LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
CONCRETE WORKS Carpenter Steel Fixer Con Mason Helper
1 PCC below footings
a Formwork m2 40 1 1
b Concrete m 3
20 2 3
2 PCC below slab on grade
a Formwork m2 25 1 1
b Concrete m 3
40 2 3
3 Column footings / Pile Caps
a Formwork m2 30 2 2
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m 3
55 2 2
4 Strip footings
a Formwork m2 25 2 2
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m 3
55 2 2
5 Pedestals (Neck Columns)
a Formwork m2 25 2 1
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m3 20 1 2
6 Tie Beams
a Formwork m2 30 2 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m3 20 2 2
7 Slab on grade
a Formwork & Joints m2 of slab 200 2 1
b Mesh Reinforcement m 2
300 2
c Bar Reinforcement (fabrication & fix) kg 250 1
d Concrete - Trowel finished m3 40 2 3
8 Retaining Walls
a Formwork m2 30 3 1
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m3 18 1 2
d De-Shuttering m 2
9 Shear Walls
a Formwork m2
b Reinforcement (fabrication & fix) kg
c Concrete m3
d De-Shuttering m2
10 Columns upto 0.5 sqm in area (using fabricated forms)
a Formwork m2 14 2 1
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m3 9 1 2
d De-Shuttering m 2
Page 1 of 5
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
CONCRETE WORKS Carpenter Steel Fixer Con Mason Helper
11 Beams
a Formwork m2 20 2 2
b Reinforcement (fabrication & fix) kg 160 1
c Concrete m3 15 1 2
d De-Shuttering m 2
12 Slabs (Solid)
a Formwork m2 15 1 1
b Reinforcement (fabrication & fix) kg 200 1
c Concrete m 3
75 3 3
d De-Shuttering m2
13 Slabs (Hourdy)
a Formwork m2
b Reinforcement (fabrication & fix) kg
c Concrete m3
d De-Shuttering m2
14 Parapets
a Formwork m2 20 2 2
b Reinforcement (fabrication & fix) kg 175 1
c Concrete m 3
12 1 1
15 Cantilevers
a Formwork m2 12 1 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m3 50 3 3
16 Stairs
a Formwork m2 15 1 1
b Reinforcement (fabrication & fix) kg 170 1
c Concrete m3 20 1 1
17 Ramps
a Formwork m2
b Reinforcement (fabrication & fix) kg
c Concrete m3
18 Lintels
a Formwork m2 8 1 1
b Reinforcement (fabrication & fix) kg 180 1
c Concrete m 3
5 1 1
Page 2 of 5
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
BLOCK WORK Block Mason Helper
Sub-Structure - Solid Blocks
1 200 mm Blockwork m2 12 1 1
Super-Structure (upto 3m height) - Solid Blocks
1 100 mm Blockwork with pointing m2 15 1 2
2 150 mm Blockwork with pointing m 2
3 200 mm Blockwork with pointing m2 10 1 2
4 250 mm Blockwork with pointing m2
Super-Structure (upto 3m height) - Hollow Blocks
1 250 mm Blockwork with pointing m2
2 200 mm Blockwork with pointing m2 16 1 2
3 200 mm blockwork in non-straight walls with pointing m2 12 1 2
4 150 mm Blockwork with pointing m 2
5 150 mm blockwork in non-straight walls with pointing m2
6 100 mm blockwork in straight walls with pointing m2 18 1 2
7 100 mm blockwork in non-straight walls with pointing m 2
14 1 2
Miscellaneous
1 Cover Block m2 9 1 1
2 Cutting & Chasing m 2
2 Block shifting GF to 3rd Floor No 240 1
PLASTER Plaster Mason Helper
1 Plastering Accessories fixing m2 60 1 1
2 Internal Plaster 12mm thick on walls m 2
16 1 1
3 Internal Plaster 12mm thick on ceilings m2 12 1 1
4 External Plaster 16mm thick (upto 3m high) m 2
5 External Plaster 16mm thick (over 3m high) m2
6 External Plaster 19mm thick (upto 3m high) m2 20 1 1
7 External Plaster 19mm thick (over 3m high) m2 18 1 1
8 External plaster -Rush coat m 2
100 1 1
9 Compressed Plaster m 2
60 1 1
10 Sub frame fixing No 5 1 1
11 Tyroline over plastered or fare face concrete surface m 2
175 1 1
Page 3 of 5
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
TILING WORK Tiler Helper
1 Ceramic Floor Tiles m2 20 1 1
2 Ceramic Wall Tiles m 2
18 1 1
3 Ceramic Tile Skirting LM 40 1 1
4 Ceramic floor / wall tiles grouting m2 32 1 1
5 Ceramic claustra work m 2
6 1 1
6 Granite/Marble threshold No 10 1 1
7 Granite/Marble Floor Tiles m2 10 1 1
8 Granite/Marble Wall Tiles m 2
9 Terrazzo Tiles m2 20 1 1
10 Terrazzo Skirting LM 40 1 1
11 Terrazzo Treads & Risers LM 30 1 1
12 Floor Screed 50mm thick m 2
27 1 1
13 Interlocking Pavers m2 48 1 1
14 Kerbstone m 56 1 1
FALSE CEILING Ceiler Helper
1 Suspension System m 2
35 1 1
2 Ceiling Tiles m2 60 1 1
3 Gypsum Ceiling & Cornish (i/c Suspension System) m 2
2.5 1 1
4 Dry wall partition m 2
20 1 1
PAINT WORK Painter Helper
1 Prime Coat m2 200 1 1
2 Surface preparation for paint m 2
80 1
3 Paint 1st Coat - brush application (Emulsion Paint) m2 100 1 1
4 Paint 2nd Coat - brush application (Emulsion Paint) m 2
100 1 1
5 Paint 1st Coat - roller application (Emulsion paint) m 2
125 1 1
6 Paint 2nd Coat - roller application (Emulsion Paint) m2 125 1 1
7 Paint 1st Coat - brush application (Enamel Paint) m2 60 1 1
8 Paint 2nd Coat - brush application (Enamel Paint) m 2
60 1 1
9 Paint 1st Coat - roller application (Enamel Paint) m 2
95 1 1
10 Paint 2nd Coat - roller application (Enamel Paint) m2 70 1 1
11 Epoxy Paint on Floors per coat m 2
50 1 1
12 Bitumen paint for waterpoofing single coat m 2
50 1
13 Stucco Paint m2
Page 4 of 5
LABOR PRODUCTION RATES
8 HRS
Sr. No. ITEM PRODUCTIVITY LABOR
Unit Qty
WOOD WORKS Joiner Helper
1 Wooden frames fixing for openings upto 5 m 2 nos 8 2 1
2 Wooden door shutters fixing (incl hardware) nos 5 2 1
3 Wooden Pergola m 2
4 Wooden Vanities nos
5 Kitchen Cabinets nos
6 Wardrobes nos
7 Handrail LM
METAL WORKS Metal Workers Helper
1 Steel Frames fixing for openings upto 5 m 2
nos 8 1 1
2 Steel Shutter fixing nos 5 1 2
3 Handrail and Balustrade LM 8
4 Glazed Balustrade with Stainless steel handrail LM 6
5 Structural Steel Columns and Beams kg
6 Wardrobes nos
7 Passanger Lifts nos
ALUMINIUM WORKS Aluminium Workers
1 Aluminium doors for openings upto 5 m 2 nos 8 2
2 Aluminium windows (glazed) nos 6 2
3 Glazed Curtain Walling m 2
4 Aluminium Louvers nos
5 Aluminium Cladding m2
6 Skylights m2
Page 5 of 5