ABC Numerical

Uploaded by

bando007
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Atharva Engineering Company Ltd.

, produces three products for which standard cost and


quantities per unit are as follows:
Products A B C

Output In units 10,000 20,000 30,000


Direct material In Rs. 50 40 32
per unit
Direct labour In Rs. 30 40 48
per unit
Labour hours 3 4 5
per unit
Machine hours 4 4 7
per unit
No. of purchase 600 900 1000
requisitions
No. of machine 120 130 150
set-ups

Production Overhead split by departments:


Department X- Rs.12,00,000; Y-Rs.15,00,000.
Department X is labour intensive and Y is machine intensive.
Total labour hours in Department X =2,00,000; Total machine hours in Department Y =
5,00,000.
Production overhead split by activity:
Receiving and Inspection – Rs.14,00,000 and Production scheduling/setup- Rs.13,00,000.
No. of batches received/inspected- 2500, No. of batches for scheduling/setup- 400.
Question:
a. Prepare cost statement under traditional absorption costing and activity based costing
methods. Also compare the result of the two methods and give your comments.