0% found this document useful (0 votes)
149 views2 pages

Summary of Estimates of Bills of Materials: I-Concrete Works

The document is a summary of estimates for the materials and labor costs for a proposed commercial building project located on Arnaldo Boulevard in Roxas City. It includes estimated costs for concrete works, steel works, masonry works, painting works, carpentry works, doors and windows, and notes the total project cost is estimated to be ₱2,346,739.05. Labor costs are estimated to be 35% of the materials costs, or ₱345,493.05. The estimates provide a breakdown of anticipated costs for various building materials like cement, rebar, concrete blocks, paint, and wood.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
149 views2 pages

Summary of Estimates of Bills of Materials: I-Concrete Works

The document is a summary of estimates for the materials and labor costs for a proposed commercial building project located on Arnaldo Boulevard in Roxas City. It includes estimated costs for concrete works, steel works, masonry works, painting works, carpentry works, doors and windows, and notes the total project cost is estimated to be ₱2,346,739.05. Labor costs are estimated to be 35% of the materials costs, or ₱345,493.05. The estimates provide a breakdown of anticipated costs for various building materials like cement, rebar, concrete blocks, paint, and wood.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT TITLE: PROPOSED COMMERCIAL BUILDING

LOCATION: ARNALDO BOULEVARD,ROXAS CITY


OWNER: FAR EAST NOBLE HOUSE INC.
PREPARED BY:

Summary Of Estimates Of Bills Of Materials

I-Concrete Works
a. Footing And Column
95 bag/s - cement 245 /bag ₱23,275.00
15 cu.m. w.gravel 830 /cu.m ₱12,450.00
8 cu.m. w.sand 650 /cu.m. ₱5,200.00

b. Roof Beam,Tie B ,tie beam


95 bag/s - cement 245 /bag ₱23,275.00
15 cu.m. w.gravel 830 /cu.m ₱12,450.00
8 cu.m. w.sand 650 /cu.m. ₱5,200.00

c. Slab
297 bag/s - cement 245 /bag ₱72,765.00
33 cu.m. w.gravel 830 /cu.m ₱27,390.00
16.5 cu.m. w.sand 650 /cu.m. ₱10,725.00

II-Steel Works
a. Footing And Column
177 pcs. 16mmø x 6m 315 /pc ₱55,755.00
50 pcs. 10mmø x 6m 124 /pc ₱6,200.00
30 kl. 32kgs.#16g.i.tie wire 50 /kl. ₱1,500.00

b. Roof Beam,Tie B tie beam & cantilever


160 pcs. 16mmø x 6m 315 /pc ₱50,400.00
110 pcs. 10mmø x 6m 124 /pc ₱13,640.00
6 kl. #16g.i.tie wire 50 /kl. ₱300.00

c. Roofing
134 0.4mm THK long span roof 245 ₱32,830.00
2 pcs. G.I. Fascia Flashing(sides) 205 ₱410.00
8 pcs. G.I. Corner Flashing 205 ₱1,640.00
84 pcs. 1.3 thk. X 2" X 6" C-Purlins 728 ₱61,152.00
48 pcs. 1/4"thk.X1 1/2"X1 1/2" 450 ₱21,600.00
67 pcs. 1/4"thk.X2"X2" 800 ₱53,600.00

d.slab
1000 pcs. 10mmø x 6m 124 /pc ₱124,000.00
2 kl. #16g.i.tie wire 50 /kl. ₱100.00
III-Masonry Works
6218 pcs. 4"CHB 13 /pc ₱80,834.00
21 bag/s cement 245 /bag ₱5,145.00
2 cu.m. w.sand 650 /cu.m. ₱1,300.00

IV-Painting Works
9 pail concrete primer 2128 /pc ₱19,152.00
9 pail semi gloss latex paint 2500 /pc ₱22,500.00

VI-Carpentry Works
92 pcs 1/4" X 4' x 8' mar.plywood 360 /pc. ₱33,120.00
7673 bd.ft 2" x 2" x 14` 20 bd,ft ₱153,460.00
₱987,123.00
LABOR COST: 35% ₱345,493.05

VII-Doors and Windows Lumpsum


(labor and materials) ₱27,000.00

TOTAL PROJECT COST: ₱2,346,739.05