Panchi Industrial Services 133/1 Nh-24 Bye Pass Vijay Nagar, Ghaziabad - 201009

This document provides a daily site report from PIS Job No. PIS/FM/UV-14-15. It includes: 1. A manpower deployment table listing supervisory, administrative, and workman categories and numbers deployed. 2. A table on erection and alignment progress including description, units of measurement, scope, and progress to date. 3. A list of tasks completed that day including oil boiler ducting fabrication, feed pump frame fabrication, and MDC assembly. 4. The plan for the following day including safety valve pipe fabrication and erection, vent piping fabrication and erection, MDC erection, and oil boiler ducting erection.

Uploaded by

Guddu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
130 views4 pages

Panchi Industrial Services 133/1 Nh-24 Bye Pass Vijay Nagar, Ghaziabad - 201009

This document provides a daily site report from PIS Job No. PIS/FM/UV-14-15. It includes: 1. A manpower deployment table listing supervisory, administrative, and workman categories and numbers deployed. 2. A table on erection and alignment progress including description, units of measurement, scope, and progress to date. 3. A list of tasks completed that day including oil boiler ducting fabrication, feed pump frame fabrication, and MDC assembly. 4. The plan for the following day including safety valve pipe fabrication and erection, vent piping fabrication and erection, MDC erection, and oil boiler ducting erection.

Uploaded by

Guddu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PANCHI INDUSTRIAL SERVICES 133/1 NH-24 BYE PASS VIJAY NAGAR ,GHAZIABAD -201009

date 21/10/15 PIS Job No. - PIS/FM/UV-14-15


W.O.No. JOB:IBR /NON IBR PIPING & ERECTION WORK
A. Man Power Deployment :
Supervisory/ Administrative Personel Workman
Sl. Category No Sl. Category
E1 Site In Charge W1 Electrician
E2 QC Engineer / Superviser W2 IBR Welder
E3 Safety Engineer / Superviser 1 W3 SR / RT Technician
E4 Field Engineer / Superviser 1 W4 Pipe fitter / Str. fitter
E5 Material Superviser W5 Str. Welder / Gas Cutter / Grinder
E6 Time Keeper / clarke W6 Serang / Rigger
Crane & Hydra operator W7 Khalasie / Helper

B. Erection & Alignment Progress


Pre-assembly Erection
This month This month
Up to Last til Up to Last til
Sr.No. Description UOM Scope Month yesterday Cumulitive Month yesterday
1
2
3
4
5
6
7

Sr.No. Description Qty Wt "MT"


1 oil faired boiler ducting fabrication complite ,erection will done Friday 1st half 1
2 feed pump frame fabrication complite
3 mdc assembly complite, redy for erection
4 15 no insert plate fixing 500x200x3 mm,for cabel tray
5 chimeny aligment
6
7
D. Plan for the day Date:23/8/15
Sr.No. Description
1 safety valve exsisting pipeing fabrication & erection
2 vent pipeing fabrication & erect
mdc erection
oil faired boiler ducting erection
economiser aligment
For PSI
PRADEEP KUMAR MISHRA
DAILY SITE REPORT

Workman
Category Day Night

2
er / Grinder 4
1
2

Erection Welding & Alignment


This month
Up to Last til
Cumulitive Month yesterday Cumulitive

Total "MT" Remarks


today mostly erection complite but I have safety issu
this is exta work not our scope

exta work

this week plan plan


economiser to bag filter ducting
bag filter to id fan ducting
dearetor tank platfarm &
asseries & mounting
than dioil tank aligment & piping
fabrication & erection
For ,FM,UV