Understanding The GIS Interlocks
Understanding The GIS Interlocks
By:
              1.1.2.What is a switch?
                  A switch is a device for making and breaking the connection in an electric circuit. A simple
                  example is the light switch in a room which can be used to turn the lights on or off. In a
                  substation, Disconnectors, Earthing Switches and Circuit Breakers are typical examples of
                  switches.
              1.2.2 Disconnector:
                  A disconnector or disconnecting switch a switch used typically in HV and EHV switchgears to
                  perform off load operations which in turn make the system ready for on load switching. Off load
                  switching is always done before on-load switching when the system is dead. Disconnecting
                  switch is sometimes denoted as ‘DS’
For Example :
                                                                 DS
                             Power                                                                  Cable Feeder
                             Supply                                                                                       Load
                                CB
                                                                                   ES
                    *The DS must be closed before closing the CB because if the CB is closed and the DS is allowed to
                    close after that, it will be on load switching at a very slow speed which will damage the system
                    due to arching.
                    *If we want to close the earthing switch, The DS should be open. Otherwise if the CB is closed ,
                    the power supply will be grounded. Or if the CB is open , anyone can close it which will ground
                    the power supply.
                    These are few simple cases which illustrate that in order to safely perform a switching operation,
                    a certain set of conditions need to be satisfied to allow the operation. In the above cases:
                         For CB operation, the DS must be closed. If DS is open, it should not allow CB to close.
                         For DS operation , the ES and the CB must be open. If anyone is close, it should not allow the
                          DS to operate.
                         For ES Operation, the DS must be open. If DS is closed, ES should not be allowed to operate.
                    So we can see that these are the 3 governing conditions or interlocks for ensuring safe switching
                    operation in the above 3 cases described. In other words, the first condition is the interlock for
                    the CB. The second condition is the interlock for the DS. And the third condition is the interlock
                    for the ES.
                    It should also be noted that interlock exists in both directions. i.e. For operation of disconnector,
                    the ES must be open. Subsequently , for operating of earth switch , disconnector must also be
                    open. Before closing of CB, DS must be closed. Subsequently , DS must only be allowed to
                    operate when CB is open.
                    All these conditions are included in the control scheme of the switches by wiring. If a bay control
                    unit relay is available for the bay, then these conditions can be included in soft logic also.
                         Interlock of earthing switch should always be with service position of the feeder CB.In
                          switchgears, CB in service means the CB is racked in. In GIS , CB in service means the
                          disconnectors of CB are closed. If So if DS is closed (or CB is racked in), ES should not be
                          allowed to close and vice virsa.
                         Interlock of DS should be with CB and ES.
ES.1
                                                                                                                  Upper Portion
                                                                                      UPPER
    Remote End SS                                                                      CB
ES.2
DS.2
ES.3
DS.4
                                                                                                                                                                                                              Transformer Feeder
                                                                                                                  Middle Portion
                                                                                                      ES.5                                                      DS.3
                                                         VT.DS.2
                                                                                     MIDDLE
                       ES.8
                                                                                       CB
                                                                                                                                                                                                 ES.4
Line Feeder
                                                                                                     ES.6                                           VT.DS.1
                                               DS.6
DS.5
ES.7 380KV
DS.7
                                                                                                                                                                   230KV           13.8KV
                                                                                                      ES.9
                                                                                                                                    230KV GIS
                                                                                                                    Lower Portion
                                                                                     LOWER
                                                                                       CB
                                                                                                                                                                                            13.8KV
                                                                                                                                                                                             ES.1
                                                                                                      ES.10                                               230KV
                                                                                                                                                          TRAFO                                         13.8KV
                                                                                                                                                           ES.1                                           CB
                                                                             DS.8
                                               BUS2 ES
                                                                                                                                                                                            13.8KV
                                                                                                                                                           230KV                             ES.2
                                                                                              380KV BUS.2                                                  TRAFO
                                                                                                                                       230KV                 DS        230KV
                                                                                                                                        CB2                             CB1
                                                                                                                                                                                                 13.8KV BUS
230KV ES.2
Figure-7 : Single Line Diagram of a one and half breaker scheme bay .
Similarly the line feeder can also be connected to the Bus by two methods:
              So we can see that three CBs are used to connect two feeders to the bus inside the substation. In
              other words , one and half CB per feeder is required in this arrangement. Hence it is called one and
              half circuit breaker scheme.
              It is to be noted that the general conditions for CB that are not related to switches e.g. All Lock out
              relays reset , Synchro check OK , CB spring charged , SF6 pressure normal,have not been mentioned
              here. It is assumed that the reader is familiar with these conditions.
For easy understanding, we will break down the single line diagram into 6 portions:
                    1-    The upper CB and its related disconnectors and earth switches or the ‘Upper portion’.
                    2-    The Transformer feeder.
                    3-    The middle CB and its related switches or the ‘Middle portion’.
                    4-    The line feeder.
                    5-    The lower CB and its related disconnectors and earth switches or the ‘lower portion’.
                    6-    Bus Section.
DS.1
ES.1
Upper CB
DS.2
ES.2
              As it is described in the previous section , the interlock of DS is with ES and CB. So logically the
              interlock of DS.1 should exist with all the earth switches and Circuit Breakers that are directly
              connected to DS.1.
              So the question arises that what is the reason to include ‘ ES.2 OPEN’ status in the interlock when
              the remaining statuses were enough to fulfill the interlock condition. The reason is that , every
              switch is provided with several auxiliary contacts (Normally open and Normally Closed). These
              contacts are used wherever the status of the switch is required in the scheme. An interlock circuit is
              one example. The switch and its auxiliary contacts are tested during the commissioning of the
              substation. However, the possibility cannot be over ruled that with the passage of time, there can be
              a slight chance of any one of the contacts of one switch to malfunction. The possibility is very less
              but it cannot be established that it will never happen.
              Now let’s consider that in the given case, one (52-B) auxiliary contact of Upper CB gets stuck in
              closed position. This means that its interpreting that the CB is Open. Now even if the CB is closed ,
              this particular contact is giving the status that the CB is open. So if the same faulty auxiliary contact
              is used in this DS.1 interlock, and the general rule is used to design interlock . i.e.
              Then DS.1 will be allowed to close only if ‘Bus ES’ and ‘ES.1 ‘are open regardless of CB status. It
              means that if CB is closed, and ES.2 is also closed , the system will think that CB is open and hence it
              will allow DS.1 to close the connect the live bus bar to earth. To cope with this kind of situation, the
              interlock is made more efficient by including ES.2 open status.
DS.3
ES.3=
ES.4=
              As we can see that the service condition interlock for DS.3 is including switches from 380kV GIS as
              well as 230kV GIS and 13.8kV switchgear. Lets break down the interlock into portions
DS.3 SERVICE=
(380kV)
There are 2 reasons for including the 230kV side and 13.8kV side in the interlocks.
                    1- If the disconnector on the HV side of transformer (DS.3) is closing , the interlock should not
                       only exist with the HV side earth switches but also the LV and tertiary (if tertiary winding is
                       available) side earth switches.
                    2- To avoid back energization. Or in other words , to define the direction of the load flow
                       through the transformer.
230 CB1 OPEN+230 CB2 OPEN+230 TRAFO ES1 OPEN+230 TIE ES2 OPEN
              (230 TRAFO ES1 OPEN + 230 TRAFO ES2 OPEN) is used for condition #1 described above. It is making
              sure that if the Transformer DS is going to close on the upper side, the earth switches on lower side
              are open.
              (230 CB1 OPEN+230 CB2 OPEN) is used for condition #2 described above. It is making sure that if the
              Transformer DS is going close on the upper side , the lower side is still open and hence the flow of
              load shall only be from upper side to lower side. If this condition was not included , there might be a
              possibility that if 230kV Bus Bar is already energized and the respective CB is closed. It can back
              energize the transformer.
              It should be noted that instead of using (230 CB1 OPEN+230 CB2 OPEN) , (230 TRAFO DS OPEN)
              could also be used to fulfill condition #2 for 230kV and avoid back energization. Hence we can see
              that a particular interlock condition can be achieved in more than one way.
The 13.8kV Earth switches and CB are also included for the same purpose as 230kV.
DS.4
ES.5=
MIDDLE CB
              SERVICE=DS4 CLOSE+ DS5 CLOSE +DS3 OPEN OR CLOSE+DS OPEN OR CLOSE +SYNCH CHECK
              OK+CLOSE BLOCK OK +CLOSE AUTH OK
DS.5
ES.6=
ES.7=
DS.6
ES.8=
              As we can see that the interlock of ES.8 is having some conditions that are different from the
              conditions of all other switches.This holds true for line earth switches and transformer earth
              switches. The interlock of Transformer feeder earth switch ES.4 in section 2.2.3 can be seen for
              reference.
Now let us analyze the condition for ES.8 earth switch operation.
              ‘DS.6 OPEN’ is the normal condition which is making sure that the Line ES should not be allowed to
              close if the Line DS is already close.But this condition is not enough to guarantee safe operation for
              ES.8. The reason is that if the Line is energized from the remote end side the ES should not be
              allowed to close in that case also as it will ground an energized line.For this purpose,An Under
              Voltage relay is provided in the control panel of every feeder and the second portion of the interlock
              is used to make sure that if the earth switch is going to close, it is a 100% safe operation to perform.
Now let us take a deeper look into the second part of the interlock equation.
              We can see that it can further be divided into 3 portions. We will discuss the purpose of each
              portion.
‘VT DS CLOSE’ :
              A safe operation of the line earthing switch is performed by making sure that the line is already de-
              energized or dead.For this purpose, on the local side we have already made sure that our line
              disconnector is open by including it in the interlock condition. But the remote end line disconnector
              is not available to us for using in the interlock.But if the line disconnector of the remote end is
              closed, It will supply voltage to our station which can be read by the Line VT of my Feeder as the VT
              is present after the Eathing switch.This voltage can then be used in the interlock.But in order for the
              line VT to sense the voltage, we have to make sure that the VT disconnector is already closed.And
              hence this condition has been added as the first portion of the interlock.
DS.7
ES.9=
LOWER CB
DS.8
ES.10=
                                                                          DS.11                                            DS.12
BUS-1A                                                                                                                                                                                       BUS-1B
                                                                                                 BS CB
                                                                                      VT-1B                                        VT-2B
       DS.1                                    DS.2                                                                                 DS                        DS.1                                    DS.2
                                                                                       DS
                                                       ES.2                                                                                                                                                  ES.2
ES.1                                                                                                                                                   ES.1
                            LINE                                                                                                                                                 TRAFO
                             CB                                                                                                                                                    CB
ES.3 ES.3
DS.3 DS.3
                                                                                                                                                                                           VT DS
                                   VT DS
          ES.4                                                                                                                                                         ES.4
115 KV
                                                                                                                                                                                 13.8 KV
                                            REMOTE END
                                            LINE ES
                                    REMOTE END
                                    LINE DS
                                                                                                                                                                13.8KV ES1
                                                                                                                                                                                  13.8KV
                                                                                                                                                                                    CB
13.8KV ES2
13.8KV BUS
              Consider ‘Figure-8’ above showing the single line diagram representation of a typical double bus
              single breaker system. All switches have been labelled for easy understanding. The same general
              rules for interlocking will be applied here also as it is in one and half breaker scheme.
              Like the one and half breaker scheme , the general conditions for CB that are not related to switches
              e.g. All Lock out relays reset , Synchro check OK , CB spring charged , SF6 pressure normal, have not
              been mentioned here also and it is assumed that the reader is familiar with these conditions.
              Mechanical interlocks are also not mentioned although one example is given in Line Feeder
              interlocks (ES.3) for understanding how mechanical interlocks work.
              As we can see that in double bus single breaker scheme , the bus section is also having a circuit
              breaker unline the one and half breaker scheme.Also for coupling of the two buses (for load transfer
              or load sharing purpose) , two bus couplers are available.
For easy understanding, we will break down the single line diagram into 5 portions:
                    1-    Line Feeder
                    2-    Transformer feeder.
                    3-    Bus Coupler -1
                    4-    Bus Section
                    5-    Bus Coupler-2
TEST = DS.1 OPEN + DS.2 OPEN + DS.3 OPEN + ALL LOR RESET
DS1:
SERVICE=ES.1 OPEN + ES.2 OPEN + ES.3 OPEN + ES.11 OPEN + DS.2 OPEN + CB OPEN
              BUS TRANSFER: CB CLOSE + DS.2 CLOSE + { BC1 SERVICE CLOSE* OR (BC2 SERVICE CLOSE*+ BS
              SERVICE CLOSE) } * Service close means Circuit breaker along with disconnectors on its both sides.
DS2:
SERVICE=ES.2 OPEN + ES.1 OPEN + ES.3 OPEN + ES.21 OPEN + DS.1 OPEN + CB OPEN
              BUS TRANSFER: CB CLOSE + DS.1 CLOSE + { BC1 SERVICE CLOSE* OR (BC2 SERVICE CLOSE*+ BS
              SERVICE CLOSE) } * Service close means Circuit breaker along with disconnectors on its both sides.
(LINE) DS.3 :
SERVICE = ES.1 OPEN + ES.2 OPEN + ES.3 OPEN + ES.4 OPEN + CB OPEN
ES.4:
              DS.3 OPEN+ ALL 3 PHASES UV RELAY PICKED UP + LINE PT DS & VT BOX MCB CLOSED + VT MCB FOR
              UV RELAY IN LCC PANEL ON
LINE VT DS:
              As it has already been discussed that the interlock of an earth switch exists with service position of
              CB. Now let us consider Figure-9 to analyze the portion of line feeder . To put the CB in service
              position for this feeder , we need to close ‘DS.1 OR DS.2’ on the upper side of CB and DS.3 on the
              lower side of CB.
                                                           DS.1
                                                                                     DS.2
                                                           ES.1
                                                                                       ES.2
CB
ES.3
DS.3
ES.4 VT DS
Figure-9 : Single line diagram of Line Feeder in Double Bus –Single Breaker arrangement
Hence according to the rules discussed above, the interlock of ES.3 should be as followes.
              The reason for not mentioning DS.3 is that sometimes in GIS , the disconnector and earth switch
              come as one unit that are mechanically interlocked with each other. In this case , the ES can not be
              closed unless the DS of the same DS/ES unit is open. Hence the interlock of ES.3 in this particular
              case exists with DS.3 also but as it is a mechanical interlock so it is not available in the electrical
              interlocks.And hence not mentioned in Interlock equation also on purpose.
              It is to be mentioned here that when reviewing a GIS interlocking scheme , you may face a similar
              situation where you may not be able to find a necessary interlock in the electrical ciruit.In this case it
              has to be verified that the mechanical interlock exists before establishing that the scheme is having
              an error.
              It should also be considered that , depending on the GIS model and manufacturer, the same DS.3
              and ES.3 may not be present as a signle unit in some GIS and in that case the electrical interlock for
              DS.3 will be included for ES.3
TEST = DS.1 OPEN + DS.2 OPEN + DS.3 OPEN + ALL LOR RESET
DS1:
SERVICE= ES.1 OPEN + ES.2 OPEN + ES.3 OPEN + ES.12 OPEN + DS.2 OPEN + CB OPEN
              BUS TRANSFER: CB CLOSE + DS.2 CLOSE + { BC2 SERVICE CLOSE OR (BC1 SERVICE CLOSE+ BS SERVICE
              CLOSE) }
DS2:
SERVICE= ES.2 OPEN + ES.1 OPEN + ES.3 OPEN + ES.22 OPEN + DS.1 OPEN + CB OPEN
              BUS TRANSFER: CB CLOSE + DS.1 CLOSE + { BC2 SERVICE CLOSE OR (BC1 SERVICE CLOSE+ BS SERVICE
              CLOSE) }
DS.3 :
SERVICE = ES.1 OPEN + ES.2 OPEN + ES.3 OPEN + ES.4 OPEN + CB OPEN+ LV SIDE ES OPEN
ES.3:
ES.4:
              DS.3 OPEN+ ALL 3 PHASES UV RELAY PICKED UP + LINE PT DS & VT BOX MCB CLOSED + VT MCB FOR
              UV RELAY IN LCC PANEL ON
TRAFO VT DS:
DS.1:
BUS.1 ES OPEN
              DS.1 OPEN + BUS SEC DS.1 OPEN + ALL 3 PHASE UV + BUS PT DS CLOSE + ALL BUS-1 FEEDERS DS
              OPEN + ES KEY ENABLE + PT BOX MCB CLOSE + LCC MCB GOING TO UV RELAY CLOSE.
DS.1:
INNER ES.1
OTHER DS OPEN