PANCHI INDUSTRIAL SERVICES 133/1 NH-24 BYE PASS VIJAY NAGAR ,GHAZIABAD -201009
date 21/10/15                     PIS Job No. - PIS/FM/UV-14-15
W.O.No.                           JOB:IBR /NON IBR PIPING & ERECTION WORK
A. Man Power Deployment :
                 Supervisory/ Administrative Personel                                                                       Workman
Sl.        Category                                          No   Sl.                                                  Category
E1         Site In Charge                                         W1      Electrician
E2                QC Engineer / Superviser                                       W2          IBR Welder
E3                Safety Engineer / Superviser                                 1 W3          SR / RT Technician
E4                Field Engineer / Superviser                                  1 W4          Pipe fitter / Str. fitter
E5                Material Superviser                                            W5          Str. Welder / Gas Cutter / Grinder
E6                Time Keeper / clarke                                           W6          Serang / Rigger
                  Crane & Hydra operator                                         W7          Khalasie / Helper
B. Erection & Alignment Progress
                                                                          Pre-assembly                                  Erection
                                                                    This month                                       This month
                                                         Up to Last til                                   Up to Last til
     Sr.No.       Description     UOM          Scope     Month      yesterday Cumulitive                  Month      yesterday
        1
       2
       3
       4
       5
       6
       7
Sr.No.                                              Description                                           Qty          Wt "MT"
              1 oil faired boiler ducting fabrication complite ,erection will done Friday 1st half                 1
              2 feed pump frame fabrication complite
              3                     mdc assembly complite, redy for erection
              4              15 no insert plate fixing 500x200x3 mm,for cabel tray
         5                                         chimeny aligment
         6
         7
D. Plan for the day             Date:23/8/15
Sr.No.                                                                      Description
         1                                             safety valve exsisting pipeing fabrication & erection
              2                                                 vent pipeing fabrication & erect
                                                                           mdc erection
                                                                oil faired boiler ducting erection
                                                                      economiser aligment
For PSI
PRADEEP KUMAR MISHRA
               DAILY SITE REPORT
        Workman
   Category                               Day         Night
                                                 2
er / Grinder                                     4
                                                 1
                                                 2
   Erection                      Welding & Alignment
                                     This month
                          Up to Last til
               Cumulitive Month      yesterday Cumulitive
               Total "MT"                Remarks
                  today mostly erection complite but I have safety issu
                            this is exta work not our scope
                                       exta work
                                 this week plan plan
                            economiser to bag filter ducting
                               bag filter to id fan ducting
                               dearetor tank platfarm &
                                 asseries & mounting
                           than dioil tank aligment & piping
                                fabrication & erection
For ,FM,UV