06 Sec. 4 Sewer Testing
06 Sec. 4 Sewer Testing
06 Sec. 4 Sewer Testing
Sewer Testing
Sewer Testing
4.1
General
Sewers and ancillary works shall be tested and inspected for watertightness to prevent infiltration and exfiltration and to ensure the pipes
are laid correctly according to the designed straightness and grade. The
testing of the sewers and ancillary works before backfill will facilitate
the replacement of any identified faulty pipes and joints. The testing of
the sewers and ancillary works after backfill will reveal the leakages
caused by the displacement of joints and subsequent damage. The testing
shall be supervised by consultants and their testing certificates issued
by the consultants shall be submitted to the Commission before final
approval.
I) Before Backfill
a) Gravity Sewer:
i) Exfiltration Test (either low pressure air or water tests).
ii) Check for straightness, obstruction and grade.
b)
Force Main:
i) Exfiltration Test (when required).
ii) High pressure water test.
iii) High pressure leakage test (following high pressure water
test).
iv) Check for straightness, obstruction and grade.
c) Manhole and others:
i) Visual inspection.
ii) Watertightness test (when required).
For pipe or part that is made of material that will deteriorate under the
sun, the exposed parts of the pipe shall be shielded from direct exposure
to the sun during testing.
The concrete used for supporting the pipe or resisting thrust shall be
cured for at least seven days prior to testing.
Volume 3
97
Sewer Testing
Gravity Sewer:
Before and after any test, the sewer pipeline to be tested shall be clean,
which shall be flushed clean when necessary. Any leaks or defects
identified from any test shall be located and repaired. After testing has
been completed, the cleaned sewer shall be plugged at open ends to
prevent dirt or soil from getting into the sewer.
4.2
An exfiltration test, which can be either a low pressure air test or a water
test shall be performed on the sewer before any concrete pipe encasement
or backfill. After backfilling, an exfiltration test is required again on the
sewer laid. In addition, an infiltration test shall be conducted if:
When infiltration has been confirmed by the infiltration test, light and
mirror method or CCTV may be used to isolate the locations of leaks.
If a CCTV inspection is conducted, a video and written record of the
CCTV inspection shall be provided to the Commission no later than 7
days after the inspection.
For gravity sewers, the sewer length to be tested shall be the length
between manholes or proposed manhole locations. The test length for
water test may be shorter where the gradient is so steep as to cause too
high a head at the downstream end. The pressure head on the sewer being
tested shall not be less than 2 m above pipe crown at the upstream end
and shall not be more than 7 m above pipe crown at the downstream
end.
When desired, the air and water tests may be undertaken on shorter
lengths of the laid sewer before backfill. This is to prevent any faulty
joint to go unnoticed until it is revealed by a test on the complete length,
which will be more costly and time consuming to rectify the defects.
Testing of shorter lengths may also be necessary where it is required to
98
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
backfill the sewer to surface level quickly. This early backfill may be
encountered when there is wet weather, traffic crossings or site safety
requirements.
4.3
For pressure sewers, the normal tests during the sewer laying may include,
where required, the low pressure air or water exfiltration tests on short
individual sections. These low pressure air or water exfiltration test are
conducted, when required, to ensure that the joints are watertight.
For the high pressure water test, the test length will depend on:
Volume 3
99
Sewer Testing
4.4
a)
b)
c)
d)
e)
f)
4.5
4.5.1
General
Low pressure air test is one of the two sewer exfiltration tests recommended
for sewer testing. The air test is quicker to conduct than the water test.
Furthermore, no large quantity of water needed to be disposed off after
the test. This test provides a quick mean for checking any damage pipe
or joints. Sometimes the test is conducted on a short length to prevent
damage pipe or joints from passing without noticed until the final sewer
test, which could be more costly and time consuming to rectify. However,
these tests on the shorter length should not replace the final test.
100
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
4.5.2
a) Seal the open ends, including sideline ends, using approved plugs.
Strut the plugs to prevent movement. Provide temporary bracing
where necessary to prevent pipeline movement during testing.
(One of the end plugs will require a connection point to permit
injection of air).
b) Connect a hand or motorised pump to the pressure injection line
at the end plug. Pressurise the test length at a slow and constant
rate.
c) Use dial pressure gauges to measure pressure. Apply an air pressure
of:
i) 30 kPa for vitrified clay and reinforced concrete pipelines.
ii) 50 kPa for all other pipelines.
(Two gauges in series shall be used so that the accuracy of one
gauge can be confirmed by the other. The dial gauges shall be able
to be read to an accuracy of 0.1 kPa).
d) Wait five minutes for air pressure to stabilise due to temperature
absorption into pipe wall and other effects. Adjust the pressure to
the required test pressure during this period.
e) Check for leaks at plugs and test apparatus. Release the air pressure
where leakage occurs. Make necessary repairs and adjustments of
apparatus to prevent leakages. Repressurise the sewer pipeline in
accordance with the preceding steps again.
f) Start the test and record the pressure loss for the test duration after
the final gauge adjustment to the test pressure. Conduct the test for
the test duration given in Table 4.1.
Test Duration
(minutes)
2
4
6
8
11
14
17
Volume 3
101
Sewer Testing
g) Pass the test if the pressure loss over the test duration does not
exceed:
4.5.3
I) Before Backfill
a) Readjust the pipe pressure to the specified test pressure and examine
for leakage by pouring a solution of soft soap and water over the
exposed joints if the test fail.
b) Repair leaks and repeat testing where leaks are found at joints.
c) Where leaks are not found at joints, move the plug, the one that is
not used to exert air pressure, along the pipeline to isolate lengths
with leakage. Uncover pipe barrels in the isolated lengths where
leakage in pipe barrels is suspected. Replace leaking pipe lengths
and repeat testing.
d) Conduct low pressure water testing to verify that the air test was
not erroneous where the test length fails the air test but no source
of leakage can be identified.
a) Move the plug up from the other end along the sewer pipeline to
isolate the lengths that fail the air test.
b) Exhume the failed length of pipeline and replace pipe lengths.
c) Repeat the air test.
d) Conduct water testing to check that the air test was not erroneous
when failed lengths could not be isolated using the air test.
e) Use CCTV, when required or available, to identify the leakage if
the fail section can not be isolated by the air test or water test.
4.6
4.6.1
General
The low pressure water test is commonly used for checking the watertightness of the joints and the integrity of the sewer pipes. Unlike the
high pressure water test, this test can not be used to check the mechanical
strength of the sewer pipe. Compared with low pressure air test, this test
requires more time to set up the test. Also, the water used for the test
102
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
Procedure
a) Seal the open ends, including sideline ends, using approved plugs.
Strut the plugs to prevent movement. Provide temporary bracing
where necessary to prevent sewer movement during testing.
b) Establish appropriate arrangements involving a standpipe to apply
the water head at the upstream end.
Acceptable arrangements include:
i) temporarily fitting a 90 bend to the upstream end, which should
then be connected with a vertical riser of straight pipe to used
as a standpipe.
ii) sealing the upstream end with a plug which has a connection
point for a hose, which can be connected to a tube acting as a
standpipe.
d) Fill in water from the upstream end. Ensure water head is not less
than 2 m above pipe crown at the upstream end and not greater
than 7 m above pipe crown at the downstream end. Shorten the test
length if the sewer gradient is so steep as to cause these water head
requirements not to be met.
e) Fill the sewer slowly to the required head and bleed air from behind
the upstream plugs.
(Air may be released by slightly loosening the plug and pushing in
a piece of wire between the seal and the pipe.)
f) Maintain the water head for two hours. Top up the water as
required.
g) Check for leakage at the plugs and the test apparatus during the
pressurising period and the constant pressure holding period. Release
the water pressure if leakage occurs. Make the necessary repairs and
adjustments before repressurising again.
h) Commence the test immediately after the last adjustment of water
head in the preceding two hours period.
i) Add water to maintain the starting water head every 5 minutes
during the test period of 30 minutes. Record the total amount of
water required for readjustment.
j) Pass the water test if:
i) the loss of water does not exceed 1 litre per hour per linear
metre per metre internal diameter for vitrified clay and reinforced
concrete pipes.
Volume 3
103
Sewer Testing
ii) there is no loss of water for pipe other than vitrified clay and
reinforced concrete pipe.
iii) these is no visible leakage at the joints for all pipe types.
4.6.3
I) Before Backfill
a) Readjust the internal water head to the specified test head if the
test section fails the water test. Examine visually for leakage at the
external surface of joints.
b) Uncover pipe barrels and inspect for leakage if leakage is not evident
at joints. Drain the water and move the downstream plug towards
upstream, where necessary, to isolate pipe lengths that fail the water
test.
c) Repair or replace pipes before repeating the low pressure water test
until the sewer passes the test.
a) Isolate pipe lengths that fail the water test by moving the downstream
plug towards the upstream end in sections when the test sewer fails
the water test. Alternatively, conduct a CCTV inspection, where
required, to identify the source of leakage if the source of leakage
can not be isolated.
b) Exhume failed pipe lengths and replace.
c) Repeat test until the sewer pipeline passes the test.
4.7
4.7.1
General
High pressure water test is normally used for testing the pressure sewers
and pipeworks within the pump station. The main aims of the test are
to ensure the mechanical stability of the pipe and joints can withstand
the working pressure. Since the test is conducted under high pressure,
the anchorage of the sewer is more critical than the low pressure tests.
Preferably, the test should be conducted before backfill. During the test,
the test pumps should not be subjected to hydrostatic pressure.
4.7.2
Procedure
a) Seal the sewer pipeline ends using test-end units consisting of short
lengths of pipe permanently fitted with caps or valves. Connected the
104
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
Volume 3
105
Sewer Testing
l) Pass the pressure test if there is no reduction from the test pressure
in the next 10 minutes after the test pressure is conducted. Do not
reduce the pressure as the high pressure leakage test should be
conducted immediately after this.
4.8
4.8.1
General
High pressure leakage test normally follows the high pressure water test
immediately. This is to avoid any unnecessary pressurising and water
filling, which could take time and is costly. The purpose of this test
is to ensure the pipe and joint will remain intact under the pressure
environment.
4.8.2
Procedure
a) Conduct the test immediately after the high pressure water test.
Maintain the following test pressures (whichever is lower) for 24
hours by pumping in make-up water if necessary:
i) The maximum rated pressure of the pipes laid, or
ii) 1.5 times the design operating pressure of the pipeline (includes
surge allowance).
b) Measure the amount of make-up water pumped into the pipe to
maintain the test pressure.
c) Pass the test if the measured amount of make-up water does not
exceed 0.1 litre per millimetre of pipe diameter per kilometre of
pipe per day for each 3 bars of pressure applied.
d) Reset the test pressure and check all visible joints to locate leakage
when the test length fails the test.
4.9
a) Visual inspection
b) Insertion of mandrel
c) CCTV inspection
106
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
a)
b)
c)
d)
e)
The first three methods will provide a more exact assurance for both
the gradient and straightness of sewers, which shall be used whenever
possible. The latter two methods will provide a rough idea on whether
the sewers are laid in certain gradient or straight, which should be used
only for a quick check.
4.10
CCTV Inspection
4.10.1
4.10.2
Volume 3
107
Sewer Testing
a) Solid state colour CCTV camera with pan & rotate features, together
with a lighting unit, automatic date/ metre age.
b) A self powered tractor or crawler on which the camera is conveyed
along a pipeline under inspection in a stable manner.
c) Calibration chart for various sizes of sewer for the camera used.
d) Test device for the CCTV camera using Marconi Resolution Chart
No.1 or its derivative to demonstrate satisfactory performance of
the camera.
e) Test device for the monitor and video recorder to establish the
effectiveness and accuracy of the on-site monitor and video
recorder.
f) The control unit comprises the camera unit, crawler control and
screenwriter. This console can be mounted permanently in a vehicle
or use as portable system.
g) A video recorder for recording high quality video images.
h) A mean of producing still images from the monitor screen.
i) A PC-based site reporting system capable of producing reports
customised to the Contractors needs and to include photographs
captured directly from video.
For the diameter pipe greater than 600 mm, it shall have zooming
capabilities.
4.10.4
The following areas are identified as the minimum coverage for CCTV
inspection.
108
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
A 100% CCTV inspection shall be conducted for sewers laid in the ground
with high risk of failure and having the following characteristics:
Volume 3
109
Sewer Testing
4.10.5
a) The list of sewer segments and house connections selected for CCTV
inspection shall be recorded and the parties witnessing the selection
process shall duly sign the record.
b) Names and designations of all persons involved in the random selection
process as well as the time, date and place where the selection were
carried out shall be recorded in the report on the random selection
process. Record of the sewer segments randomly selected for CCTV
inspection shall be included as appendix in the report.
c) The random selection process shall be completed in a single
session.
110
a) The CCTV inspection shall be carried out 7 days after notice issued
by the Commission.
b) Inspection shall be carried out within 24 hours after random selection
has been completed.
c) Once started, CCTV inspection for a project shall be carried out
without any break. Should for any reason a break/delay of more than
24 hours become necessary, the random selection process shall be
repeated to select the remaining sewer segments for the inspection.
Reasons for the break/delay shall be recorded.
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
v) Grade 5 : Red
Volume 3
111
Sewer Testing
4.10.7
a) For Grade 1 and Grade 2, the developer shall rectify and make
112
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
Volume 3
113
Sewer Testing
4.11
Infiltration Test
4.11.1
General
4.11.2
Procedure
a) Plug the inlets at all upstream open ends, after the groundwater level
4.11.3
4.12
Watertightness Test
4.12.1
General
114
Volume 3
Malaysian Sewerage
Industry Guidelines
Sewer Testing
a)
b)
c)
d)
e)
The test should be carried out only after the structures have achieved
sufficient strength to withstand the test pressure. Where possible, the
test shall be carried out before backfilled or concrete surrounded.
For manhole less than 1.5 m in depth, the manhole shall be filled with
clean water to the bottom of cover. For manhole more than 1.5 m in
depth, the water head for the test shall not be less than 1.5 m or the
mean groundwater level, whichever is larger. For any other ancillary
structure, the water shall be filled to the top of the structure unless
otherwise specified by the authorised inspection person.
The procedures for testing the manhole are listed below. For other
ancillary structures, the procedures can still be adopted. However, the
height which the water level should be tested shall follow the instruction
from the authorised inspection person.
4.12.2
Procedures
d)
e)
f)
g)
Volume 3
115