Inspection Test Plan: Fabrication and Instalation of Piping

This inspection test plan outlines the quality control activities, characteristics to be verified, controlling documents, acceptance standards, verification documents, and responsibilities for the fabrication and installation of piping. Key aspects include verifying materials meet certificates and standards, welding is performed according to approved procedures by qualified welders, 100% visual and NDT inspections are conducted on welds, mechanical completion activities are completed prior to shipping, blasting and painting meet approved specifications, and final review and approval is given prior to shipping to the site for installation. Responsibilities are assigned and records will be maintained.

Uploaded by

Rejoy baby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
134 views3 pages

Inspection Test Plan: Fabrication and Instalation of Piping

This inspection test plan outlines the quality control activities, characteristics to be verified, controlling documents, acceptance standards, verification documents, and responsibilities for the fabrication and installation of piping. Key aspects include verifying materials meet certificates and standards, welding is performed according to approved procedures by qualified welders, 100% visual and NDT inspections are conducted on welds, mechanical completion activities are completed prior to shipping, blasting and painting meet approved specifications, and final review and approval is given prior to shipping to the site for installation. Responsibilities are assigned and records will be maintained.

Uploaded by

Rejoy baby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

INSPECTION TEST PLAN Contract No:

DANEM ENGINEERING WORKS WLL. FABRICATION AND INSTALATION OF PIPING QCP NO: Rev:0

CLIENT:

Verifying Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Responsible Person Remarks
Documents/Reports DANEM QVC

Approved Drawings Site Contractual Documents Relevent Contractual Documents Drawing Calculations Design Engg:
1.0 Engineering H H
survey Standards Relevent Standards Requirements Project Manager

Preliminary activities
Approved letter of
drawing approval technical Approved Drawings Approved Drawings
2.0 - signature on Project Manager H H
documents to start of Specifications Specifications
documents
manufacture

Test certificates
Drawing, Material Certificate QA/QC ,
3.0 Material Store record MTC ,Drawing Material inspection H w
,Grade &Heat Number Fab:SUPVR
report

Clearly identified ,Segregated


Store Keeper ,
3.1 Material storage to prevent MTC , Store Record Identification as per MTC - H R
SUPVR
damage&contamination

Shop Fabrication prior to Dimensions, Heat Number QA/QC ,


4.0 Approved Drawings Approved Drawings Inspection Report H R
cutting of pipe ,Grade, Size&Specs Fab:SUPVR

Accordance with
Approved WPS,Check weld Fit QA/QC ,
4.1 Fit-Up Approved Drawings approved and project Inspection Report H R
up as per WPS Fab:SUPVR
spec
Electrode baking/Holding/Issue QA/QC , Store
5.0 Welding Monitoring Welding control procedure MFRS Recommendations Records S S
Records Keeper

ApprovedWPS /PQR,Welders ASME SEC-IX ASMEB31.3 Weld /NDT summary


5.1 Welding WPS /PQR,Welders certificate QA/QC H R
certificate &drawings report

100% Visual inspection on


5.2 Visual Inspection Approved Drawings Weld map ASMEB31.3 &drawings Inspection Report QA/QC H R
completed weld

ASME.SEC V,NDT
Radiogrphy on completed Weld map/ Records / Asper Scope
6.0 NDT Procedure &Project Test Reports QA/QC H R
welds of Work and Approved Drawings
Specification

1 of 3
INSPECTION TEST PLAN Contract No:

DANEM ENGINEERING WORKS WLL. FABRICATION AND INSTALATION OF PIPING QCP NO: Rev:0

CLIENT:

Verifying Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Responsible Person Remarks
Documents/Reports DANEM QVC

Shop Activities have to


Mechanical Completion App. Drawing Project QA/QC
7.0 completed prior to shipping Weld Map Records QC Documents H R
(Shop Fabrication) Specification FAB. SUPVR.
to site

As per approved
Surface preparation and Painting procedure and Project Blasting & painting QA/QC
8.0 Blasting&Painting drawings and Project H R
painting Spec. Report. PAINTING. SUPVR
Spec.

8.0 Shipping

Final Review
8.1 Shipping to Site ( Document &Reports ) Delivery Note Relevant Document Delivery Note FAB.SUPVR. H S
Approval Identification Mark

9.0 Site Installation

Approved WPS,Check weld Fit Accordance with QA/QC ,


9.1 Fit-Up Approved Drawings approved and project Inspection Report H R
up asper WPS Fab:SUPVR
spec
Approved WPS ASME SEC-IX ASMEB31.3 Weld /NDT summary
9.2 Welding WPS /PQR,Welders certificate QA/QC H R
/PQR,Welders certificate &drawings report

As per approved
Stage wise Inspection
9.3 Stage wise Inspection As per approved drawings drawings and Project Inspection Report QA/QC H R
during Installation.
Spec.

As per approved
Alignment Check of all
9.4 Alignment As per approved drawings drawings and Project Inspection Report QA/QC H R
Flanges
Spec.

As per approved
Orientation check of all
9.5 Orientation As per approved drawings drawings and Project Inspection Report QA/QC H R
Flanges.
Spec.

As per approved
Alignment Check of all
9.6 Alignment As per approved drawings drawings and Project Inspection Report QA/QC H R
valves
Spec.

2 of 3
INSPECTION TEST PLAN Contract No:

DANEM ENGINEERING WORKS WLL. FABRICATION AND INSTALATION OF PIPING QCP NO: Rev:0

CLIENT:

Verifying Inspection by
Item Quality Control Activity Characterstic to be verified Controling Documents Acceptance Standards Responsible Person Remarks
Documents/Reports DANEM QVC

As per approved
Orientation check of all
9.7 Orientation As per approved drawings drawings and Project Inspection Report QA/QC H R
valves
Spec.

As per approved
9.8 Overall dimension Overall dimension check As per approved drawings drawings and Project Inspection Report QA/QC H R
Spec.

100% Visual inspection on


9.9 Visual Inspection Approved Drawings Weld map ASMEB31.3 &drawings Inspection Report QA/QC H R
completed weld

ASME.SEC V,NDT
Radiogrphy on completed Weld map Records / Asper Scope
9.10 NDT Procedure &Project Test Reports QA/QC H R
welds of Work and Approved Drawings
Specification

Weld map /Records / Asper Scope App. Drawing Project


10 Hydro Test Hydro Test of Piping Test Report QA/QC H W
of Work and Approved Drawings Specification

Activities have to be App. Drawing Project QA/QC


11 Mechanical Completion Weld Map and Records QC Documents H H
completed Specification FAB. SUPVR.

Quality Inspection Test


12 Quality Dossier Contractual Requirements Documents and Reports QC Dossier QA/QC Engineer H H
Plan Clients Requirements

Legends: H: Hold point I:Inspection R:Review W:Witness S: Surveillance

3 of 3