STATUS OF PROJECTS UNDER PMU-SONAMARG
CIVIL WORKS
1. Zojila Tunnel
Implementing Agency:-NHIDCL.
Name of Contractor: IL&FS Transportation Networks Limited (ITNL) (Terminated)
Date of Termination: - Contract terminated on 15.01.2019.
Contract Agreement with M/s IL&FS Transportation Networks Limited amounting to Rs
4899.42 crore was signed on 24.01.2018.
The Appointed Date (Date of commencement) was notified as 19.05.2018.
The contractor ITNL stopped the work since 15.09.2018 due to financial problems.
Fresh bid was invited with bid due date 08.08.2019. The bidding process for the
subject project was annulled due to administrative reasons.
As per further directions of MoRTH , Draft CCEA Note has been submitted on
08.11.2019 for approval.
MEIL Stood as L1 bidder for Zojila Tunnel.
2. Z-Morh Tunnel (DBFOT) PPP Model
Sl. No. Z-Morh tunnel (Status)
1 Mode of Implementation BOT (Annuity) on DBFOT pattern
2 Length (in Km) 6.50
3 Approach road Length (West Portal =4.636, Eastern Portal=0.93, V.T
Approach Road=0.87)
4 Type of Tunnel 2-lane bi-directional tunnel with parallel escape
tunnel
5 Cut & Cover Tunnel 42 m (Western portal) & 31 m (Eastern portal)
7 Total Project cost Rs 2378.76 Crore
8 Concession period Construction Period 3.5 Years & DLP Period 15 Years
9 Date of award 19.12.2020
10 Date of Signing of 17.01.2020
Concession Agreement
11 Appointed Date Yet to be given
12 Construction Completion 3.5 Years from Appointed Date
Date
13 Semi Annual Annuity Rs 296.10 Crore
14 Physical progress 38.9% (as per the I.E MPR August 2018)
15 Financial Progress 39.3% (as per the I.E MPR August 2018)
16 Availability of Land 100%
17 Name of the EPC Contractor APCO Sri Amarnathji Tunnelway Private Limited
DPR WORKS
1. (i) Construction of Approach Roads with Avalanche Protection Works to West and
East portal of the proposed Zojila Tunnel.
(ii) For making the NH-1 from Z-Morh Tunnel to proposed Zojila Tunnel (approx. 20
km) all weather road.
DPR work is in progress by the consultant M/s. SMEC International Pty. Ltd.
Draft Detailed Project Report has been submitted by the consultant.
2. 2-lane with Paved Shoulder of NH configuration for Baramulla-Gulmarg Road
DPR work is in progress by the consultant M/s Rodic.
Feasibility Report has been submitted by the consultant.
3. 2-lane with Paved Shoulder of NH configuration for Donipawa-Ashajipora Road
DPR work is in progress by the consultant M/s Rodic.
Final DPR has been submitted by the consultant.
Sl. No. Z-Morh tunnel (Status)
1 Mode of Implementation BOT (Annuity) on DBFOT pattern
2 Length (in Km) 6.50
3 Approach road Length West Portal =4.636 Km
Eastern Portal=0.93 Km
V.T Approach Road=0.87 Km
4 Type of Tunnel 2-lane bi-directional tunnel with parallel escape
tunnel
5 Major Bridges 02 Nos ( 110m & 240m )
6 Minor Bridges 01 No (30m)
7 Total Project cost Rs 2378.76 Crore
8 Concession period Construction Period 3.5 Years & DLP Period 15 Years
9 Date of award 19.12.2020
10 Date of Signing of 17.01.2020
Concession Agreement
12 Construction Completion 3.5 Years from Appointed Date
Date
13 Semi Annual Annuity Rs 296.10 Crore
14 Name of the EPC Contractor APCO Sri Amarnathji Tunnelway Private Limited
Sl. No. Z-Morh tunnel (Status)
1 Mode of Implementation BOT (Annuity) on DBFOT pattern
2 Length (in Km) 6.50
3 Approach road Length (West Portal =4.636, Eastern Portal=0.93, V.T
Approach Road=0.87)
4 Type of Tunnel 2-lane bi-directional tunnel with parallel escape
tunnel
5 Cut & Cover Tunnel 42 m (Western portal) & 31 m (Eastern portal)
7 Total Project cost Rs 2378.76 Crore
8 Concession period Construction Period 3.5 Years & DLP Period 15 Years
9 Date of award 19.12.2020
10 Date of Signing of 17.01.2020
Concession Agreement
11 Appointed Date Yet to be given
12 Construction Completion 3.5 Years from Appointed Date
Date
13 Semi Annual Annuity Rs 296.10 Crore
14 Physical progress 38.9% (as per the I.E MPR August 2018)
15 Financial Progress 39.3% (as per the I.E MPR August 2018)
16 Availability of Land 100%
17 Name of the EPC Contractor APCO Sri Amarnathji Tunnelway Private Limited