A) DESIGN
1. Reference to the drawing, the type of pipe that were used in this project are Mild
Steel Cement Lining (MSCL) type or mild steel pipe. For mild steel pipe, the size that
were used are 150 mm, 200 mm, 300 mm, and 400 mm.
B) CONSTRUCTION
i) Water pipeline construction.
1. Check plumber registration with Suruhanjaya Perkhidmatan Air Negara (SPAN).
Prior to commencement of work, the responsible person have to ensure that
contractor is registered with SPAN.
2. Then, the contractor need to check and ensure that the referenced drawing is a
construction drawing of the latest revision. The contractor also need to check the
work programme activity status and ensure that if work program allow the
pipeline construction activity, and whether it is in the critical path method. The
assigned contractor can bring the drawing to Pengurusan Air Pahang Berhad
(PAIP) and they will advise about which suitable or nearest water supply that can
be connected to the construction site.
3. Next, the assign contractor must ensure that the material delivered to site is as
approved in the method statement and drawing.
4. After the contractor has ensure that every step above is completed, then the land
surveying can do their works which is to mark the centerline of pipeline and must
be carried out by licensed surveyor.
5. Then, site clearing for pipe laying must be done to remove trees and vegetation.
6. Once pipes are delivered to site, it is the duty of site staff to check that the pipe
conform to approved method statement, drawing and specification. They are to
check according to UTG procedure.
7. After that, check pipe thickness to prevent catastrophic damage from leaking
water of gases, including fire risk.
8. After that, lowered the risk of damage to other building elements and to ensure
safe working conditions.
iv) Pipe laying work and backfilling the pipes after the placement of the pipe is
confirmed.
1. It requires specifications, contract requirements and understanding soil conditions.
2. Backfilling is used in tasks such as protecting foundations, landscaping, or filling
in voids in underground structures.
vi) Tapping
1. It is the method of making a connection to existing piping or pressure vessels
without the interrupting or emptying of that section of pipe.
2. This means that a pipe or tank can continue to be in operation whilst maintenance
is being done to it.