Leicester University Work Permit Guide
Leicester University Work Permit Guide
PERMIT TO WORK
PROCEDURE AND REQUIREMENTS
ESTATES & FACILITIES MANAGEMENT DIVISION
PREPARED BY:
MR STEPHEN REES
HEAD OF MAINTENANCE
ESTATES & FACILITIES MANAGEMENT DIVISION
UNIVERSITY OF LEICESTER
ON BEHALF OF:
MR P GOFFIN
DIRECTOR OF ESTATES
ESTATES & FACILITIES MANAGEMENT DIVISION
UNIVERSITY OF LEICESTER
Page 1
UNIVERSITY OF LEICESTER
ESTATES AND FACILITIES MANAGEMENT DIVISION
Permit to Work
1.0 Introduction
Permits themselves do not make a job free from risks, they rely upon effective
control and co-ordination in order that hazards are identified and risks are
suitably assessed.
The Health and Safety Executive identify the following required elements for a
Permit-to-Work:
When maintenance staff need to carry out work that requires a permit, it will be
issued and signed by the relevant Trade Foreman, or Services Maintenance
Manager.
5.0 Contractors
When a contractor requires a permit they shall provide the relevant Estates
Project Manager or Engineer with a suitable and sufficient assessment of the risks
inherent with the work and a method statement for the works to be undertaken.
Page 3
This information should, whenever possible, be submitted at least 48hrs before
the start of the work and will allow the Competent Person sufficient time to
assess the work in detail. For work involving Service Maintenance contractors,
Method Statements shall be provided for specific tasks at the beginning of the
contract and if necessary Permits-to-Work issued as and when required.
The Competent Person should ensure that no other permits have been
issued that will have an impact on the one required.
All the copies of the permit should be signed by the relevant Competent
Persons, and if necessary the Contractors representatives to confirm that
contractors and staff understand the implications of the conditions listed
on the permit.
The precise time limits for which the permit is valid are to be indicated
and observed at all times.
When the work has been completed the Competent Person will inspect the site to
ensure that:
When the Competent Person is satisfied that these conditions have been met the
permit will be cancelled and copies filed with the contract documents (if
appropriate) and in the Permit file. These permits should be kept for 12 months.
High Voltage
The Permit-to-Work system for High Voltage applies to contractors and Estates
staff who may have need to enter any High Voltage substations. It DOES NOT
allow for switching of the H.V. circuits or for maintenance of the equipment, this
can only be carried out by authorised ABB Ltd. staff, or other contractors
appointed by the university.
The Competent Person must ensure that access to the substation will not in
any way affect the H.V. switchgear or controls.
The Competent Person must stay at the substation if access is required for
1 hour or less. For periods of more than 1 hour the Competent Person must
be available on the campus and be within immediate communication with
those in the substation.
Only those staff named on the Permit-to-Work will be allowed in the
substation.
The substation must not be left unlocked and unattended.
Page 5
Low Voltage
The Competent Person should issue a Permit-to-Work when any of the following
work is carried out on low voltage electrical installations:
Switching off any switch fuse, distribution board, or mains circuit board
that may affect the University‟s IT systems, the safety of any person, or
the electrical supply to fire alarm systems.
Work on remote and automatically controlled low voltage switchgear.
Hot Work is defined as work that involves temperatures that could give rise to
risks of fire and ignition of flammable substances and combustible materials, and
includes work where there is a naked flame or generation of sparks, smoke or
fumes.
All work must cease at least 1 hour before the end of the working day and
the permits are location specific.
Page 6
Where work lasts for more than one day i.e. re-roofing with a bitumen
boiler, the Competent Person signing on behalf of the Estates Department
may issue a permit covering 5 consecutive working days.
The Permit-to-Work shall not apply to hot work in the fitters workshop at
the Maintenance Centre.
Before the permit is signed, the Competent Person shall inspect the working area
for the following control measures:
Fire Control
The Competent Person shall ensure that the following general controls are in
place:
This Permit-to-Work is intended for Maintenance Staff and Contractors who have
a need to work on roofs at any University Academic or Residential Property,
Page 7
where a perimeter hand rail or edge protection is not provided or where the roof
of the building is considered as dangerous.
i) Details of PPE
ii) Other permits as necessary i.e. hot works etc.
iii) Permit signed by Competent Person
Attenborough Tower
Concrete Laboratory
i) Upper roofs have no edge protection or lanyard man safe systems. Do not
work within 2 metres of roof edge.
ii) Weather conditions to be assessed - no access allowed in bad weather, high
winds or rain.
All work within plantrooms, service ducts and risers shall be subject to a Permit-
to-Work.
Plantrooms etc are under the control of the Maintenance Section and any works
carried out by contractors either direct for the Maintenance Section or vie
Development will require a Permit-to-Work issued by an authorised person.
Page 9
Mr Bill Brookes: Electrical Service Maintenance Manager
Mr Steve Bishop: Mechanical Services Maintenance Manager
All work within the category 3 laboratory located in Medical Science Building shall
be subject to a Permit-to-Work.
Maintenance Staff
Before any work is carried out in the Category 3 suite, a Permit-to-Work should be
issued by the Containment Level 3 Suite Manager (C3SM) or appointed deputy.
Contractors
When contractors require a permit they shall provide the relevant Estates Project
Manager or Maintenance Services Manager with a suitable and sufficient
assessment of the risks inherent with the work and a method statement for the
works to be undertaken. This information should be submitted at least 72 hours
before works start to enable the Estates Project Manager / Maintenance Manager
to approve the details before C3SM issues the permit.
Other permits as necessary for the works to be undertaken shall be issued by the
authorised person in the E&FMD, i.e. hot works, roof permits etc.
C3 lab permits shall be issued for a maximum of 5 working days. If the works
extend beyond this number, additional permits will be required.
Page 10
No person working for the University, either staff directly employed or
contractors shall enter, or be instructed to enter a confined space for any
purpose:
a) Oil Tanks
Details of PPE.
Method statement of work to be carried out.
Monitoring of the atmosphere.
Observer outside with means of communication.
Rescue plan.
b) Water Tanks
Details of PPE.
Inlet/outlet valves locked-off.
Method statement of work to be carried out.
Observer outside with means of communication.
Rescue plan.
Details of PPE.
Method statement of work to be carried out.
Monitor atmosphere.
Observer outside with means of communication.
Rescue plan.
d) Manholes
Details of PPE.
Method statement of works to be carried out.
Observer outside with means of communication.
Rescue plan.
e) Boilers
Page 11
f) Lift Pits
g) Ventilation Ducts
Details of PPE.
Method statement of works to be carried out.
Observer outside with means of communication.
Ventilation plant to be electrically isolated.
Rescue plan.
The duration of the Permit-to-Work will be no longer than one working day.
Additional permits will need to be issued daily if work exceeds this time
period.
All work with asbestos materials shall be carried out in accordance with the
requirements of current legislation, in particular:
All work involved with the removal of asbestos materials will be undertaken by
licensed asbestos removal contractors, but some University Estates staff will
come into contact with products containing asbestos during their normal working
practices.
Page 12
3. University of Leicester policy is that all works involving asbestos will be
undertaken by licensed contractors. The Competent Person shall employ a
suitable contractor to undertake the works.
4. The contractor shall provide a detailed Safety Plan for the operations to
include:
Scope of work.
Programme of work.
Proposed method of removal.
Waste disposal.
PPE for operatives.
Air monitoring procedures.
Accident emergence procedures.
Probably duration of work.
Location of decontamination unit.
The Competent Person should inspect the works to ensure that the control
measures are in place and invite a Union, or Staff Representative to be present, if
considered to be necessary.
Completion of Work
Before the enclosures are dismantled the contractor must arrange for Assurance
Monitoring within the enclosure, undertaken by a University approved Laboratory.
Usually the order to the Laboratory will be raised by the University, with
responsibility for arranging the time and place for the test left with the
contractor to organise.
The laboratory must be satisfied that the asbestos fibre count does not exceed
limits (0.01 fibres/ml).
Page 13
Appendicies
Page 14
ESTATES & FACILITIES MANAGEMENT DIVISION
Fielding Johnson Building, University Road, Leicester LE1 7RH, UK
T +44 (0)116 252 2522 F +44(0)116 223 1333
The areas covered by this permit are accessed by a secure key issued by the Estates and Facilities
Management Division authorised personnel named below:
This permit ceases to be in operation when the works detailed are complete and any keys issued have
been returned to the above names personnel.
When entering any of the sections, the following procedures shall be observed:
1. Before entering:
a. Let someone know you are going into a switchroom and when you are likely to return.
b. If you are unsure about any aspect of the job, STOP and seek further advice.
2. As you enter:
3. While inside:
4. As you leave
a. Clean up
b. Lock up
c. Return permit and keys to EFMD
Permission is granted to the person(s) named below to enter high voltage sub-stations in the
location(s) indicated and for the purposes given:
Name: Company:
Location:
Description of Work
to be Undertaken:
Precautions to be taken:
SECTION B
Declaration: The dangers associated with working in or near to High Voltage
electrical systems have been explained to me and are fully
understood.
Name Signature
Company Date
SECTION C
To use:
At: Location:
SECTION B YES NO
Please tick as appropriate.
The above location has been examined………………………………………………………………
Are there combustible liquids, vapours, gases or dusts? ……………………………………
Suitable fire fighting equipment is available………………………………………………………
All combustible material has either been removed or suitably …………………………
protected against sparks.
Contractor aware of Fire Procedures (Section 16 – University of ………………………
Leicester Contractors General Code of Safe Practice)
Management arrangements to be implemented during and immediately after work:
SECTION C
Permit issued by: Signature:
Position: Date:
SECTION D
The work area and any adjacent areas where sparks or heat might have spread have been inspected on
completion of the work. An additional safety check of the area has been carried out at least one hour after
the work was finished.
Notes
a) This Permit is applicable to all operations involving the application of flame, welding, burning,
brazing, and cutting equipment; bitumen or other mastic heaters and any other heat producing
operations involving the risk of fire.
b) This Permit applies to the works specified in Section A only.
c) Smoke/Heat detectors local to the work must be isolated before works begin and re-instated on
completion. (Fire alarm isolation Request Form MF02)
IN THE EVENT OF A FIRE, VACATE THE AREA, OPERATE THE NEAREST FIRE ALARM BREAK GLASS THEN
CONTACT SECURITY ON 0116 252 2023.
ESTATES & FACILITIES MANAGEMENT DIVISION
Fielding Johnson Building, University Road, Leicester LE1 7RH, UK
T +44 (0)116 252 2522 F +44(0)116 223 1333
At (exact location):
SECTION B YES NO
Please tick as appropriate.
The above location has been examined………………………………………………………………
Is the roof edge protected?.…………………………………………………………………………………
Suitable fall prevention equipment available and up to date test
certificates inspected……………………………………………………………………………………………
Two operatives to do the task………………………………………………………………………………
Are operative trained to use fall arrest equipment? ……………………………………………
Contractor aware of Contractors General Code of Safe Practice Procedures………
(Section 9 – Work above ground).
Is roof fragile, are crawl boards available.
SECTION C
Permit issued by: Signature:
Position: Date:
SECTION D
The dangers associated with working on roofs, especially those with no edge protection have been explained
to
me and are fully understood.
Name Signature
Company Date
Notes
This „Permit to Work‟ allows job specific entry to plantrooms service ducts and other
service areas to undertake the works as detailed on the Permit.
The areas covered by this permit are under the control of the Estates and Facilities
Management Division Maintenance Section and no works can commence until a permit has
been issued by one of the following authorised persons:
This permit ceases to be in operation when the works detailed are complete and the
plantroom has been returned to the control of the Maintenance Section and accepted by
the person issuing the permit.
The Contractor taking control of the plantrooms agrees to take responsibility for returning
it to the Maintenance Section in a clean and tidy condition which includes removal of all
rubbish and waste, completion of all thermal insulation, except that missing and agreed at
handover.
The Contractor agrees that unrestricted access to the plantroom will be made available to
Maintenance Staff to enable routine maintenance and service to equipment not forming
part of the Contractor‟s works.
Date: From To
Time: From To
SECTION B
The plantroom(s) has been jointly inspected and when handed to the person named in
Section A the following items were evident:
SECTION C
I accept control of the plantroom and agree to return it in a clean and tidy condition
subject to
the items detailed in section B
Name: Signature:
Company: Date:
SECTION D
Return of the Plantroom to the Maintenance Section has been accepted by the undersigned
on the date indicated:
Name: Signature:
Date:
ESTATES & FACILITIES MANAGEMENT DIVISION
Fielding Johnson Building, University Road, Leicester LE1 7RH, UK
T +44 (0)116 252 2522 F +44(0)116 223 1333
Precise description of
work to be undertaken:
Duration of Permit
Hazard Identification
Infection hazard: group 3 biological hazards are used in this laboratory.
No other special hazards are present.
Precautions
Biohazards have been secured within the containment level 3 labs.
If the permit and the site rules are adhered to, then the ricks from the above hazards are
negligible. No other specific precautions are needed.
Site Rules
(C3SM: Containment Level 3 Suite Manager)
You must contact C3SM (Containment Level 3 Suite Manager) or appointed person
before attempting to gain access.
Report to the C3SM, or the appointed person on arrival and departure.
Sign in as required by the C3SM when you arrive and depart site.
No eating, drinking or smoking is permitted in the laboratories.
Do not move ANY piece of equipment in the labs – contact the C3SM or a member of
the lab staff if you need anything to be moved.
Do not unplug or otherwise disconnect any other service to any lab equipment –
contact the C3SM or a member of the lab staff if your need anything to be
disconnected.
Do not open the doors of any lab equipment or lab furniture – this includes cupboards,
fridges, freezers and incubators.
Do not enter any lab other than the one in which you are working and which this
permit covers.
Report all incidents immediately to the C3SM or his nominated deputy.
Inform the C3SM or appointed person when (1) leaving site temporarily, (2) finishing
work for the day (3) completing the job.
In some situations direct supervision is required – this means that a member of the lab
staff will accompany you in the lab until you have finished the job.
Any alteration, or work additional to the original job description, must e authorized by
appointed personnel.
The contractor must liaise with the C3SM or the appointed person to complete the C3
maintenance book detailing the work carried out.
YES NO
Contractor has been handed a copy of the University‟s latest
edition of Contractors General Code of Safe Practice:
Name: Position:
Name: Position:
In addition to isolation and procedures in Parts A and B, the following safety precautions
will be taken:
Acceptance
I have read and understood this Permit and will undertake to work in accordance with the
conditions set out herein and the University “Contractors General Code of Safe Practice”.
Company:
Authorised/accepted permit to be returned to the Estates Office and copied to the C3SM
BEFORE commencement of the work. Master copy to be retained by Estates.
Handback
YES NO
The work has been completed…………………………………………………………
Name: Position:
Name: Position:
Ref……………………………..
Valid until……………………..
Date……………………………
ESTATES & FACILITIES MANAGEMENT DIVISION
Fielding Johnson Building, University Road, Leicester LE1 7RH, UK
T +44 (0)116 252 2522 F +44(0)116 223 1333
Precise description of
work to be undertaken:
Steam or heat…………………………………………………………………………………………
Position: Date:
PART C (to be completed by Contractor)
Breathing apparatus…………………………………………………………………………………
Eye protection…………………………………………………………………………………………
Dust respirator…………………………………………………………………………………………
Exhaust fan……………………………………………………………………………………………
I have read and understood this Permit and will undertake to work in accordance with the
conditions set out herein.
Company:
(*delete as appropriate)
CLIENT/DUTY HOLDER:
Signature:
Please Print:
Date:
Will the work disturb any Asbestos containing materials (ACMs) identified in the premises
Asbestos Register?
http://leicester.ac.micadipr.net/idr-data/lite/asbestos.html
YES The proposed work MUST NOT proceed. Advice must be sought from:
Signature:
Date: