SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2012)                                     Rev 6              31-Mar-12
SAIC NUMBER              DATE APPROVED         QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Pipeline Inspection Prior to Welding of Temperature
                                                                                              SAIC-L-2115              30-Apr-13               PIPING-
Tie-In Weld Joint
PROJECT TITLE                                                                               WBS / BI / JO NUMBER       CONTRACTOR / SUBCONTRACTOR
MASTER GAS SYSTEM(MGS) PHASE 1                                                              10-01282                   BR.CAT INTERNATIONAL
EQUIPMENT ID NUMBER(S)                                      EQUIPMENT DESCRIPTION                                  EQPT CODE          SYSTEM ID.       PLANT NO.
                           N/A                                                      N/A                                  N/A                           K94
LAYOUT DRAWING NUMBER                                       REV. NO.            PURCHASE ORDER NUMBER                                 EC / PMCC / MCC NO.
VA-157489-                                                  0                                         N/A
SCHEDULED INSPECTION DATE & TIME                            ACTUAL INSPECTION DATE & TIME                           QUANTITY INSP.     MH's SPENT        TRAVEL TIME
                                                                                                                           SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER                                                   SAUDI ARAMCO ACTIVITY NUMBER                                         WORK PERMIT REQUIRED?
SATIP-L-450-04                                                            3.8
SAUDI ARAMCO INSPECTION LEVEL
W
                                                                          CONTRACTOR INSPECTION LEVEL
                                                                          H
                                                                                                                                                        YES
ITEM
                                    ACCEPTANCE CRITERIA                                       REFERENCE             PASS       FAIL          N/A       RE-INSP DATE
 No.
         A temperature tie-in weld is a weld that connects
         one of the following:
         1) Two pipeline strings together.
                                                                                            SAES-L-450
 Def:    2) An existing pipeline to a pipeline under construction.
                                                                                               Para. 15.1
         3) A pipeline to an anchor.
         4) Pipeline sections to an intermediate mainline valve
            that is being inserted.
    A    General Requirements
         One of the following provisions must be in place prior to welding of
         temperature tie-in joint:
         1) Anchor is installed on the end of pipeline upstream of the welding
         progression, along with friction forces on the tail.
                                                                                            SAES-L-450
  A1                                               2) At least 450 m of buried
                                                                                               Para. 15.1
         pipeline downstream of the tie-in weld.        3) 900 m to 1200 m of
         pipeline string resting on wooden skids or sand.
         4) 1800 m to 2400 m of pipeline string resting on steel supports.
         The first string of a buried pipeline is placed in the trench and spot             SAES-L-450
  A2
         backfilled (or tied into an anchor), during the hottest part of the day.             Para. 15.5.1
                                                                                            SAES-L-450
  A3     Subsequent strings are connected by temperature tie-in welds.
                                                                                              Para. 15.5.1
         All welding requirements and preparations conform with SATIP-W-012,
  A4                                                                                           Quality Plan
         and inspection conforms with SAIC-W-2006.
         Welding shall not be done when surfaces are wet or damp or exposed to SAES-W-012
  A5
         rain or when the welders are exposed to inclement conditions.           Para. 10.2.2
         Wind shields or tents are in place if the wind is strong enough to affect
                                                                                            SAES-W-012
  A6     arc stability or shielding gas coverage, or when deemed necessary by
                                                                                               Para. 10.2.1
         Saudi Aramco Inspection.
         Welding surface is clean and free from oil, moisture, rust, scale, sand,
                                                                                            SAES-W-012
  A7     paint, metallic coatings or other foreign matter, at least 25 mm from the
                                                                                               Para. 10.3.1
         area of interest prior to welding.
         Protective sleeves are wrapped snugly around the coated ends of the                SAES-H-200
  A8
         pipes adjacent to the girth weld area.                                                Para 6.2.1
         When external clamps are used on pipe > 16" dia., the root bead is 50%             SAES-W-012
  A9
         complete prior to removal of the external clamp.                                      Para. 10.4.2
         At least two welders are used for pipelines greater than 16 inch diameter, SAES-W-012
 A10
         operating simultaneously and in opposite quadrants.                           Para. 10.7.1
                                                                                Page 1 of 4
      Working clearance for welding is not less than 900 mm all around the   SAES-W-012
A11
      pipe.                                                                     Para. 10.8
                                                                 Page 2 of 4
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2012)                               Rev 6            31-Mar-12
                                                                                      SAIC NUMBER             DATE APPROVED        QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Pipeline Inspection Prior to Welding of Temperature
                                                                                         SAIC-L-2115            30-Apr-13              PIPING-
Tie-In Weld Joint
PROJECT TITLE                                                                         WBS / BI / JO NUMBER      CONTRACTOR / SUBCONTRACTOR
MASTER GAS SYSTEM(MGS) PHASE 1                                                        10-01282                  BR.CAT INTERNATIONAL
ITEM
                                    ACCEPTANCE CRITERIA                                  REFERENCE            PASS     FAIL          N/A       RE-INSP DATE
 No.
         The Construction Engineer has determine the highest practical tie-in
         temperature for each tie-in weld.
         *NOTE: The tie-in temperature shall be within the range stated in the
                                                                                      SAES-L-450
 A12     Project Specifications.
                                                                                         Para. 15.2
         **NOTE: Indicate the following:
           a. Project specified Tie-In Temperature Range: __________
           b. Highest practical Tie-In Temp: __________
         The measured tie-in temperature is within the project specified tie-in
         temperature range. ( Tie-In Temp=____________)
          *NOTES:a) Contact measuring device shall be shielded from direct            SAES-L-450
 A13
         sunlight to prevent an inaccurate reading.                                      Para. 15.3
         b) Actual tie-in temperature is the average of two readings, one at the
         top and one at the bottom of the pipe.
         The actual tie-in temperature and the pipeline stations of the tie-ins are   SAES-L-450
 A14
         recorded in the inspection record books.                                        Para. 15.4
         The hot pass is made while the pipe is still fully supported by the          SAES-W-012
 A15
         sideboom tractor or supports.                                                   Para. 10.7.3
                                                                                      SAES-L-450
 A16     Temperature tie-in welds are kept free of movement to prevent cracks.
                                                                                        Para. 15.5.1
         During the night and the cool periods of the day, there should be at least
                                                                                      SAES-L-450
 A17     900 m to 1200 m of pipe outside the trench to keep the S-curve in
                                                                                        Para. 15.5.2
         sufficient tension to restrain the pipe already in the trench.
   B     Aboveground Non-restrained Pipelines:
         A string is always connected to each side of the anchor stub when the        SAES-L-450
  B1
         work is stopped at the end of the day.                                          Para. 15.8
   C     Buried Pipelines:
         When a sufficient number of strings have been completed, the first string
                                                                                    SAES-L-450
  C1     of a buried pipeline shall be placed in the trench and spot backfilled (or
                                                                                      Para. 15.5.1
         tied into an anchor) during the hottest part of the day.
                                                                                      SAES-L-450
  C2     The subsequent strings shall be connected by temperature tie-in welds.
                                                                                        Para. 15.5.1
          Each new string must be kept free of movement to prevent cracks in the SAES-L-450
  C3
         tie-in weld.                                                              Para. 15.5.1
         The portion of the pipeline outside the trench shall be supported by side    SAES-L-450
  C4
         booms holding the line in a gentle S-curve.                                    Para. 15.5.2
         Spot backfilling (used to anchor to the line) may be completed at any        SAES-L-450
  C5
         temperature but no closer than 1200 m from the free end of the tail.           Para. 15.5.4
          If spot backfilling closer to the free end is required, it shall be done    SAES-L-450
  C6
         during the hottest part of the day.                                            Para. 15.5.4
                                                                           Page 3 of 4
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2012)                                                Rev 6            31-Mar-12
                                                                                                      SAIC NUMBER              DATE APPROVED        QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Pipeline Inspection Prior to Welding of Temperature
                                                                                                         SAIC-L-2115              30-Apr-13             PIPING-
Tie-In Weld Joint
PROJECT TITLE                                                                                         WBS / BI / JO NUMBER        CONTRACTOR / SUBCONTRACTOR
MASTER GAS SYSTEM(MGS) PHASE 1                                                                        10-01282                    BR.CAT INTERNATIONAL
ITEM
                                         ACCEPTANCE CRITERIA                                             REFERENCE             PASS     FAIL          N/A       RE-INSP DATE
 No.
          If the tie-in weld is made with the pipe in the trench (at tie-in temperature)
          the string being tied in and the tail must be spot backfilled on the same
                                                                                         SAES-L-450
  C7      day of the tie-in.
                                                                                           Para. 15.5.5
            * NOTE: The spot backfilling shall not be closer than 24 meters from the
          free end.
   D      Aboveground Restrained Lines:
          When a sufficient number of strings have been completed, the starting
                                                                                        SAES-L-450
  D1      end of the pipeline is tied-in to a full thrust anchor or to a minimum of 600
                                                                                          Para. 15.6.1
          meters of buried pipeline using a temperature tie-in.
          The strings which have been tied-in while resting on the skids or on the
                                                                                                      SAES-L-450
  D2      sand, are placed onto the supports by side booms, holding the line in a
                                                                                                        Para. 15.6.2
          gentle S-curve between supports and skids.
          The pipeline that has been placed onto the supports has the top halves
                                                                                     SAES-L-450
  D3      of ring girder supports or support straps, bolted in place on the same day
                                                                                       Para. 15.6.2
          it is placed.
          There shall always be at least 900 m to 1200 m of pipe attached to the
                                                                                                      SAES-L-450
  D4      line on skids or on the ground, to restrain it during the night and cool
                                                                                                        Para. 15.6.3
          periods of the day.
          The pipeline strings may also be welded while resting on permanent
                                                                                        SAES-L-450
  D5      supports, but only if the supports are designed to resist the friction forces
                                                                                          Para. 15.6.4
          of the line developed under full temperature differential.
          Two strings on supports may be tied together with a temperature tie-in
          weld. This 1800 m to 2400 m double string may then be tied in to the
                                                                                                      SAES-L-450
  D6      pipeline at normal daily temperatures. However, the pipeline being tied
                                                                                                        Para. 15.6.5
          into must have an end anchor or be buried in order to obtain the highest
          possible effective tie-in temperature.
REFERENCE DOCUMENTS:
1. SAES-L-450, Construction of On-Land and Near Shore Pipelines, (31 Dec 2011)
2. SAES-W-012, Welding Requirements for Pipelines, (04 Oct 2009)
REMARKS:
                            Contractor / Third-Party                                                                         Saudi Aramco
Construction Representative*                                                             PMT Representative
                                       Work is Complete and Ready for Inspection:                                     T&I Witnessed   QC Record Reviewed        Work Verified
 Name, Initials and Date:                                                                 Name, Initials and Date:
                             M ARIF                                                                                  GEOVANNI
QC Inspector                                                                             PID Representative
                                Performed Inspection       Work / Rework May Proceed                                  T&I Witnessed   QC Record Reviewed        Work Verified
 Name, Initials and Date:                                                                 Name, Initials and Date:
                             E HASSAN/ ISMAIL / VIJAY                                                      IMRAN ANWAR
QC Supervisor                                                                            Proponent and Others
                              Quality Record Approved:                                                                T&I Witnessed   QC Record Reviewed        Work Verified
                                                                                           Name, Organization,
  Name, Sign and Date:
                                                                                            Initials and Date:
                             D.VARADHA RAJAN
 *Person Responsible for Completion of Quality Work / Test                                                                                           Y = YES    N = NO F = FAILED
                                                                                       Page 4 of 4