RISK IN Fidic
RISK IN Fidic
Submitted To:
Dr. Hadikusumo
Submitted By:
Table of Contents
1.0 Introduction:
FIDIC (‘Fédération Internationale des Ingénieurs – Conseils) is an international
organization developed the brief and practical contract types for the international projects. FIDIC
Red book refers to the general conditions of contract for construction. In order to change/modify
any of the condition in the general conditions of FIDIC based of the specific conditions of the
project, we need to document that in the supplementary conditions of the contract.
In the following part of this report, we have tried to analyze the project risks based on
various perspective such as time, cost, owner, contractor as documented in the general conditions
of the contract of FIDIC RED BOOK (1999 Edition) etc. The analysis is in form of Questions as
stated below.
1
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
2
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
3
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
4
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
5
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Cost
S.No. CLAUSE No. CLAUSE RISK MANAGEMENT
1 1.1 Definitions
Few terms related with cost for example, tendering, bill
of quantities, variation, money and payment should be
taken into consideration.
6
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Cost
S.No. CLAUSE No. CLAUSE RISK MANAGEMENT
Employer's Use of
3 1.1O Contractor's The contractor should give the employer a non-
Documents terminable transferable non-exclusive royalty-free
license to copy, use and communicate the
7
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Cost
S.No. CLAUSE No. CLAUSE RISK MANAGEMENT
Assignment of
12 4.5 benefits of Once the benefit gets transferred to owner, then
subcontract responsibility directly goes to owner for material
supply equipment operation.
Rights of way and Contractor should find additional ways to access to the
15 4.13
facilities site and use the other areas not provided and specified
by owner.
When fossils, coins, antiquity or archeological artifacts
are found, the owner, on report by the contractor, acts
16 4.24 Fossils immediately to avoid delay.
8
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Cost
S.No. CLAUSE No. CLAUSE RISK MANAGEMENT
To ensure quality work, the owner’s staff shall at all
reasonable times have full access to the site for which
the Project is going on. The contractor shall give the
owner’s personnel full opportunity to carry out their
17 7.3 Inspection
assigned duties without hindrance.
9
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Cost
S.No. CLAUSE No. CLAUSE RISK MANAGEMENT
Engineer's Duties and The engineer has the right to issue variations which
4 3.1
Authority may include omissions i.e. Cancellation of the works.
10
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Sufficiency of the The contactor must fulfil all the requirements so that
11 4.11 accepted contract the correctness and the sufficiency of the accepted
amount contract amount can be easily met.
11
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
12
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
13
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
The Following table shows the risks borne by the owner according to FIDIC and
suggestions to manage these risks.
14
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
15
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
16
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
17
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
The Following table shows the risks borne by the contractor according to FIDIC and suggestions
to manage these risks.
18
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
20
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Performance
security is
required by owner
15 4.2 Performance security Risk of claim as a risk control to
ensure contractor
will perform the
contract.
The contractor is
required to obtain
Risk of termination by prior consent of
16 4.4 Subcontractor
employer the engineer to
subcontract parts
of the works.
The Contractor
must identify the
17 4.6 Cooperation Risk of price variation
price of
cooperation.
The contractor
needs to make
safety manual and
Risk of obtaining taking over
18 4.8 Safety procedures project safety plan
certificate
that comply with
govt. safety
regulation.
The contractor
should provide all
the data’s required
while executing
19 4.1O Site data Risk of claim
site works, also
mention site
conditions
,geography etc.
21
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
22
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
23
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
24
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Investigation
The Engineer may also notify productive in
the cause foe the suspension. project.
If and to the extent that the Revise scheduling
33 8.8 Suspension of Work
cause is notified and is the of project.
responsibility of the Make details
Contractor planning of critical
works.
The Contractor shall not be Investigation
entitled to an extension of productive in
time for, or to payment of project.
the Cost incurred in, making Revise scheduling
good the consequences of of project.
Consequences of the Contractor’s faulty
34 8.9
Suspension design, workmanship or
materials or of the Make details
Contractor’s failure to planning of critical
protect, store or secure in works.
accordance with Sub-Clause
8.8 [Suspension of Work]
Investigation
productive in
project.
Payment for Plant and The Contractor shall be
Revise scheduling
35 8.10 Materials in Event of entitled to payment of the
of project.
Suspension value
Make details
planning of critical
works.
Investigation
The suspension under sub- productive in
clause 8.8, the Contractor can project.
request the Engineer’s Revise scheduling
36 8.11 Prolonged Suspension
permission to proceed if the of project.
suspension has continued for Make details
more than 84 days. planning of critical
works.
26
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Contractor must
prepare the
If contractor cannot receive taking-over
the final payment certification procedure, Or if
because of his lack, taking- contractor find
Application for Final
41 14.11 over date will be delayed. And serious
Payment Certificate in the worst case, the deterioration, as
contractor cannot receive the soon as possible
performance security. they have to treat
it before taking
over.
Using bank
If the exchange rate
consulting,
negatively changes, actual
42 14.15 Currencies of Payment appropriate
payment become smaller than
insurance should
contract price
be applied.
The contractor
should understand
the clause's
particular
conditions of
In the stated particular
termination. And
conditions, contractor has the
43 15.2 Termination by Employer they must avoid
probability of termination of
causing these
the contract.
conditions. Good
communication
will help to get the
support of
engineer.
The practice of
Before the TOC, contractor proper project
has the responsibility of the management
44 17.1 Indemnities property. And they also have (safety
the responsibility of the management,
damage of staffs. construction
management and
28
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
The practice of
proper project
management
From the project's (safety
commencement to TOC, management,
Contractor's Care of the contractor has the construction
45 17.2
Works responsibility of the management and
damage/loss of works and so on) will prevent
goods. the property
damage and
human resource
damage.
Insurance has the exclusion
By using particular
statement. If the causing loss
condition, how to
Insurance for Works and or damage is classified
46 18.2 indemnify should
Contractor's Equipment exclusion, contractor has to
be decided in the
discuss with owner who
contract.
should indemnify.
If the foretaste is
Applying force majeure to found, contractor
Force Majeure Affecting subcontractor, constructor should make the
47 19.5
Subcontractor must take the responsibility of decision how to
the damage/loss. treat the issue as
soon as possible.
At first, contractor
should mitigate
the predictable
risk in the
contract. And after
If dispute is judged by
contracting,
arbitration, contractor must
48 20.6 Arbitration contractor should
receive any result. And it
monitor the
becomes the final result.
project risk. And
once problems
and risks causing,
contractor should
make decision
29
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
This portion of the document elaborates the clauses of FIDIC that can favor the
contractor to put claim, or to suspend or terminate the contract because of the action or lack of
action of the employer. The employer is in sensitive condition in these clauses and he needs to
consider these carefully. The clauses are:
30
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
31
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Payment for
The Contractor shall be entitled to
Plant and
Claim for extension of time and payment of the value (as at the date of
9 8.10 Materials in
additional payment suspension) of Plant and/or Materials
Event of which have not been delivered to site.
Suspension
The employer should be much careful in
There is a possibility that, after taking using the partially completed facility as
Taking Over of over, the contractor may bear extra cost this might pose a claim against him. If no
10 10.2 Parts of the in completing the works due to the other option, then taking over should be
Works partial use of the facility by the much specified and employer need to be
employer. careful that it might not interfere with
the on-going contractor works.
32
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
The change in the government rules and To avoid such claims, the employer
regulation can affect the contractor should mention a range in the particular
Adjustments
directly (change in construction laws) or conditions for keeping him flexible of
15 13.7 for Changes in
indirectly (material price change). Such price escalations. If the escalations go
Legislation changes will affect the cash flow n beyond that, he should compensate the
performance of the contractor. contractor for the increased risk.
33
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
If owner/owner's personnel/engineer
General
don't follow insurance policy and cause Owner side should understand and keep
22 18.1 Requirements
damage/loss, contractor can claim the insurance policy.
for Insurances owner to indemnify them.
34
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
This portion of the document elaborates the clauses of FIDIC that can favor the employer
to put claim against the contractor (multiple reasons), or to suspend or terminate the contract
because of the non-performance of the contractor. The contractor is in sensitive condition in
these clauses and he needs to consider these carefully. The clauses are:
35
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
37
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
39
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
40
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
10 12.4 Omissions
7.0 Conclusion:
This report has been developed by a profound study of the FIDIC general conditions of
contract (1999 Edition). By study of the document we go to know that, FIDIC unequivocally
elaborates the project risks considering multiple practical scenarios and assumptions. One
interesting thing worth mentioning here is that though the contract conditions clearly highlight
project risks with respect to the employer and the contractor perspectives. But the clauses that
pose the risk on the contractor are much more than those of the contractor. So, Contractor needs
to much careful while working in the FIDIC Arrangement.
41
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Appendix I
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
1 GENERAL PROVISION
1 1 Definitions
1 2 Interpretation
1 3 Communications
1 4 Law and Language
1 5 Priority if Documents
1 6 Contract Agreement
1 7 Assignment
Care and Supply of
1 8
Documents
Delayed Drawings or
1 9
Instructions
Employer's Use of
1 10 Contractor's
Documents
Contractor's Use of
1 11
Employer's Documents
1 12 Confidential Details
1 13 Compliance with Laws
Joint and Several
1 14
Liability
2 THE EMPLOYER
Right of Access to the
2 1
Site
Permits, Licences or
2 2
Approvals
2 3 Employer's Personnel
Employer's Financial
2 4
Arrangements
2 5 Employer's Claims
42
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
3 THE ENGINEER
Engineer's Duties and
3 1
Authority
Delegation by the
3 2
Engineer
Instructions of the
3 3
Engineer
Replacement of the
3 4
Engineer
3 5 Deteminations
4 THE CONTRACTOR
Contractor's General
4 1
Obligations
4 2 Performance Security
Contractor's
4 3
Representative
4 4 Subcontractors
Assignment of Benefit
4 5
of Subcontract
4 6 Co-operation
4 7 Setting Out
4 8 Safety Procedures
4 9 Quality Assurance
4 10 Site Data
Sufficiency of the
4 11 Accepted Contract
Amount
Unforeseeable Physical
4 12
Conditions
Rights of Way and
4 13
Facilities
Avoidance of
4 14
Interference
43
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
4 15 Access Route
4 16 Transport of Goods
Contractor's
4 17
Equipment
Protection of the
4 18
Environment
Electricity, Water and
4 19
Gas
Employer's Equipment
4 20 and Free-Issue
Material
4 21 Progress Reports
4 22 Security of the site
Contractor's
4 23
Operations on Site
4 24 Fossils
NOMINATED
5
SUBCONTRACTORS
Definition of
5 1 "nominated
Subcontractor"
Objection to
5 2
Nomination
Payments to
5 3 nominated
Subcontractors
5 4 Evidence of Payments
6 STAFF AND LABOUR
Engagement of Staff
6 1
and Labour
Rates of Wages and
6 2
Conditions of Labour
Persons in the Service
6 3
of Employer
44
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
6 4 Labour Laws
6 5 Working Hours
Facilities for Staff and
6 6
Labour
6 7 Health and Safety
Contractor's
6 8
Superintendence
6 9 Contractor's Personnel
Records of Contractor's
6 10 Personnel and
Equipment
6 11 Disorderly Conduct
PLANT, MATERIALS
7
AND WORKMANSHIP
7 1 Manner of Execution
7 2 Samples
7 3 Inspection
7 4 Testing
7 5 Rejection
7 6 Remedial Work
Ownership of Plant and
7 7
Materials
7 8 Royalties
COMMENCEMENT,
8 DELAYS AND
SUSPENSION
Commencement of
8 1
Work
8 2 Time for Completion
8 3 Programme
Extension of Time for
8 4
Completion
8 5 Delays Caused by
45
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
Authorities
8 6 Rate of Progress
8 7 Delay Damages
8 8 Suspension of Work
Consequences of
8 9
Suspension
Payment for Plant and
8 10 Materials in Event of
Suspension
8 11 Prolonged Suspension
8 12 Resumption of Work
TESTS ON
9
COMPLETION
Contractor's
9 1
Obligations
9 2 Delayed Tests
9 3 Retesting
Failure to Pass Tests on
9 4
Completion
EMPLOYER'S TAKING
10
OVER
Taking Over of the
10 1
Works and Sections
Taking Over of Parts of
10 2
the Works
Interference with Tests
10 3
on Completion
Surfaces Requiring
10 4
Reinstatement
11 DEFECTS LIABILITY
Completion of
11 1 Outstanding Work and
Remedying Defects
46
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
Cost of Remedying
11 2
Defects
Extension of Defects
11 3
Notification Period
Failure to Remedy
11 4
Defects
Removal of Defective
11 5
Work
11 6 Further Tests
11 7 Right to Access
11 8 Contractor to Search
Performance
11 9
Certificate
11 10 Unfulfilled Obligations
11 11 Clearance of Site
MEASUREMENT AND
12
EVALUATION
12 1 Works to be Measured
Method of
12 2
Measurement
12 3 Evaluation
12 4 Omissions
VARIATIONS AND
13
ADJUSTMENTS
13 1 Right to Vary
13 2 Value Engineering
13 3 Variation Procedure
Payment in Applicable
13 4
Currencies
13 5 Provisional Sums
13 6 Daywork
Adjustments for
13 7
Changes in Legislation
47
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
Adjustments for
13 8
Changes in Cost
CONTRACT PRICE AND
14
PAYMENT
14 1 The Contract Price
14 2 Advance Payment
Application for Interim
14 3
Payment Certificates
14 4 Schedule of Payment
Plant and Materials
14 5
intended for the Works
Issue of Interim
14 6
Payment Certificates
14 7 Payment
14 8 Delayed Payment
Payment of Retention
14 9
Money
Statement at
14 10
Completion
Application for Final
14 11
Certificate
14 12 Discharge
Issue of Final Payment
14 13
Certificate
Cessation of
14 14
Employer's Liability
14 15 Currencies of Payment
TERMINATION BY
15
EMPLOYER
15 1 Notice to Correct
Termination by
15 2
Employer
Valuation at Date of
15 3
Termination
48
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
Payment after
15 4
Termination
Employer's Entitlement
15 5
to Termination
SUSPENSION AND
16 TERMINATION BY
CONTRACTOR
Contractor's
16 1 Entitlement to Suspend
Work
Termination by
16 2
Contractor
Cessation of Work and
Removal of
16 3
Contractor's
Equipment
Payment on
16 4
Termination
RISK AND
17
RESPONSIBILITY
17 1 Indemnities
Contractor's Care of
17 2
the Works
17 3 Employer's Risks
Consequences of
17 4
Employer's Risks
Intellectual and
17 5 Industrial Property
Rights
17 6 Limitation of Liability
18 INSURANCE
General Requirements
18 1
for Insurances
18 2 Insurance for Works
49
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
and Contractor's
Equipment
Insurance against
18 3 Injury to Persons and
Damage to Property
Insurance for
18 4
Contractor's Personnel
19 FORCE MAJEURE
Defenition of Force
19 1
Majeure
Notice of Force
19 2
Majeure
19 3 Duty to Minimise Delay
Consequences of Force
19 4
Majeure
Force Majeure
19 5 Affecting
Subcontractor
Optional Termination,
19 6
Payment and Release
Release from
19 7 Performance under the
Law
CLAIMS, DISPUTES AND
20
ARBITATION
20 1 Contractor's Claims
Appointment of the
20 2 Dispute Adjudication
Board
Failure to Agree
20 3 Dispute Adjudication
Board
Obtaining Dispute
20 4
Adjudication Board's
50
ANALYSIS OF THE FIDIC CONDITIONS OF CONTRACT (RED BOOK) 1999 EDITION
Claim, Suspension&
Project Risks Management Project Risks
Termination
EOT/Additional
No Title
Payment
Time Cost Quality Safety Owner Contractor Contractor Owner
Decision
20 5 Amicable Settlement
20 6 Arbitation
Failure to Comply with
20 7 Dispute Adjudication
Board's Decision
Expiry of Dispute
20 8 Adjudication Board's
Appointment
51