Installation Check List: No. Description Installation Before After

This document is an installation checklist for a FAT (fiber access terminal) with 6 sections to check both before and after installation. Section 1 checks the outer appearance of the FAT, section 2 checks the inner condition with the cover open, section 3 checks the inner condition with the upper compartment open, section 4 checks how the cables are secured to the pole, and sections 1-4 contain subpoints to verify specific installation criteria. The checklist is to be checked and signed off on by an installer to confirm the FAT meets specifications both before and after installation.

Uploaded by

Aung Thein Oo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
152 views1 page

Installation Check List: No. Description Installation Before After

This document is an installation checklist for a FAT (fiber access terminal) with 6 sections to check both before and after installation. Section 1 checks the outer appearance of the FAT, section 2 checks the inner condition with the cover open, section 3 checks the inner condition with the upper compartment open, section 4 checks how the cables are secured to the pole, and sections 1-4 contain subpoints to verify specific installation criteria. The checklist is to be checked and signed off on by an installer to confirm the FAT meets specifications both before and after installation.

Uploaded by

Aung Thein Oo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Installation Check List

Installation
No. Description
Before After
1 FAT Outer Appearance OK/NG OK/NG
1.1 Verify FAT has be fixed properly. OK/NG OK/NG
1.2 Verify FAT cover is closed properly. OK/NG OK/NG
1.3 Verify FAT is locked properly. OK/NG OK/NG

2 FAT Inner Condition 1(open the FAT cover) OK/NG OK/NG


2.1 Verify FAT has NO water leakage. OK/NG OK/NG
2.2 Verify FAT has NO instrusion of insects. OK/NG OK/NG
Verify FAT accessories have been completely equipped
2.3 (all cable pluh, seal, grip, screw are fixed properly). OK/NG OK/NG
2.4 Verify all drop cables are istalled following specification. OK/NG OK/NG
2.5 Verify proposed port is vacant (can be used). OK/NG OK/NG
2.6 Verify all connectors are fixed properly. OK/NG OK/NG

3 FAT Inner Condiction 2 (open the upper compartment) OK/NG OK/NG


3.1 Verify all cables are installed following specification. OK/NG OK/NG
3.2 Verify all cables are tied properly at drop cable holder. OK/NG OK/NG
3.3 Verify all cables are coiled inside coil holder. OK/NG OK/NG
3.4 Verify all protection sleeves are fixed properly in sleeve holder. OK/NG OK/NG
3.5 Verify all cables are in good condition (NO cut or sharp bend) OK/NG OK/NG

4 Secure the cable on the pole OK/NG OK/NG


4.1 Verify all cables pass through inside the PVC OK/NG OK/NG
4.2 Verify all cables have 1m length for fusion splicing on the ground. OK/NG OK/NG
Verify guy hook have been installed on the pole with stainless steel
4.3 strapping band and buckle. OK/NG OK/NG
4.4 Verify messenger wire have been fixed into tension clamp properly. OK/NG OK/NG
4.5 Verify all cables are coiled 6inches radious together in a group. OK/NG OK/NG
4.6 Verify cable is properly used entry way to house. OK/NG OK/NG