth of water exceeds 12m, the tank is termed as reservoir.
      De-silting the reservoir: This would require the employment of sophisticated equipment such as
       hydraulic dredges. Before taking up the project, it is necessary to study whether the proposal would
       yield minimum cost to restore the original capacity of the reservoir.
The surplus weir is at the end of the bund. The other side of the weir is directly on the hilly terrain. The weir
is of curved type and has counter forts to strengthen the weir. The approximate length of the weir is 45m to
dispose the surplus water during floods. It has no temporary storage arranged for storing surplus water up to
MWL. The bund is provided with a sluice opening @ 150m chainage from the start of the bund. Since water
was present in the upstream portion. The details of the sluice were difficult to survey.
2.5 PLAN:
The plan of the existing bund was plotted using compass survey.
2.5.2 OBJECTIVE:
To draw the capacity contour map of the catchment and estimate the quantity of water the can be stored.
Following are the aspects to be considered while fixing the capacity of the reservoir:
      The catchment at the site proposed receives sufficient rain to cater the demand and if the proposed
       site can hold the required quantity of water then required height of the bund can be constructed.
      The catchment at the site proposed receives sufficient rain to cater the demand and if the proposed
       site cannot hold the required quality of water then the required height of the bund shall be restricted
       to site conditions.
      The catchment at the site proposed receives less rain which cannot cater the demand and any height
       of the bund can be constructed, then the height of the bund is fixed to store maximum water. The
       catchment at the site proposed receives less rain which cannot cater the demand any height of the
       bund can be restricted because of site condition, then the height is fixed taking the site condition. In
       all the above cases, it is necessary to compute the yield of catchment.
= 60.64%
CHAPTER: 3
3.1.1 WATER:
       Human existence is governed by the availability of a water supply that is both adequate in terms of
quality. Water is the most abundant resource found in nature however only 0.62% of this is present in
freshwater lakes, rivers and groundwater supplies can support human activities. Water is chemical
compound and may occur in a liquid, Solid or gaseous form. No life can exist without water and it becomes
imperative in a modern society to build a suitable water supply scheme which may provide portable water to
the various section of society in accordance with their demand and requirements of the various sections.
3.1.2 SANITATION:
        The utilization of enormous quality of water occurs in society and it returns as waste water from
every house or unit. To connect, convey and treat this water, a well-defined sanitary system is required. This
waste water is treated before being disposed in an appropriate way.
   5. Quality requirement
   6. Treatment of the water
   7. Distribution system
3.3.1VILLAGE TRAVERSING:
       This survey work was done in order to obtain information about the layout of the village such as the
number of houses, population and existing water supply scheme.
       EQUIPMENTS:
              Plane Table With Accessories
              Measuring Tape, Ranging Rods
PROCEDURE:
       The entire area under consideration is surveyed in detail. Thus a detailed map indicating the houses,
network of road and place of worship, existing water supply scheme and sanitary scheme is plotted. A
proper scale was so chosen that the drawing was neither to small nor too large keeping in mind the area to be
covered. Use of three point problem was carried out when the work had to be continued the next day. The
plane table was placed at the side not in middle since it would affect traffic flow. Location of the table at
each junction point was so selected that it covered many roads from a single station.
It is the annual average of daily water required by one person. It is dependent on the living standard of
people in the region. A per capita demand of 135lpcd has been chosen.
                                                              0
  4      Radiological         Emitter
3.6 TREATMENT:
       Since the source of water is a tube well, Aeration and Chlorination are the treatment methods to be
given. The dosage of chlorine is kept as 1mg/l.
The intake well is a circular or rectangular well with circular ends located in a river bed, so that it always
remains surrounded with water, even during low flood stage. The well is built in masonry or concrete, and is
raised above the river HFL and covered at the top by wooden sleepers etc as to make it approachable from
the river bank through a foot bridge arrangement.
Screens are generally provided in front of the intake works, so as to exclude the large sized particles.
Screens are normally inclined at about 45° - 60° to the horizontal, so as to increase the opening area to
reduce the flow velocity.
        4                     Distance    to   be 60 m
                              travelled by water
        5                     Suction Head Hs       7.115 m
3.6.4AERATORS:
1. It removes tastes &odours caused by gases due to organic decomposition.
4. It decreases the carbon di oxide content of water and there by reduces its corrosiveness and rises its PH
value.
3.6.8Coagulants:
The water that are used for domestic purpose contains fine suspended particles which take certain time to
settle down.
      Particles of size 0.06mm requires 10 hours to settle down.
The particles of size less than 0.0001mm will not settle down at all and are called as Colloidal Particles.
These colloidal particles are electrically charged particles. Such particles can be removed by adding
coagulants to water
Coagulants are the chemical compounds used to remove the very fine suspended particles or colloidal
particles (of size less than 0.0001mm) present in the water that are used for various domestic purposes.
      The coagulants neutralize the negative protective charge on the colloidal particles and allow them to
       coagulate.
      Coagulation form the particles into insoluble gelatinous floc which unite together to form particles of
       bigger size which can be removed by sedimentation.
3) Characteristics of water (type and quantity of suspended matter, temperature of water and pH of water).
2. Sodium aluminate
4. Chlorinated copperas
5. Magnesium carbonate
6. Polyelectrolyte’s
Aluminumsulphate or alum
      Alum is an universal coagulant used in water works.It is most commonly used Coagulant
      In the presence alkalinity in water the alum is added and it tends to hydrolyze into Aluminum
       hydroxide.
Sodium Aluminate
      Chemical composition of Sodium Aluminate is Na2Al2O4
      Best grade of Sodium Aluminate contains 55% of Aluminum, 34% of Na2O3, 4.5% of Na2CO3 and
       6.3% of NaOH.
Ferric Coagulants
      Chemical composition of ferric coagulant may be Ferric Chloride (FeCl3), ferric sulphate
       (Fe2(SO4)3), ferrous sulphate (FeSO4.7H2O), or ferric hydroxide (Fe(OH)2).
      Ferric coagulants acts as oxidizing agent and remove taste, odor, and hydrogen sulphide present in
       water.
      These are commonly used in sewage treatment and good result can be obtained at pH value above
       3.5.
2FeCl3+3Ca (OH)2                          2Fe(OH)3+3CaCl2
Fe2(SO4)3+3Ca(OH)2                        2Fe(OH)3+3CaSO4
FeSO4.7H2O+Ca (OH)2                       Fe(OH)2+CaSO4+7H2O
4Fe(OH)2+2H2O+O2                          4Fe(OH)3
Chlorinated Copperas
      It is a mixture of ferric sulphate and ferric chloride obtained by adding chlorine to the ferrous
       sulphate.
 The flock generated by this coagulant is tough and settle down easily.
6FeSO4+3Cl2 2FeCl3+2Fe2(SO4)3
The duration of mixing in the flash mix chamber is carefully controlled and is usually between thirty
seconds and one minute. If the water is mixed for less than thirty seconds, then the chemicals will not be
properly mixed into the water. But if the water is mixed for more than sixty seconds, then the blades will
shear the newly forming floc back into smaller particles.
When determining the length of time that water must spend in the flash mix chamber, flow rates must be
calculated. The volume of the flash mix chamber and the amount of flow determine the contact time.
3.6.13 Clariflocculator:
Clariflocculator is a combination of flocculator and clarifier fabricated to attain economic and speedy
construction. It’s used at huge water treatment plants, industrial wastewater treatment plants, and potable
water treatment. It has two concentric tanks where inner tank serves as a flocculation basin and the outer
tank serves as a clarifier. These systems are fabricated proficiently according to the varied requirements of
the customers. Clariflocculators generally are used to perform the chemical primary treatment of effluents.
A circular clariflocculator is designed having vertical paddles. The water enters through a central influent
pipe and is fed into flocculator zone through ports. The effluent from the flocculation passes below the
partition wall dividing the flocculator portion and the clarifier portion. The clarified effluent is collected by a
peripheral effluent launder.
3.6.14 FILTRATION
Principle of this is removal of “REMAINING COLLOIDAL DISSOLVED MATTER, BACTERIA”.
The water is filtered through the beds of granular material, such as sands, etc. The process of passing the
water through the beds of such granular material is known as filtration. Filtration helps in removing colour,
odour, turbidity, and some pathogenic bacteria from water.
They are ,
1. The slow sand gravity filters.
Construction
1. Enclosure tank
 The bed slope is kept at about 1in 100 towards the central drain
       The depth of tank is kept 2.5 or 3m and area may vary from 100 to 2000m2 or more, depending upon
        the quantity of water to be treated.
2. Filter media
       Filter media consist of sand layer about 90cm to 110cm in depth, and placed over a gravel support.
3. Base material
       The base material is gravel, and it consist of 30mm to 75mm thick with different gravel sizes.
       The size of gravel in the top most layer is 3 to 6mm, intermediate layer varying from 6 to 20mm and
        20 to 40mm bottom most layer is kept 40 to 65mm.
Operation
1. The treated water from the sedimentation tank is allowed to enter the inlet chamber of the filter unit and
get distributed uniformly over the filter bed.
2. The water percolates through the filter media (sand bed) and then enters the gravel layer and comes out as
the filtered water.
3. The filtered water is collected in the laterals through the open joints, which discharge into the main drain
and then filtered water is taken to storage tank.
3.6.15 Cleaning
Cleaning is done by scrapping and removing the 1.5 to 3cm of top sand layer. The top surface is raked,
roughened, cleaned and washed with good water. The amount of water required for cleaning is small say
0.2% to 0.6% of filtered water.
3.6.16 Disinfection
Disinfection unit is used for removal of “PATHOGENIC BACTERIA, ORGANIC MATTER AND
REDUCING SUBSTANCES”.
The chemicals used for killing these bacteria are known as disinfectants, and the process is known as
Disinfection or sterilization.
Minor Methods of Disinfection
1) Boiling of water
Chlorine has been found to be the best and the most ideal disinfectant and is now invariably used throughout
the world.
3.6.16.1 CHLORINATION
Chlorination commonly used to indicate broadly that the water has been treated with a sterilizing agent.
Disinfecting Action of Chlorine When chlorine is added to water, it forms hypochlorous acid or
hypochloride ions, which have an immediate and disastrous effect on most forms of microscope organisms.
The reactions that take place are
Cl2 + H2O HOCl (Hypochlorous acid) + HCl
The hypochlorous acid is unstable and may break into hydrogen ions and hypochlorite ions
HOClH+ (Hydrogen ions) + OCl-(Hypochlorite ions)
The above reaction is reversible and depends upon the pH valve of water. The dissociation of hypochlorous
acid into ions is more effective at high pH valves and vice versa. Thus, at pH valves greater than 10, only
OCl ions are found; while in pH valves of less than 7 (more than 5), HOCl will generally exist without
dissociating into OCl ions; and in the pH range of below 5, chlorine does not react and remains as elemental
chlorine.
Out of these forms of free available chlorine, the hypochlorous acid is the most destructive, being about 80
times more effective than the hypochlorite ions. For this reason, the pH valve of water during chlorination is
generally maintained slightly less than 7, so as to keep the dissociation of HOCl to minimum, and thereby
keeping more HOCl in solution compared to OCl ions.
                                             =1500
Ultimate population after 30 years by assuming 30% increase
                                             = [(30/100) x1500] + 1500
                                             =1950
Assuming the rate of water supply or per capita demand = 110lpcd
Therefore Average Demand                     =Population x Per Capita Demand
                                             =1950x 110
                                             =214500l/day (214.5m3/day or 0.214MLD)
Also,
Assuming maximum daily demand as 1.5 times the average daily demand
Maximum Daily Demand, QMAX                   =1.5xAverage water demand
                                             =1.5x214.5
                                       QMAX=321.75m3/day (321.75m3/dayor0.322MLD)
                       D =0.142m
                       D=0.15m≈15cm
H I = 1013.630-972.980         =40.65m
Head loss, hf                  = (4flv2)/ (2gd)
                               = [(4x0.015x455x0.852)/ (2x9.81x0.128)]
                               = 7.85m ≈ 8m
Total head                     = 40.65+7.85= 48.5m ≈49m
Efficiency of the pump         = (WQH)/ (75xn)
                               = [(9.81x0.011x49)/ (0.735x0.85)]
                               = 8.46HP ≈ 10HP
Provide 2 NOS. Of 10HP pump (one should be stand by) to pump the water from treatment plant to
OHT.
= 214500lit/day
=0.2145MLD
MLD=million litre/day
Assume,
Detention time=6hours=360min
Velocity of flow=10cm/min=0.1m/min
V=0.2145*10^6*6/24
V =0.53625m3
A=V/L=0.53*103/36=14.72m2
Provide an extra depth of 0.5m for sludge storage and 0.5 m for free board making a total
depth=4+0.5=4.5m.
Therefore Hence, by use of filters units of 2 the cross – section of the filter units are 2m*3m
Question: population of a town is 1950 with an assured water supply of 135l/head/day. BOD of waste
water is 150mg/l. Design an oxidation pond for treating sewage.
Data:
=31.59x106 mg/day
=31.59 kg/day
Surface area of oxidation pond (A) = (BOD of waste per day/organic loading)
=1053m2
A=LxB= (2xB) xB
B(2xB)=1053
B2=526.5m
B=22.94m=23m
L=2xB=2x23=46m
Capacity of tank=LxBxd=1*23*46
=1058m2
=1058x103litres
=1058x103/210600
=5.02 days
Design:
=263.25*103litre/day.
Assuming max daily demand as 1.8times the average the maximum quantity of water required is,
=263.25*103*1.8
=0.47385MLD.
=0.47385*106/103*24*60*60
=0.00548cumecs.
Q=A*V
0.00548=A*0.85
A=Q/V
A=0.00548/0.85
A=0.00644m2.
Therefore,
Hydraulic gradient:
Hazen-william`s formula
V=0.85cH*R0.63*S0.54
Where,
CH= co-efficient of hydraulic capacity smoother the pipe greater is the value=110.
V=0.85*140*(d/4)0.63*S0.54
V=0.85m/sec
0.0729=S0.54
S=1/127.42
3.8 SANITATION:
       After utilization the water returns as waste water from every house or unit .This water has to be
disposed safely without polluting the environment. The main purpose of maintaining proper sanitation is to
keep the environment clean which in turn has a direct impact on public health. Such a practice would ensure
a safe and healthy environment free from factors that might lead to serious outbreak of epidemics.
                                         CHAPTER: 4
                               HIGHWAY PROJECT
In a new highway project, the engineer had to plan design and construct either a network of new roads or
road links. There are also projects requiring redesign and realignment of existing roads for upgrading the
geometric design standards.
4.1 AIM:
The aim of the highway project is to propose a new alignment two obligatory points identified at Melukote
village. The proposal comprises of extensive field data collection, analysis of the collected data so as to
provide an economical highway alignment and with a geometric design, which meets the design guidelines.
4.1.1CONTENTS:
      Introduction
      Location- map
      Salient features of the project
      Recommendation about alignment survey
      Studies for alignment
      Procedure for survey
4.2 INTRODUCTION:
The existing road which connects the Melukote village from Kadalgere was found to be a longer route with
width of the road to be small and not uniform. Since Melukote village was known for its temples and nature
which was the source of attraction, the tourists were finding difficulty in using the existing road containing
steep gradients. Therefore, a new highway alignment was to be proposed connecting the above obligatory
points which will be the shortest route possible but deviating from farm lands and public properties.
The proposed alignment is to 1.230km length and the survey was conducted for a width of 10m on either
side of the road to account for future expansion. On the basis of the survey data collected, a formation level
was proposed such that the area of cutting and filling will be minimum. For fixing this propose level, the
ruling gradient and minimum gradient was considered such that area of cutting will be equal to the area of
filling.
   4. To find the deficiencies (if any) within the pavement structure and to redesign for the design traffic.
To work the areas of land to be acquired for the realignment and the quantity of materials required like
earthwork and various pavement materials for proposed realignment stretch and strengthen pavement.
4.3.1MAP STUDY:
If the topographic map of the area is available, it is possible to suggest the likely routes of the road. In India
topographic maps are available from the survey of India with 15 or 30m contour intervals. The main features
like rivers, hills, valleys etc. are also shown on these maps. By careful study of such maps it is possible to
have an idea of several possible alternate routes so that further details of these may be studied later at the
site. The probable alignment can be located on map from the following details available on the map.
      Alignment avoiding valleys, ponds etc.
      When the road has to cross a row of hills, possibility of crossing through a mountain pass.
 Approximate location of bridge site for crossing of rivers, avoiding bend of river, if any.
   a. Study of Survey Sheets, Maps, Etc: Reconnaissance begins with the study of all the available
       maps. In India, topographical sheets are available in scale 1:50000.
   b. Aerial Reconnaissance: Aerial reconnaissance will provide a bird’s eye view of the alignment under
       consideration, along with the surrounding area. It will help to identify factors, which call for
       rejection or modification of any of the alignments.
   c. Ground Reconnaissance: The various alternate routes found feasible as a result of map and aerial
       photograph study and aerial reconnaissance are further examined in the field by ground
       reconnaissance. As such, this part of the survey is an important link in the chain of activities leading
       to the selection of the final route.
   d. Final Reconnaissance of Inaccessible and Difficult Stretches: Ground reconnaissance may
       disclose certain difficult stretches, which call for detailed examination. A trace cut might be specially
       made in such sections for inspection.
   e. Reconnaissance Report: Based on the information collected during the reconnaissance survey, a
       report must be prepared. It should include all relevant information collected during the survey.
C. SURVEY PROCEDURE:
The survey should cover a strip of sufficient width taking into account the degree and the extent of cut/fill,
with allowance for possible shift in the centreline of the alignment at the time of final design. In the normal
course, a strip width of about 30m in straight or slightly curving reaches and 60m sharp curves and hairpin
bends. Physical features such as buildings, monuments, burial grounds, place of worship, pipelines, power
lines, telephone lines, existing roads etc. that are likely to affect the project proposals should be located by
means of offsets measured from the traverse line.
Levelling work includes taking ground levels along the trace cut at intervals of 10m and at abrupt changes in
slopes and also establishing benchmarks at intervals 250m exceptionally 500m by running check levels on a
closed traverse basis independently. While learning along centreline, reading of benchmarks should also be
taken to have a cross check in regard to accuracy of the fieldwork. It is particularly important that a single
datum GTS datum should be used to tie up all levels.
Cross sections should be taken at intervals of 30m and at point of appreciable change in soil conditions.
While taking cross sections, soil classification should also be recorded. At sharp curves and difficult
locations, detailed levelling may be done for the plotting of contours.
   b. For the selected alignment, a trail grade line is drawn taking into consideration the controls which are
       established by mountain passes, intersections with other roads, railway/river crossing, unstable areas
       etc.
   c. For the alignment finally chosen, a study of the horizontal alignment and conjunction with the profile
       is carried out and adjustments made in both as necessary for achieving proper co-ordination.
   d. Horizontal curves including spiral transitions are designed and the final centreline marked on the
       map.
   e. The vertical curves are designed and the profile shown on the longitudinal section.
The reference pillars should be so located that these will not be disturbed during construction. Description
and location of the reference pillars should be noted for reproduction on the final alignment plans.
At the road crossings, the angles that the intersecting roads make with the final centreline should be
measured with the help of a transit. Similar measurements should be made at railway level crossings.
4.4.2 BENCHMARKS:
To establish firm vertical control for location, design and construction, benchmarks established during
preliminary should be re-checked.
Final alignment was carried out by transferring the alignment from the drawings to the ground by driving
pegs along the centreline of the finally chosen alignment, and setting out simple circular curves whenever
necessary.
4.5.5 CAMBER/CROSSFALL:
Camber/cross fall is essential for the drainage in the lateral direction. The pavement on straight reaches
should be provided with a crown in the middle and surface on either side sloping towards the edge.
The camber or cross fall on straight sections of roads should be as given as in Table 1. For a given surface
type, the steeper values of camber should be adopted in areas having high intensity of rainfall and lower
values where the intensity of rainfall is low.
The cross-fall for earth shoulders should be at least 0.5% more than the pavement camber subject to a
minimum of 3%. On super elevated sections, they should normally have the same cross fall as the pavement.
4.6 DESIGN SPEED:
Table 2: Design speeds (Kmph) for different terrains
  Road             Plain             Rolling             Mountainous        Steep
                   Ruling    Min     Ruling      Min     Ruling Min         Ruling       Min
  Classification
  N.H & S.H        100       80      80          65      50        40       40           30
  M.D.R            80        65      65          50      40        30       30           20
  O.D.R            65        50      50          40      30        25       25           20
  V.R              50        40      40          35      25        20       25           20
Table 4: Minimum radius of horizontal curves for various classes of hill roads
  Sl.      Road Classification Mountainous Terrain               Steep Terrain
                               Ruling        Min                 Ruling        Min
  No.
  1        Nation    &        State 50             40            40             30
           Highway
  2        Major         District 40               30            360            20
           Roads
  3        Other District Roads    30              25            25             20
  4        Village Roads           25              20            25             20
NOTE: If the deviation angle is less than 10 then horizontal curve is not required at such places.
Now (2/3)xe is provided at the straight portion in a length equal to (2/3)xL, also a remaining (1/3 xe is
provided in the curved portion in a length equal to (1/3)xe.
In a similar way, the calculated extra widening W e is also provided, i.e., (2/3)xWe in the straight portion and
(1/3)We in the curved portion.
Also, the extra widening is introduced on the inner side of the curve for curves without transition curves also
in hilly roads.
The vertical alignment should be provided for a smooth longitudinal profile consistent with category of a
road and the terrain. Grade changes should not be too frequent as to cause kinks and visual discontinuities in
the profile.
4.8.1 GRADIENTS:
Recommended gradients for different terrain conditions except at hair-pins bonds are given in the table 8.
A minimum gradient of about 1 in 500 may be sufficient to drain the water in concrete drains but on inferior
surfaces of drains, a slope of 1 in 200 or 0.5% may be needed.
=1.12m
Length of final sub chord (C9) = 4.72m
Number of normal chord= 7
Total no’s of chord = 1+7+1=9
DEFLECTION ANGLE ‘∂’
∂1 = 1718.9xC1/R
= 1718.9x1..12/(65x60)
= 0029’37.8”
∂2 = ∂3 = ∂4 = ∂5 = ∂6 = ∂7 = ∂8 = 1718.9x5(65x60)
= 2012’13.38”
∂9= 1718.9x4.72/(65x60)
= 204’49.12”
CHECK:
D/2 = 360/2 = 18000’00”
      127R
Step 1: Calculation of e by taking the value f = 0 and 75% of the design speed
(50)2 = (e + 0)
     127x65
e =0.3
As e > 0.07 Hence provide super elevation as, e = 0.07 that is 7%
Step2: Calculation of f by taking value e = 0.07 and 100% of the design speed
(50)2 = (f – 0.07)
127x65
f = 0.23> 0.15
there fore provide f = 0.15
4.8.6DESIGN OF VERTICAL CURVE:
Length of Curve = (Total change of grade) / (Rate of change of grade)
                     = (g1-g2)/g chain
Assume, R=450m
0.1%=30m
r= (450*0.1)/30
r=1.5chain
D = (1718.87)/450
  = 3.18
D = 3’49’10.96”
   a. FLEXIBLE PAVEMENTS:
Flexible pavements are those, which on the whole have low or negligible flexural strength and are rather
flexural in there structural under loads.
The flexible pavement layers reflect the deformation of the lower layer to the surface of the layer. Thus if
the lower layer of the pavement or soil sub-grade is undulated, the flexible pavement surface also gets
undulated. A flexible pavement consists of four components: Soil sub-grade, Sub-base course, Base Course,
Surface course.
   b. RIGID PAVEMENTS:
Rigid pavements are those, which possesnote worthy flexural strength or flexural rigidity. The stresses are
not transferred from grain to grain to the lower layers as in the case of flexible pavements layers. The
pavements are made of Portland cement concrete plain, reinforced are Pre-stressed concrete. The rigid
pavements are usually designed and the stresses are analyzed using elastic theory, assuming the pavement as
an elastic plate resting over elastic or a viscous foundation.
This test uses a cylindrical plunger of 50mm diameter to penetrate a pavement component material at
1.25mm/minute. The load values took cause 2.5mm and 5mm penetration are recorded. These loads are
expressed as percentages of standard load values at respective deformation levels to obtain CBR value. The
standard load values obtain from the average of a large number of test on crushed stones are 1370kg and
2055kg at 2.5mm and 5mm penetration respectively.
TABULAR COLUMN:
                                                         Depth        of Depth         of
 Chainage      Reduced Level        Formation Level                                         Datum
                                                         Cutting         Filling
 0             893.81               893.81               -               -                  885
 10            893.815              894.19                               0.375              885
 20            895.065              894.57               0.495                              885
 30            895.77               894.949              0.821                              885
 40            896.105              895.329              0.776                              885
 50            896.45               895.709              0.741                              885
 60            896.965              896.089              0.876                              885
 70            897.575              896.469              1.106                              885
 80            899.125              896.848              2.277                              885
 90            900.55               897.228              3.322                              885
 100           901.46               897.608              3.852                              885
 110           902.29               897.988              4.302                              885
 120           903.05               898.368              4.682                              885
 130           903.905              898.747              5.158                              885
 140           904.925              899.127              5.798                              885
 150           906.315              899.507              6.808                              885
 160           906.905              899.887              7.018                              885
 170           907.63               900.267              7.363                              885
 180           908.19               900.646              7.544                              885
 190           908.825              901.026              7.799                              885
 200           906.815              901.406              5.409                              885
 210           906.825              901.786              5.039                              885
 220           908.11               902.165              5.945                              885
 230           908.79               902.545              6.245                              885
 240           908.705              902.925              5.78                               885
 250           908.88               903.305              5.575                              885
 260           908.46               903.685              4.775                              885
                                     CHAPTER: 5
                                      ZONING
  5.1 INTRODUCTION:
    1. Zoning describes the control by authority of the use of land, and the buildings thereon. Areas of
        land are divided by appropriate authorities into zones within which various uses are permitted.
    2. Zoning is the process of planning for land use by a locality to allocate certain kinds of structures in
        certain areas. Zoning also includes restrictions in different zoning areas, such as height of
        buildings, use of green space, density (number of structures in a certain area), use of lots, and types
        of businesses.
    3. Levels or types of zoning include open space, residential, retail, commercial, agricultural, and
        industrial.
    4. Thus, zoning is a technique of land-use planning as a tool of urban planning used by local
        governments in most developed countries. The word is derived from the practice of designating
        mapped zones which regulate the use, form, design and compatibility of development. Legally, a
        zoning plan is usually enacted as a by-law with the respective procedures.
    5. There are a great variety of zoning types, some of which focus on regulating building form and the
        relation of buildings to the street with mixed-uses, known as form-based, others with separating
        land uses, known as use based or a combination thereon.
    6. Similar urban planning methods have dictated the use of various areas for Particular purposes in
        many cities from ancient times.
         Examples: For example, if you wanted to open a business in an area that was zoned as
        "residential," you might not be able to do it, unless you received a variance (exception).
  5.2 USES OF LAND
      The use of land in town planning will be classified into two
      Categories:
         1. Profit-making uses of land
         2. Non profit-making uses of land
      1.Profit-making uses of land: The land which is developed with profit motive is said to be used for
      profit-making and the sites developed for office, residences, industries, etc. are the examples of
      profit-making uses of land.
      2.Non-profit-making uses of land: The land which is developed without any motive of profit-
      making is said to be used for non-profit making and it includes playground, parks, road, government
      offices, etc.
       The main non-profit-making use in urban area will naturally be the roads. The relation between
      profit-making use of land and nonprofit-making use of land should be noted.
      The profitable uses of land are highly dependent on the non-profit uses of land.
5.2.1 ADVANTAGES OF ZONING:
      1. Danger from fire.
      2. Future Development.
      3. General amenities.
      4. Health of community.
      5. Population distribution.
      6. Public utility services
         In general it may be suggested that zoning promotes health, safety,                 prosperity, orderly
  development and overall welfare of the community. There is some example showing the undesirable
  situations which might develop in the absence of zoning are as follows:
           The big apartment flats of big heights may be constructed very near to small cottages or houses
            and thereby, they suffer from loss of light and air for surrounding structure.
           The development centers of public interest may take place at random without any
            considerations of their surrounding and hence their functioning result into wastage of time,
            money and space.
           The unsightly factories giving obnoxious gases and untimely noises invade the residential area
            of the town and by the way of their working, they make the residential area unfit for living.
           The public amenities may be provided as the need arises and ultimately, a time may come
            when it’s become either too costly or practically impossible to alter or to modify such
            amenities.
1. Density Zoning
2. Height Zoning
3.Use Zoning
    DENSITY ZONING: In density zoning, the density of population in the residential areas is controlled
    by means of suitable rules and regulations.
             Indirect measures are adopted to have effective density zoning:
             1) The front, side and rear margins of the boundaries are specified. 2) The maximum height of
             the building is specified.
             3) The maximum size of allotment for each house is specified.
             4) The number of houses per unit area is limited.
             5) The ratio of total site area to the total built-up floor area is specified.
    HEIGHT ZONING: The height zoning aims at controlling the height of buildings with due
    consideration of contents of the buildings and the
    Street width/ the marginal open spaces for the provision of light and
    Ventilation.
   The height zoning affords the following advantages:
    1) Controls the development of central business area of the cities and it
    there by assists in solving the problems associated with such heavy
    concentration e.g. traffic congestion etc.
    2) It is found that if buildings with uniform height are constructed on
    important streets or roads, it gives pleasing aesthetic appearance.
    3) It prevents an undue monopoly of light and ventilation by some tall
    buildings at the expense of adjacent units of small heights.
    USE ZONING: This is the most important aspect of zoning and it defines the uses to which various
    parts of the town will be put.
      Detailed zoning for a military town takes into consideration the following factor:
      1.       Conservation of environment.
      2.       Functional grouping of major and other allied sub units.
      3.       Location of units generating noise, smoke, smell, etc. To
      Minimize environmental ill effect.
      4.       Minimum distance between the place of work, residential zones
      and central amenities.
      5.       Road circulation pattern.
      6.       Store holding units along peripheral roads.
      7.       Zones for the bulk external services.
5.3Economy of zoning:
       One of the virtues of zoning is that great improvements could be done without serious liabilities
           on the part of tax-payers, if zones are pre-planned. Of course, considerable amount of money will
           be required for land acquisition, road improvements and various other aspects of the
           implementation of town planning schemes. But the same can be minimized and extra costs which
           might result due to charges, addition, alterations and modification after the town has been
           developed without zoning can certainly be avoided.
       The zoning is essential also as the basis for economy in carrying out all site planning work and
          local development schemes.
       It may further be noted that zoning indirectly helps in reducing costs because the use of land is
          known definitely and hence sewer lines, water lines and various other public services required for
          the town life can be designed and laid in the best efficient way.
5.4 ZONING POWER:
           The map showing the existing use of land marked in different colors suchas residential,
              commercial, etc.
           The map should also show the portions of detached houses, semi detached houses, flats and
              apartment houses,etc.
           It should be also marked on the map the position of all manufacturing plants, public
              properties, parks, play-Grounds, etc.
           The map showing density of population in different areas of the town and expressed either as
              houses Per unit area should be prepared.
           The map showing land values in the different sections of the town should be prepared.
           The map showing the details gathered from traffic survey should be prepared.
        potential, alternatives for land use, and economic and social conditions in order to select and adopt
        the best land-use options. Often one element of a comprehensive plan, a land use plan provides a
        vision for the future possibilities of development in neighborhoods, districts, cities, or any defined
        planning area.
Neighborhood Planning:
       Neighborhood planning gives communities direct power to develop a
       shared vision for their neighborhood and shape the development and
       growth of their local area. They are able to choose where they want new
       homes, shops and offices to be built, have their say on what those new
       buildings should look like and what infrastructure should be provided,
       and grant planning permission for the new buildings they want to see
       go ahead. Neighborhood planning provides a powerful set of tools for
       local people to ensure that they get the right types of development for
       their community where the ambition of the neighborhood is aligned
       with the strategic needs and priorities of the wider local area.
5.3.3Objects of zoning:
        1. The town planner gets ample opportunities for designing their future growth and development of
           town. The zoning serves as a main tool to the town planner to achieve his goal.
        2. The zoning affords a proper co-ordination of various public amenities such as transport facilities,
           water supply drainage, electric power, etc.,
        3. The zoning proves to be an effective instrument in the hands of the town planner for making any
           town planning scheme effective and successful.
Purpose of zoning:
5.5 NOTIFICATION
        The draft of the Karnataka Town and Country Planning(Approval of Plot) rules, 2017, which the
       Government of Karnataka proposes to make in exercise of the powers conferred by section 17 read
       with section 74 of the Karnataka Town and Country Planning Act, 1961(Karnataka Act 11 of 1963)
       is hereby, published as required by sub-section(l) of section 74 of the said Act, for the information of
       the persons likely to be affected thereby and notice is hereby given that the said draft will be taken
       into consideration after thirty days from the date of its publication in the official Gazette.
        Any objection or suggestion, which may be received by the State Government from any person
       with respect to said draft before the expiry of the period specified above will be considered by the
       State Government. Objections and suggestions may be addressed to the Secretary             to
       Government, Urban Development Department, VikasaSoudha, Bangalore-560001.
      c) 'Applicant' means any person who applies to the Authority for approval of plot as per these
           rules. The Applicant shall be the owner of the property or his authorized representative or a
           promoter authorized by the owner;
      d)       'Application' means an application made to the authority in such form appended to these
      rules;
      e)       'Amalgamation' means clubbing of two or more properties as a single property;
      f)       Architect/ Professional on record'- means an architect registered under Architects Act, 1972
      or registered professional who is brought on record to represent his client for preparing the required
      drawings to apply for approval of plot or [and to supervise the works at site in case of formation of
      layout. He shall be registered with the Local Authority for the cause;
      g)       'As Built Plan' means the layout plan drawn to scale, depicting the roads/ streets, sites, park
      and open spaces, civic amenity sites and public utilities and infrastructure drawings, as constructed
      on ground;
      h) 'Authority' means the Planning Authority as defined under sub-section of section two of the type.
   i) 'Bifurcation of Plot' means division of a plot into two;
      1) Bifurcated plot' means the building sites formed from bifurcation of a plot;
      (k) Building Site' means a plot held for building purposes, approved as per these rules;
      (l)"CEO" means the Chief Executive Officer for the purpose of these rules,- Member Secretary in
      case of Planning Authority constituted under section 2(7) (a)(ii) and 2(7) (b) of the Act and
      'Commissioner' in case of Bengaluru Development Authority constituted under Bengaluru
      Development Authority Act, 1976, Urban Development Authority constituted under
      Karnataka Urban Development Authorities Act, 1987 and Hampi World Heritage Area Management
      Authority constituted under the Hampi World Heritage Area Management Authority Act, 2002;
      (m)'Civic Amenity Site' means a site earmarked for Civic amenity in a layout approved by the
      Planning Authority as per these rules;
      (n)'Defect liability period' means a period of 5 years from the date of sanctioning final layout plan,
      during which period, the applicant shall maintain all the Infrastructure, including roads;
      (o)'DR/TDR': means Development Rights or Transfer of Development Rights available for plots as
      prescribed under Section 14-B of Act and rules made there under;
      before, during and after development, as the case may be, to certify the particulars of the plot as
      submitted by the Applicant and the developments made as per the provisions of the approved
      Provisional layout plan and report to the Authority;
      (q) 'EWS and LIG sites' means sites reserved for Economically weaker section and Lower Income
      Group category, which shall be of the area or size as notified by the State Government from time to
      time;
      (r)'Form' means a form appended to these rules;
      (s)'Frontage' means the width of the site/ land abutting the access/public road;
      (t)'Government' means, the Government of Karnataka;
      (u)'Group Housing' means building(s) proposed on a building site where one or more blocks with
      one or more floors, each containing two or more dwelling units, with a total of four or more dwelling
      units in all such buildings;
      (v)'Hierarchy of Roads/ streets' means the designation of roads based on the characteristics or
      functions of the roads such as trip distance, access control, traffic separation, traffic volume, type of
      vehicle movement etc.;
      (w)'Hilly Areas' means such of the Local Planning Areas as may be notified by the Government from
      time to time;
      (x)'Integrated Township' means a layout with a minimum extent and additional standards or
      conditions as prescribed in these rules;
      (y)'Land use' includes the purpose to which the site or part of the site of the building or part of the
      building is in use or permitted to be used by the Authority. Land use includes zoning of land use as
      stipulated in the Master plan and the Zonal Regulations; and
      (z)Layout' means sub division of one or more plots, held in one ownership or joint holders, by laying
      out roads for the formation of building sites and earmarking area for park and open spaces, civic
      amenity sites and public utilities.
      (aa)Layout Plan' means a plan of the layout drawn to scale, showing individual building sites, either
      residential, non-residential or industrial, as the case maybe, along with roads, park and open spaces,
      civic amenity sites, public utilities, parking etc;
      (ab) 'Market Value' means the guideline value of the land notified under section 45B of the
      Karnataka Stamp Act, 1957;
      (ac) 'Original plot' means a plot having the same extent that was existing at the time of
      commencement of these rules;
VIT, BENGALURU                                                          DEPT. OF CIVIL ENGINEERING.        96
EXTENSIVE SURVEY PROJECT                                                                               BATCH-5
          (ad) 'Parking Space' means an area enclosed or unenclosed, covered or open, sufficient in size to
          park vehicles together with a driveway connecting the parking space with a public street or any
          public area and permitting the ingress and egress of the vehicles;
          (ae) 'Park and Open Space' means the area reserved in an approved plot for leisure and recreational
          uses;
          (af) 'Person' includes any company an undivided family, an association of persons or a body of
          individuals, whether incorporated or not under law and includes local authorities, Karnataka Housing
          Board, Karnataka Industrial Area Development Board, any other Boards and Corporations
          constituted under respective statutes owned and controlled by state or central government and any
          other state or central government departments.
          (ag)'Plot or Site' means a continuous portion of land held in one ownership;
          (ah) Promoter' as defined in the Real Estate (Regulation and Development) Act, 2016. This is
          synonymous to Developer;
          (ai)      Provisional Layout plan ‘means a Layout plan approved by the Chief Executive Officer or
          Authority, as the case may be, under Section Sub-section (2A) of Section 17 of the Act;
          (aj) Public Utility' means the basic essential services to the public such as water supply, sewerage,
          power supply, fuel stations, gas supply system, telecommunication, public transportation etc;
          (ak) Road or Street' means any street, road, square, Court, alley, passage or riding path over which
          the public have a right of way and includes
    ii.          The footway attached to any such street, public bridge or causeway; and
   iii.          The drains attached to any such street, public bridge or causeway and the land, whether covered
                 or not by any pavement veranda or other structure which lies on either side of the roadway up to
                 the boundaries of the adjacent property, whether that property is private property or property
                 belonging to the Government or the Authority or Local Authority.
(am) Site plan' means a plan of the plot proposed for Approval of plot;
          (an) 'Sub division of plot' means bifurcation of a plot or formation of layout or Integrated Township
          by sub dividing one or more Plots;
VIT, BENGALURU                                                              DEPT. OF CIVIL ENGINEERING.      97
EXTENSIVE SURVEY PROJECT                                                                            BATCH-5
        (ao) Town Planning Officer' means for the purpose of these rules, an officer from the Department of
        Town and Country Planning discharging the duties as-
   i.   'Member Secretary' in case of Planning Authority constituted under section 4C of the Act.
  ii.   Town Planner Member' in case of the Bengaluru Development Authority constituted under the
        Bengaluru Development Authority Act, 1976 and the Urban Development Authority constituted
        under the Karnataka Urban Development Authorities Act, 1987.
 iii.   'Planning Officer' in case of Hampi World Heritage Area Management Authority as constituted
        under the Hampi World Heritage Area Management Authority Act, 2002.
 iv.    'Officer' of the Department of Town and Country planning in the respective District or Subdivision
        in case of Planning Authority constituted under clause (b) of subsection (7) of section 2 for the
        Municipal limits; and
        (ap) Zonal Regulations' means the regulations of the Master Plan governing land use and
        developments prepared under the Act.
        2. The words and expressions, which are not defined in these rules, shall have the same meaning as
        assigned to them in the Karnataka Town and Country planning Act, 1961;
        3. Approval of plot- Initially approval of a plot shall be obtained under these rules specifying the
        development potential and the conditions applicable for development of the plot. Sanction for
        development of a plot shall be accorded only after approval of the plot is obtained as under the
        provisions of these rules.
        4. Types of Approval of plot-
          (1) The following types of approval of plot are sanctioned under these rules, namely:
                     (a) Approval of single plot;
plots other than original plots, 30% of the total extent of plot shall
        Provided that in such cases, the floor area ratio of the plot shall be
   considered for the full extent of plot excluding the area
surrendered to the authority, as mentioned above.
     (5) Fees for single site approval- Fees payable for approval of single
site shall be as specified in Appendix-I.
     (6) Approval of development plan for building development-If one or
more buildings, including group housing to be owned by multiple
persons, jointly or severely, are proposed to be developed in a plot
without bifurcating the plot or without forming a layout, then
building license shall be accorded as per the provisions of building
         Bye-laws, and zoning regulations if development plan approval has
been obtained as per these rules.
      (7) Maximum Extent for development Plan-Approval of a development
plan shall be accorded as per these rules, if the extent of the plot is
upto 2.5 Hectare multiple development plans shall be accorded for
plots having extent over 2.5 Hectare where each development plan
is upto 2.5 Hectare and separated through an internal road of
minimum 12m width and maximum width as specified in
          Appendix-IIA, passing through the plot;
      (8) Floor area ratio of plot-The FAR of the plot in case of
development plan approval shall be considered for the full extent
of plot excluding that reserved for civic amenities;
       (9) FAR of plot providing for Group Housing/community facilities- In case of group housing, where
3% of the total floor area of the building is proposed to be developed as community facilities for the
common use of the occupants, the applicant shall be permitted to utilize the FAR of the area reserved for
civic amenities, in the building/ s. In such cases the area reserved for civic amenities shall be considered as
additional area for park and open space.
          (10) Fees for development plan approval-Fees payable for approval of development plan shall be
          as specified in Appendix-I;
          (11) Approval for bifurcation of plot- Approval for bifurcation of plot shall be accorded for any
          extent of plot, as per these rules; and
          (12) Conditions for bifurcation of plot-No plot shall be permitted to be bifurcated under the
          provisions of these rules unless following conditions are fulfilled, namely:
            (a) The plot is abutting a road having existing width of 9m. In case of Hilly areas, the plot shall
          abut a road having existing width of 6m.
           (b) Both the bifurcated plots shall about the same road which was abutting the plot before
          bifurcation.
           (c) Bi fraction of plot shall not be permitted wherein a bifurcated plot is abutting a road formed
          within the plot that was bifurcated, even if such road is relinquished to the authority or local
          authority.
           (d) A plot may be permitted to be bifurcated any number of times as long as the bifurcated plots
          are having an extent upto 4000Sq.m.
          (e) Any plot having an extent less than 4000Sq.m shall be permitted to be bifurcated only once. if
          the plot is proposed to be bifurcated more than once, then 30% of the bifurcated plots proposed
          for development or change of ownership shall be surrendered to the authority free of cost without
          claiming any form of compensation.
VIT, BENGALURU                                                           DEPT. OF CIVIL ENGINEERING.       100
EXTENSIVE SURVEY PROJECT                                                                           BATCH-5
        (f) Any bifurcated plot shall not be less than 54 Sq.m.; and
        (g) Any bifurcated plot shall have a frontage of 6m.
        (13)   Approval for bifurcation of plot for building development-If building development is
        proposed in a bifurcated plot, approval for bifurcation of plot, shall be obtained as per these rules
        along with single site approval or development plan approval, as the case may be, before building
        licence is accorded under the provisions of building Bye-laws;
         (14) Fees for bifurcated plot approval-Fees payable for approval for bifurcation of Plot shall be
        as specified in Appendix-I;
        (15) Approval of layout-Approval of layout shall be accorded for any extent of plot, under these
        rules. layout proposed in plot/ s having extent over 25 Hectare shall be considered as integrated
        township and shall be developed incorporating the additional standards or conditions prescribed
        in these rules;
        (16) Approval of layout for building development-If one or more buildings to be owned by single
        or multiple persons, jointly or severely, are proposed to be developed in a building site of
        anapproved Layout, then building license shall be accorded as per the provisions of building Bye-
        laws without any other plot approval; and
         (17) Standards/conditions applicable for approval of layout- The following standards or
        conditions shall be incorporated while preparing and sanctioning layout plans namely: -
        (a)Standards for roads- The standards for hierarchy, width, vertical alignment etc. of roads
        proposed in the layout shall be as specified in Appendix-IIA;
        (b) Standards for street lighting and power supply lines- Lux levels for the illumination of roads
        from streetlights shall be as specified by the competent authority. Underground cable or overhead
        cable shall be provided in the layout as specified by competent authority;
        (c) Standards for storm water drains-The cross section of storm water drains, both road side drains
        as well as main drains in the layout, shall be as specified in Appendix-AB;
        (d) Standards for building sites-The standards for minimum size, minimum frontage, etc. of
        building sites for residential, commercial, other non-residential and industrial use, as the case may
        be, shall be as specified in Appendix-IIC;
        (e) Standards for public utilities-The space to be provided for various public utilities shall be as
        specified in Appendix-ID;
        Provided that in cases where public utility land use of the master plan is falling within the layout,
        the same shall be earmarked for that purpose only and shall be considered towards any public
        utilities proposed in the layout.
        (f) Standards for buffers for HT line- The corridor for HT lines
        (g) Standards for buffers for natural storm water drains and other water bodies- The buffer for
        natural storm water drains and other water bodies shall be provided as notified by the
        Government; and
         (h)Standards for buffers/No development zone in case of archaeological and other monuments-
        The buffer/no development zone in case of archaeological monuments shall be as prescribed in
        the Zonal Regulations of the Master Plan for the respective local planning area or as prescribed by
        the Archaeological survey of India (ASI);
         (18) Additional standards or conditions for integrated townships-Additional standards/ conditions
        shall be adopted for the development of integrated townships as specified in Appendix-IIE;
          (19) Guidelines for preparing layout plan and infrastructure plans- The layout plan and
        infrastructure plans shall be prepared as per the Guidelines notified by the government.
         (20) Contents of drawings for different types of plot approvals- The drawings to be submitted for
        the different types of approval of plot shall contain the following details-
          (a) Site plan for single site approval- The site plan submitted for single site approval shall be
      prepared containing the details specified in Appendix-IIIA;
          (b) Site plan for development plan approval-The site plan submitted for development plan
        approval shall be prepared containing the details specified in Appendix-IIIB;
          (c) Site plan for approval of bifurcation of plot- The site plan submitted for approval of
        bifurcation of plot shall be prepared containing the
        approval of details specified in Appendix-IIIC;
        (d) Site plan for layout: The site plan submitted for approval of layout shall be prepared
        containing the details specified in Appendix-
        (e) Key plan for approval of layout- The key plan submitted for approval of layout shall be
        prepared containing the details specified in Appendix-V;
         (f) Layout plan for approval of layout- The layout plan submitted for approval of layout shall be
         prepared containing the details specified in Appendix-V; and
      (g) Infrastructure plans for approval of layout-The following infrastructure plans shall be submitted
      for approval of layout containing the details specified in the respective appendix, namely: -
         (i) Ground levels of the layout-The drawing showing the ground levels of the layout shall be
                 prepared containing the details specified in Appendix-VIA;
         (ii) Road network- The drawing showing the road network in the layout shall be prepared
                 containing the details specified in Appendix-VB;
         (iii)          Water supply network- The drawing showing the water supply network in the layout
                 shall be prepared containing the details specified in Appendix-VIC;
         (iv)Sewerage network- The drawing showing the sewerage network in the layout shall be
                 prepared containing the details specified in Appendix-VD;
         (v) Power supply network including renewable energy- The drawing showing the power supply
                 network including renewable enerw, in the layout shall be prepared containing the details
                 specified in Appendix-VIE;
         (vi)Storm water drain network-The drawing showing the storm water drain network in the layout
                 shall be prepared containing the details specified in Appendix-VIP;
         (vii)          Solid waste management system- The drawing showing the solid waste management
                 system in the layout shall be prepared containing the details specified in AppendixVIG, and
         (viii)         Tree plantation and Landscape scheme- The drawing showing the tree plantation and
                 landscape scheme in the layout shall be prepared containing the details specified in
                 Appendix-VIH.
         4. Relinquishment of areas reserved for parks and open space and civic amenities- The Owner
                 [developer shall execute a relinquishment deed in favour of the authority, for the areas
                 reserved for roads, park and open spaces and civic amenities in the prescribed format, and the
                 authority shall hand over the roads and park and open spaces to the local authority, after the
                 defect liability period, in the prescribed format.
  6. Procedure for obtaining approval of Plot-The following procedure shall be adopted for obtaining
  approval of Plot, namely: -
   (1) Application for NOCs and approval of plot.-Common application for NOCs from relevant
  departments and plot approval from the authority shall be made by the applicant in the format prescribed
  in Form-I along with site plan (along with key plan, layout plan, infrastructure plan and cost of
  developing infrastructure derived based on the prevailing schedule of rates, in case of layout), copies of
  the documents specified in Appendix-VII, Affidavit or undertaking from owner or promoter and
  professionals on record in the prescribed format, drawings and documents required for NOCs from the
  relevant departments, scrutiny fee specified in Appendix-I and the applicable fees payable for obtaining
  NOCs from the relevant departments;
  (2)Verification of documents submitted- The CEO shall verify the documents submitted along with the
  application and if found in order, will accept the application. In case of any discrepancy, the CEOsha11
  issue an endorsement in Form-Il to the applicant stating the discrepancy and the applicant may rectify the
  same and resubmit to the authority; and
  (3) Evaluation of Site Plan submitted- If the application is accepted after finding that the documents
  submitted along with the application are in order, the TPO shall evaluate the site plan along with Key
  Plan submitted by the applicant, for compliance with the provisions of these rules:
  Provided that in case of any discrepancy, the CEO shall issue endorsement in Form-Ill to the applicant
  stating the discrepancy and the professional on record who has prepared the drawing may rectify the
  same and resubmit to the authority.
  (4) Submission of Site Inspection Report- If the site plan is accepted by the TPO, the CEO shall get the
  site inspection done from the empanelled professional (empanelled by the respective local authority
  which has the jurisdiction of the plot and selected based on the pre-determined logic and competence
  specified in the Building Bye-laws) or the designated officer notified by the Government and the
  empanelled professional or the designated officer, as the case may be, shall inspect the site and prepare
  site inspection report (as detailed in Appendix-VIII), in Form-IV;
  (5) Action in case of discrepancy in site inspection report-If the Site Inspection Report contradicts to the
  details submitted by the applicant, the CEO shall issue an endorsement to the applicant stating the
  discrepancy and the professional on record who has prepared the drawing may rectify the same and
  resubmit to the Authority;
  (6) Sanction and issue of plot approval- Sanction and issuing of various types of Plot
  Approvals shall be done by authority as follows, namely:
  (i) lf the TPO accepts the drawing submitted for plot approval and the site inspection report being
  consistent with the details submitted by the applicant, the TPO shall recommend to the CEO of the
  Authority for sanction of the Single Site or Development Plan or Bifurcation of plot, as the case may be,
  and the CEO shall sanction such plot approval within the timelines specified in Appendix-IX;
  (ii) The Authority shall intimate the Applicant to pay the required fees (as specified in Appendix-I) for
  issuing the respective plot approval and to execute the Relinquishment Deed for the areas reserved for
  roads, park and open spaces and civic amenities, as the case may be, in favor of the authority; and
  (iii) The Authority shall issue the respective plot approval in Form-V after receiving the required fees
  from the applicant along with copy of the Relinquishment Deed.
  (b) Layout plan- Sanction and issuing of plot approval in case of layout is done in two stages, i.e.,
  provisional layout approval and final layout approval, after following the additional process as under rule
  6. (6) (c)
  (c)Additional process involved in Layout approval- The following additional process are involved for
  approval of layout, namely: -
  (i) Scrutiny of Layout Plan submitted- If the site inspection report is consistent with the site plan
  submitted, the TPO shall scrutinize the layout plan submitted by the applicant, for compliance with the
  conditions/ standards prescribed in the various appendices of these rules and the guidelines notified by
  the government
  (ii) Scrutiny of Infrastructure Plans submitted-If the layout plan is accepted empanelled professionals or
  the designated officers as notified by the Government, shall scrutinize the various infrastructure plans
  with reference to the conditions/ standards prescribed in the various Appendices of these rules and the
  guidelines notified by the government.
  (iii) Correction of deviation in Layout Plan or Infrastructure Plan-
   (a) During the scrutiny of layout plan, if the TPO is of the opinion that the layout plan submitted is in
  deviation/violation of the conditions or standards prescribed in the respective Appendix of these rules or
  is not in accordance with the guidelines notified by the government, he shall submit his opinion to the
  CEO.
   (b) Similarly, during the scrutiny of infrastructure plans, if the empanelled professionals or the
  designated officers as notified by the Government, is of the opinion that the Infrastructure plans
  submitted are in deviation or violation of the conditions or standards prescribed in the respective
  appendix of these rules or is not in accordance with the guidelines notified by the government, they shall
  submit their opinion to the CEO;
   (c)   If the CEO is satisfied with the opinion of TPO or the empanelled professionals or designated
  officers as notified by the Government, as the case may be, the CEO shall issue an endorsement to the
  applicant stating the reasons for corrections required and the professional on record who has prepared the
  respective drawings which requires corrections, may modify the same to rectify the deviations or
  violations stated by the TPO or the empanelled professionals or designated officers as notified by the
  Government, as the case may be and resubmit to the authority.