C TSCM42 64
C TSCM42 64
The company you advise wants to carry out the material availability check automatically in the
production order at various points in time. Which of the following options would you recommend?
(Choose two.)
Answer: B,D
Explanation:
QUESTION NO: 2
What repetitive manufacturing options can you use to carry out line loading in the SAP ECC
system and thus generate Run Schedule Quantities (RSQ) from normal planned orders?
(Choose three.)
A. Automatic selection of the production version in material requirements planning (MRP) using
Selection Methods setting.
B. Manual assignment of planned production quantities in a planning table.
C. Automatic selection of the production version by applying quota arrangement records in
material requirements planning (MRP).
D. Using a planning algorithm from capacity planning.
E. Selecting a suitable repetitive manufacturing profile that contains an option for automatic line
selection.
Answer: A,B,C
Explanation:
QUESTION NO: 3
Which statements are true for ECC Long-Term Planning (LTP)? (Choose two.)
Answer: A,C
Explanation:
QUESTION NO: 4
Which of the following activities within the KANBAN procedure normally triggers subsequent stock
posting of the goods receipt?
Answer: D
Explanation:
QUESTION NO: 5
Which of the following elements do you have to prepare for costing of a production order to
function without errors? (Choose three.)
Answer: A,D,E
Explanation:
QUESTION NO: 6
In which of the following objects can you activate backflushing of components if you want to use
this functionality during order confirmation? (Choose three.)
A. Work Center
Answer: A,D,E
Explanation:
QUESTION NO: 7
Which of the following master data do you need to provide for process manufacturing?
(Choose three.)
A. Resources
B. Master recipe
C. Serial numbers
D. Product cost collector
E. Production versions
Answer: A,B,E
Explanation:
QUESTION NO: 8
In your company planning strategies are used in the SAP-ECC demand management that are
based on consumption. Which of the following statements about consumption is true?
(Choose two.)
A. A consumption situation is dynamic and is always restructured with the planning run.
B. Consumption can also take place between order reservations and planned independent
requirements, depending on the strategy.
C. Consumption always takes place on the material level between the planned independent
requirements and the planned orders.
D. The consumption parameters (consumption mode and consumption interval) can be set in the
material master or in the MRP group.
Answer: B,D
Explanation:
QUESTION NO: 9
In production order processing, for which of the following objects can you enter a confirmation?
(Choose three.)
A. Work Center
B. Individual Capacity
C. Order
D. Operation / Suboperation
E. Trigger Point
Answer: B,C,D
Explanation:
QUESTION NO: 10
(Choose three.)
A. Bill of Materials
B. Work Center
C. Task List
D. Production Version
E. Material Master
Answer: A,C,E
Explanation:
QUESTION NO: 11
When analyzing the SAP ECC order report for a planned order for a finished product, you discover
that one of the assemblies will not be available in time for the scheduled final assembly because of
automatic forward scheduling.
Which planning procedure would you use to process the problem in order to create a solution that
is feasible from a requirements planning perspective?
Answer: A
Explanation:
QUESTION NO: 12
Which of the following statements about the SAP Solution Manager listed is correct?
Answer: C
Explanation:
QUESTION NO: 13
In SAP ECC, you want to map an in-house production process for general warehouse production.
The fields in the area of the lot size-dependent in-house production time are to be populated when
the material master for the final product is created. These fields can be maintained by updating
from the scheduling result for the associated routing. You now think that there could be significant
changes to the production times in the routing and decide against updating the material master.
What problem could this lead to?
A. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
B. Requirements planning runs up against an exception message in basic dates scheduling
because the material master parameters do not match the scheduling result from the routing.
C. In the course of basic dates scheduling with requirements planning, dependent requirements
request the components from the bill of materials at the wrong times.
D. Lead time scheduling, which occurs by the time that a planned order is converted into a
production order (at the latest), cannot take place on the basis of incorrect basic dates.
Answer: C
Explanation:
QUESTION NO: 14
Which of the following requirements for a manufacturing plant can be supported by using process
manufacturing? (Choose three.)
Answer: A,D,E
Explanation:
QUESTION NO: 15
Which objects can you use in the production order for a material component to propose the
storage location in its reservation? (Choose three.)
A. Routing
B. Work center
C. Material master (component)
D. Material master (product)
E. Production version
Answer: B,C,E
Explanation:
QUESTION NO: 16
From what point can you no longer use the Read PP master data in the production order?
QUESTION NO: 17
Which options can you offer someone who uses the SAP ECC system for production orders and
requires support for material supply in production? (Choose three.)
Answer: A,C,D
Explanation:
QUESTION NO: 18
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use
formula parameters for calculation. What can be the origin of the formula parameters used for
scheduling? (Choose three.)
Answer: B,C,D
Explanation:
QUESTION NO: 19
A user has entered planning strategy group 10 (make-to-stock production) in the material master
(SAP ECC) of a product. For the coming months, requirements with requirement type LSF
(derived from the main strategy 10) have been planned. The user would like to change the
requirement type from LSF to VSF planning with final assembly (in accordance with planning
Which of the following statements are applicable in this case? (Choose two.)
A. The user has to change the requirement type for planning strategy 10 to VSF planning with final
assembly in Customizing. The requirement type for all existing requirements is then changed
automatically.
B. The present requirement for the product can be changed manually from LSF to VSF in the
Requirement Type field in the production plan, so that the new strategy 40 determines the next
planning operation.
C. The user can enter the new planning strategy group 40 in the material master of the product,
but the requirement type is not changed automatically for existing requirements.
D. The planning strategy group can be changed from 10 to 40 in the existing production plan, and
the requirement type for all requirements is changed automatically.
Answer: B,C
Explanation:
QUESTION NO: 20
Which of the following statements about the planning functions available in SAP ECC are true?
(Choose two.)
Answer: A,B
Explanation:
QUESTION NO: 21
Which data forms the basis for calculating the capacity requirement for an operation?
(Choose three.)
Answer: A,D,E
Explanation:
QUESTION NO: 22
A user you advise wishes to transfer variable process instructions for automated processing
directly to certain work centers and machines in the production department (for example, feed
speed, pressing pressure, dry temperature). The user also wishes to receive variable as-is
messages (such as actual quantities, actual times) from these work centers and machines and to
process these messages for feedback concerning production orders. Which of the following
options would you recommend to implement these requirements?
Answer: A
Explanation:
QUESTION NO: 23
In SAP ECC, you calculate the standard available capacity for a work center capacity with the
following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization:
80%, overload. 110%, number of individual capacities: 1.
A. 7 hours
B. 8 hours
C. 5.6 hours
D. 6.16 hours
Answer: C
Explanation:
A finished material is to be planned in a controlled manner in the SAP ECC system in the context
of requirements planning. The planned orders are scheduled using what is known as basic date
scheduling (not lead-time scheduling). Which of the following statements is true for the resulting
dependent requirements?
A. When a customer order is created for the finished product, the dependent requirements are
automatically triggered for the components in the bill of material without a planning run.
B. In multi-level backward scheduling, dependent requirements are triggered at the start date for
the higher-level assembly.
C. In multi-level backward scheduling, dependent requirements are triggered at the start date for
the higher-level assembly planned order.
D. If individual material components are explicitly assigned to operations during BOM and routing
maintenance, the requirement dates of the dependent requirements for these components are
scheduled at each of the operation start dates.
Answer: B
Explanation:
QUESTION NO: 25
Which production order function can no longer be carried out after the order is released?
Answer: B
Explanation:
QUESTION NO: 26
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure
(net change planning in the planning horizon). The planning horizon is to be set equally for all
materials by default. However, some materials are to be given a different planning horizon.
What procedure would you recommend to the project team for setting the planning horizon on the
system side?
Answer: B
Explanation:
QUESTION NO: 27
Which of the following efforts can be minimized using the KANBAN procedure?
Answer: A
Explanation:
QUESTION NO: 28
In the SAP ECC system, a material is produced with the help of production orders. Though
originally used for rate-based planning only, the planning table is to be used to plan this material.
On the initial screen of the planning table, you select this material and then receive a message
informing you that you cannot use the planning table for this material.
Answer: B
Explanation:
QUESTION NO: 29
Which functions lead to a reduction in the capacity requirement for an individual operation at a
work center? (Choose three.)
Answer: C,D,E
Explanation:
QUESTION NO: 30
With which functions of the process order can you fulfill the requirements of the Good
Manufacturing Practices (GMP) standard? (Choose three.)
Answer: A,C,E
Explanation:
QUESTION NO: 31
The company you advise wants to control the availability check in so that when a production
and/or process order is created, the following receipts or issues are taken into account: planned
orders, purchase orders, production orders, reservations, dependent requirements. When the
production and/or process order is released, only the stock that is currently freely usable should be
taken into consideration. How can you fulfill this request?
Answer: A
Explanation:
QUESTION NO: 32
Which of the following statements is true for the ATP (available to promise) availability check in
SAP ECC that is triggered from a customer order?
A. The ATP check does not confirm against stocks and receipts, it checks consumption against
planning requirements.
B. An availability check by means of ATP creates fixed links between customer orders and their
confirmed receipts.
C. The ATP quantity is the quantity still available that can be used to confirm incoming customer
orders.
D. If the ATP check establishes non-availability, it checks whether it is still possible to procure or
produce in time.
Answer: C
Explanation:
QUESTION NO: 33
Which of the following structural elements does a process order have? (Choose three.)
A. Item data
B. Parallel sequences
C. Relationships
D. Phases
E. Characteristic-based process instructions
Answer: C,D,E
Explanation:
QUESTION NO: 34
Which of the following situations occur when a production order is set to Technically Complete
A. The order and its operations receive the system status Locked (LKD).
B. Reservations are deleted.
C. Purchase orders for external operations or non-stock materials are deleted.
D. The order is no longer relevant for Material Requirements Planning.
E. Capacity requirements are deleted.
Answer: B,D,E
Explanation:
QUESTION NO: 35
The master data for an in-house production process is to be set up in the SAP ECC system. To do
this, you should create a suitable routing that plans for five operations in an initial sequence (10,
20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second
sequence on other work centers if there are capacity bottlenecks. What sequence type would you
use to create the second sequence in the system?
A. Substitute sequence
B. Alternative sequence
C. Parallel sequence
D. Standard sequence
Answer: B
Explanation:
QUESTION NO: 36
Which of the following are properties of ECC Multi-Site Planning? (Choose two.)
A. Both withdrawal from alternative plant and withdrawal from another plant are defined via special
procurement keys.
B. The use of scope of planning (cross-plant total planning) is mandatory for Multi-Site Planning.
C. When using one-step stock transfer posting, transfer stock is created in the receiving plant.
D. When using two-step stock transport order with delivery, the receiving plant is defined as a
customer.
Answer: A,D
Explanation:
QUESTION NO: 37
A. SAP ERP is a system hardware that includes modules for purchasing, sales and distribution,
materials management, production and so on.
B. SAP ERP is a technological platform on the basis of which customer-specific extensions can be
imported.
C. SAP ERP is an application that an enterprise can use to manage its business processes
efficiently.
D. SAP ERP is a planning system in which extended planning processes can be mapped.
Answer: C
Explanation:
QUESTION NO: 38
A final assembly process takes place at three work centers, one after the other. The routing, which
consists of three associated operations (10, 20 and 30), plans for a specific BOM component to be
installed during operation 30 and not before. The component should therefore only be requested
at the start of operation 30.
What sequence do you follow in master data maintenance in SAP ECC to make this component
available in line with operations during final assembly?
A. 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in
BOM or routing
B. 1. Create work centers 2. Create routing 3. Create BOM 4. Carry out component assignment in
work center
C. 1. Create routing 2. Create work centers 3. Create BOM 4. Carry out component assignment in
BOM or routing
D. 1. Create BOM 2. Create work centers 3. Create routing 4. Carry out component assignment in
work center
Answer: A
Explanation:
Answer: B,C
Explanation:
QUESTION NO: 40
Which of the following statements about ATP (Available To Promise) checks for material
components are correct? (Choose two.)
A. ATP checks are automatically performed during MRP (Material Requirements Planning) runs.
B. ATP checks can be adjusted to also consider future requirements and receipts.
C. ATP checks are used to evaluate the free capacity on a certain work center.
D. ATP checks can be carried out automatically when releasing a production order.
E. ATP checks are mandatory for lead-time scheduling.
Answer: B,D
Explanation:
QUESTION NO: 41
Which options can you offer a user of the SAP ECC system for managing costs (costing and
settlement) with regards to production orders? (Choose two.)
A. Series-based costing
B. Work center-based costing
C. Order-based costing
D. Product cost collecting
Answer: C,D
Explanation:
QUESTION NO: 42
A project team member analyzes the following situation in SAP ECC in the stock/requirements list
for a finished product: there is only one customer order and one fixed planned order with a similar
quantity amount. The customer order and the planned order both have deadlines on work days but
not on the same work day; the planned order has a later deadline. The project team member
cannot find a rescheduling message referring to this deadline misalignment in the
stock/requirements list. What reasons could there be for the missing message? (Choose two.)
A. Requirement planning has not yet been carried out to update the rescheduling message.
B. The elements are linked to each other via fixed pegging.
C. The time misalignment falls within the tolerance window defined in Customizing.
D. The requirement coverage element is outside the rescheduling horizon.
Answer: C,D
Explanation:
QUESTION NO: 43
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2,
P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of
these alternatives represents a firming type. What does a firming type define? (Choose two.)
Answer: A,B
Explanation:
QUESTION NO: 44
In what order are the individual steps of material requirements planning performed in SAP ECC?
Answer: D
Explanation:
QUESTION NO: 45
Which of the following master data is mandatory for production order processing, when material
reservations and capacity requirements for operations should be generated automatically?
(Choose two.)
A. Routing
B. Inspection characteristics
C. Document structure
D. Production versions
E. Material master records (product and material component)
Answer: A,E
Explanation:
QUESTION NO: 46
In the course of a customer project, you are confronted with an SAP ECC system that shows the
error message displayed below when you test requirements planning in plant 1000. Large
numbers of materials are already available in plant 1000. As a first step in solving the problem,
you activate requirements planning in the Customizing for plant 1000.
What further steps must you take before you can put requirements planning in plant 1000 into
operation in SAP ECC?
A. - Implement the planning files in Customizing- Specify the plant parameters for plant 1000 in
Customizing
B. - Activate requirements planning in Customizing for MRP areas in plant 1000- Specify the plant
parameters for plant 1000 in the requirement planning views
Answer: D
Explanation:
QUESTION NO: 47
Which of the following master data do you need to make available for repetitive manufacturing?
(Choose three.)
Answer: B,D,E
Explanation:
Which of the following statements is true for the simulation mode in the context of material
requirements planning in SAP ECC?
Answer: The simulation mode is used in scenarios in which requirements planning created the
procurement element prematurely in terms of demand.
Answer: The simulation mode opens the analysis of the delay time. Manual rescheduling of the
receipt in the finished product and subsequent requirements planning lead to a solution that is
feasible from the requirements planning perspective. However, this solution may lead to a
date/time violation in the finished product.
Answer: The simulation mode represents an interactive multilevel form of planning, the result of
which is automatically posted to the database after the planning run.
Answer: Assuming a delay time in the critical path, the simulation mode triggers multilevel bottom-
up scheduling through to the finished product, which therefore receives a delayed receipt.
Answer: B
Which of the following features are offered by MRP Areas (Material Requirements Planning
Areas)? (Choose two.)
Answer: A,B
Explanation:
QUESTION NO: 50
A supply chain planning run is to be carried out in the SAP ECC system as an example.
What would be the most effective sequence in which to run through the planning modules?
Answer: B
Explanation:
QUESTION NO: 51
(Choose three.)
A. Copying a document that is assigned to the material master for the product to be produced
B. Calculating the lead time for the production order
C. Selecting and copying a bill of material
D. Selecting and copying a routing
Answer: B,C,D
Explanation:
QUESTION NO: 52
Which of the following master data do you always have to make available for material
replenishment using the KANBAN procedure? (Choose two.)
A. Control cycles
B. Production supply areas
C. Product cost collector
D. Rate routings
E. Production versions
Answer: A,B
Explanation:
QUESTION NO: 53
A material was planned in the context of SAP ECC material requirements planning and the MRP
controller subsequently processed the material by manually converting a specific planned order
into a production order. The MRP controller now accesses the current stock/requirements list and
the MRP list for this material and compares the two.
Which of the following statements are true for the two lists at this stage? (Choose two.)
Answer: C,D
Explanation:
QUESTION NO: 54
A. The plant for which the routing and BOM have to be created
B. All the control parameters for selecting routings and bills of material
C. The routing and BOM alternatives to be used for production
D. The explosion date on which the validity of the routing and bill of material is checked
Answer: C
Explanation:
QUESTION NO: 55
A new material with the following properties is to be recorded in SAP ECC. the material is kept in
stock, is externally procured, and is used as a component in the bills of material for various final
products. However, this material may not be purchased directly.
Answer: D
Explanation:
QUESTION NO: 56
Which of the following activities is necessary for the capacity availability check to be carried out
automatically when a production order is released?
A. Activate the availability check and assign a checking rule to the work center for the operation to
be checked.
B. Activate the availability check and assign the check control to the plant.
C. Activate the availability check and assign an overall profile in check control for the business
function order release.
D. Activate the availability check and assign an availability checking group to the material master
for the product to be produced.
Answer: C
Explanation:
QUESTION NO: 57
A customer has been using planning strategies 30 (production by lots) and 10 (anonymous make-
to-stock production) in SAP ECC. The customer wishes to move in part to planning strategy 40
(planning with final assembly). The issue of consumption has an effect here for the first time.
Which properties apply for consumption with planning strategy 40? (Choose two.)
A. Consumption can lead to an increase of the originally planned overall production quantity.
B. Consumption can result in the subsequent specification and adjustment of planning elements in
terms of quantity and date, by means of customer orders that arrive.
C. Consumption can reduce the originally planned production quantity.
D. Consumption creates a static and binding assignment, between the planned independent
requirements recorded in advance and the customer requirements that arrive, for the entire
procurement process.
Answer: A,B
Explanation:
QUESTION NO: 58
(Choose three.)
Answer: A,C,D
Explanation:
QUESTION NO: 59
What options for selecting a routing exist when creating a production order?
Answer: A,B,D
Explanation:
QUESTION NO: 60
Which functions are included in the scope of the Service Desk? (Choose two.)
A. SAP Help
B. Managing SAP Notes
C. Process for processing messages
D. Troubleshooting
Answer: B,C
Explanation:
QUESTION NO: 61
Which of the following prerequisites have to be fulfilled for production orders to be transferred to a
business data entry system via the Plant data collection (PP-PDC) interface? (Choose three.)
Answer: B,C,E
Explanation:
QUESTION NO: 62
In modeling in-house production using SAP ECC, bills of material (BOM) are to be recorded in the
system. On which business levels can you create a BOM? (Choose two.)
Answer: C,D
Explanation:
QUESTION NO: 63
The master data for a logistical process is to be stored in the SAP ECC system. In this context,
you require the production versions for subsequent planning and production. You know a mass
maintenance transaction that you could use here. Where else in the SAP ECC system could you
define production versions?
Answer: A
Explanation:
QUESTION NO: 64
For a specific end product, you want to use a planning time fence and fixing type 1 to ensure that
the planning situation in SAP ECC calms down in a short-term time window. Two customer orders
arrive at short notice and their receipts should really be within the planning time fence, due to their
date/time. Which statement is true with this scenario?
A. Within the planning time fence, the newly created planned orders are automatically frozen by
requirements planning (roll forward).
Answer: B
Explanation:
QUESTION NO: 65
Answer: A,D
Explanation:
QUESTION NO: 66
Which of the following possible errors would lead to the message shown? (Choose two.)
A. In the material master, plan selection was set to production version. A production version was
created and it is faulty.
B. There are no valid routings or no routings available on the explosion date.
C. The Customizing for the order type is set to manual routing selection and a valid routing exists.
D. The material master (product) is set to manual routing selection and valid routing exists.
Answer: A,B
Explanation:
QUESTION NO: 67
In the course of a project phase, the customer raises some questions concerning parameters of
the procurement type in the material master in the SAP ECC system. Which of the following
A. A material's procurement type can always be freely selected between E (in-house production),
F (external procurement) and X (both procurement types).
B. If procurement type E (in-house production) is set, external procurement may still be
permissible.
C. If both procurement types are allowed with entry X, requirements planning assumes in-house
production.
D. Procurement types E (in-house production) and F (external procurement) have to be further
refined with special procurement types.
Answer: B,C
Explanation:
QUESTION NO: 68
Which properties does ECC Master Production Scheduling (MPS) have? (Choose three.)
A. MPS items can be taken into consideration by a standard MRP run (Material Requirements
Planning).
B. MPS items can be defined on MRP Area level (Material Requirements Planning Area).
C. Non-MPS items can be taken into consideration by an MPS run.
D. MPS items can be defined on plant level.
E. The planning of MPS and Non-MPS items is always carried out in one planning run.
Answer: B,C,D
Explanation:
QUESTION NO: 69
A customer wishes to only produce a finished product when customer orders for it are present.
Final assembly should then be carried out at short notice in make-to-order production. Up until this
point, the important assemblies needed in final assembly should already be available in stock.
Provision of these assemblies should therefore be triggered by planning.
Which options could you offer the customer as useful alternatives in SAP ECC?
(Choose two.)
A. The finished product uses strategy 40 (planning with final assembly) and all the important
Answer: C,D
Explanation:
QUESTION NO: 70
Which one of the following scheduling types cannot be assigned as default to an order type
(production order)?
A. Midpoint
B. Forward
C. Only capacity requirements
D. Backward
Answer: A
Explanation:
QUESTION NO: 71
In your enterprise, a planning strategy is used in SAP ECC that enables joint planning of all MRP
scheduled assemblies for a finished product to trigger procurement of these assemblies. It is
important to ensure that the finished product is only produced when there is a customer order
present. When a customer order is received, production of the finished product should be triggered
in the form of make-to-order planning and production.
QUESTION NO: 72
An enterprise based in the USA produces an end product that is used with the unit of measure
"pound" (LB). The material is now to be marketed in the EU. A prerequisite for this is that the
material can be sold with the unit kilogram (KG).
A. In the basic data customizing, you create a unit of measure group that converts pounds to
kilograms. You then assign this to the material master on basic data view 1.
B. You create a new material with a reference to the original material and assign the metric unit of
measure to the new material master.
C. In the material master, you create a conversion factor for converting pounds to kilograms on
basic data view 1.
D. There is no need to take any action. There is a general conversion in the central customizing of
units of measurements, so that automatic conversion of pounds to kilograms takes place.
Answer: D
Explanation:
QUESTION NO: 73
Which of the following functions are available in the SAP ECC system for leveling overloads in
individual work centers with the capacity planning tools? (Choose three.)
A. Midpoint scheduling
B. Batch size optimization
C. Lot size optimization
D. Setup time reduction
E. Finite capacity scheduling
Answer: A,D,E
Explanation:
QUESTION NO: 74
A. Using the special procurement key subcontracting in the material master for the component
B. Using the special procurement key direct procurement/external procurement in the material
master for the component
C. Using the item type non-stock item in the bill of material for the material in question
D. Using the procurement type external procurement in the material master for the component
E. Controlling the material in question as a co-product
Answer: B,C
Explanation:
QUESTION NO: 75
In SAP ECC, a customer tests the firming options for planned orders. The customer first sets the
manual firming date from the stock/requirements list to firm planned orders that shall occur in the
short term. In the material master, a rolling planning time horizon with firming type 1 is active.
Some planned orders have also been firmed manually already.
A. The firming interval is specified by the manual firming date because it always overrides the
planning time fence from the material master; all the manually firmed planned orders are firmed
independently of this.
B. The firming interval is specified by the firming mechanism that currently stretches further into
the future and which firms planned orders that are within it; all the manually firmed planned orders
are firmed independently of this.
C. The firming interval is specified by the firming mechanism that currently stretches further into
the future; all the planned orders within this horizon are firmed only if they were previously firmed
manually.
D. The firming interval is specified by the planning time fence from the material master, because
this always overrides the manual firming date; all the manually firmed planned orders are firmed
independently of this.
Answer: B
Explanation:
Which of the following requirements for a manufacturing plant can be supported by using
production orders? (Choose three.)
A. Variable calculation of material quantities (production output, material usage) and operation
quantities.
B. Integrated display of documents (drawings, texts) in the production process.
C. Make-to-stock production.
D. Orderless production.
E. Customer requirements-dependent production.
Answer: B,C,E
Explanation:
QUESTION NO: 77
The user you advise requests that you make it possible for the user to produce materials for stock,
for customer orders, projects, orders and cost centers with production orders.
Answer: B
Explanation:
QUESTION NO: 78
A. The procurement quantity of a lot size procedure can be specified using a safety time period
profile.
B. If a long-term lot size is in use, procurement is conducted with a long-term perspective.
C. If a make-to-order production strategy is in use, a lot for lot (exact) lot size is always determined
for the corresponding procurement element.
D. The lot size quantity can be influenced using a minimum quantity and the rounding profile.
QUESTION NO: 79
A. Work Center
B. Material Master
C. Routing
D. Production Resource/Tool (PRT)
Answer: C
Explanation:
QUESTION NO: 80
An enterprise wants to absorb the uncertainty caused by fluctuating demand for a finished product
by means of a buffer variable in SAP ECC. They suggest a dynamic safety stock.
Answer: A
Explanation: