100% found this document useful (1 vote)
6K views6 pages

TNB - Borang Map A, B & C-Klinik

The document provides details for a proposed electrical load exceeding 100kVA for a new Type 6 Health Clinic with quarters development in Felda Bersia Hulu Perak, Perak. Key details include the address, site location, premise type, total land area, names of relevant parties such as architect and owner. Load details specify a total connected load of 222.54kW and maximum demand of 88.4kW. Plans submitted include the site plan, main switch room layout, single line diagram and front building elevation. Motor load details and estimated monthly consumption are also included.

Uploaded by

bond
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
6K views6 pages

TNB - Borang Map A, B & C-Klinik

The document provides details for a proposed electrical load exceeding 100kVA for a new Type 6 Health Clinic with quarters development in Felda Bersia Hulu Perak, Perak. Key details include the address, site location, premise type, total land area, names of relevant parties such as architect and owner. Load details specify a total connected load of 222.54kW and maximum demand of 88.4kW. Plans submitted include the site plan, main switch room layout, single line diagram and front building elevation. Motor load details and estimated monthly consumption are also included.

Uploaded by

bond
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

SUMMARY OF LOAD FOR DEMAND EXCEEDING 100kVA (~140A)

A. BASIC INFORMATION
1 Address Of Installation CADANGAN MEMBINA KLINIK KESIHATAN (JENIS 6) DENGAN KUARTERS
(2F/2G) FELDA BERSIA HULU PERAK, PERAK DARUL RIDZUAN
2 Site Location (Lot & Mk. No.)
3 Single-Tenancy or Multi-Tenanted Premise SINGLE TENANCY
4 Type Of Premise KLINIK KESIHATAN JENIS 6

5 Total Gross Built-In Floor Area


6 Total Land Area 10.21ek
7 Name Of Architect ARKITEK PENGUASA
Address
TINGKAT 4,
JABATAN KERJA RAYA PERAK DARUL RIDZUAN,
JALAN PANGLIMA BUKIT GANTANG WAHAB,
30000 IPOH, PERAK

Telephone No. 05-2534041


Fax No. 05-2537397
E-mail Address
8 Name Of Surveyor JURUUKUR BAHAN PENGUASA
Address
KONTRAK & UKUR BAHAN,
JABATAN KERJA RAYA PERAK DARUL RIDZUAN,
JALAN PANGLIMA BUKIT GANTANG WAHAB,
30000 IPOH, PERAK

Telephone No. 05-2534041


Fax No. 05-2537397
E-mail Address
9 Name Of Owner / Developer PENGARAH
Address JABATAN KERJA RAYA PERAK DARUL RIDZUAN,
JALAN PANGLIMA BUKIT GANTANG WAHAB,
30000 IPOH, PERAK

Telephone No. 05-2534041


Fax No. 05-2537397
E-mail Address
10 Name Of Consultant Engineer KETUA JURUTERA ELEKTRIK NEGERI
Address CAWANGAN KEJURUTERAAN ELEKTRIK JKR PERAK,
LORONG LAHAT, KAMPUNG TEMIANG,
31650 IPOH,
PERAK DARUL RIDZUAN.

Telephone No. 05-3211615


Fax No. 05-3214942
E-mail Address
11 Name Of Electrical Contractor
Address
Telephone No.
Fax No.
E-mail Address
12 Requirements For Temporary Supply MD (kW): Date Supply Required:
Voltage (V)
13 Date Supply Required (ORIGINAL) MD (kW): 88.40KW Date Supply Required: OKTOBER2019
14 Date Supply Required (FINAL) MD (kW): Date Supply Required:
15 PLANS* CERTIFIED BY PROFESSIONAL ENGINEER 3 SETS :
(Please Specify Plan No. & Date Below)
15a Master Development Plan / Layout Plan Plan No. : Date:
(Pelan Induk Lokasi & Lot Pembangunan Tanah)
Approved By JPB&D
15b Site Plan / Proposed Sub-Station Sites Plan No. : Date:
(Pelan Lokasi & Cadangan Tapak Pencawang PKR.PK(A)(94)1648 OKTOBER 2016
Elektrik Fasa)
15c Layout Plan Of Sub-Station Building Plan No. : Date:
(Stand-Alone / Compartment)
Pelan Susunatur (Layout) Bangunan Pencawang
15d Layout Plan of Main Switch Rooms Plan No. : Date:
(Pelan Bilik Suis & Skematik Papan Suis Pengguna) PKR.PK(E)46/2016-E077a/15(PINDAAN 1) MAC 2018
15e Single Line Diagram / Schematic Of Installation Plan No. : Date:
(Pelan Skematik Pepasangan)
16 Front Elevation Of Building Requiring Supply

*NOTES :
(i)
The Master Development / Layout Plans (15a) are approved by Local Authority / Jabatan Perancang bandar & Desa / Jabatan Tanah & Galian
These Plans should already contain TNB preliminary comments on sub-station and right of way / wayleave requirement, as the case may be
(ii) The Site Plans / Proposed Sub-Stations Sites (15b) indicate the locations of sub-station sites for the overall development area
(iii)
The Layout Plans of sub-station building (15c) must show the cable entry locations, trenching and ducting details according to TNB specifications
(iv) Layout Plan of Main Switch Room (15d) must indicate the location of MSB, trenching / ducting details for cable entry
(v) The Wiring Diagrams should indicate incoming switches, metering location and devices, protection schemes and device, bus-bar and switchgear
rating
(vi) All drawings and plans are to be submitted in three (3) complete sets. Soft copies in ACAD also preferable
B. LOAD DETAILS
Load After Coincident kW @
Connected Load Information
Load Category Coincident Factor
Nos. kVA Power Factor kW

Total Lighting Points and Load (kW)


Total Air-Conditioning Points and
Load (kW)

Total Motor Nos. and Load


- Single Phase
-Three Phase

Other Special Loads


(Arc Welding, Ar, Arc Furnace &
Others)
1.
2.
3.
4.
5.
Total Load (kW) 222.54 KW 88.40 KW
- Maximum
Total (kW)
- Minimum
* Minimum values need to be specified for customer taking supply at above 6.6kV
C. BUTIRAN KEPERLUAN JANGKA

NO. PROJEK PKR.PK(E)46/2016 Jld.3

TAJUK PROJEK PEMASANGAN ELEKTRIK UNTUK KLINIK KESIHATAN (JENIS 6) DENGAN KUARTERS (2F/2G) FELDA BERSIA, DAERAH HULU PERAK, PERAK DARUL RIDZUAN

KATEGORI PELANGGAN VOLTAN BEKALAN <6.6kV VOLTAN BEKALAN >6.6kV

DOMESTIK 1 FASA DOMESTIK 3 FASA M/TENANT COMPLEX CATATAN


KOMERSIL /
JENIS PELANGGAN KOMERSIL INDUSTRI
KOS RENDAH <RM KABEL INDUSTRI
25,000 > RM 25,000 T/ATAS (O/H) (U/G CABLE) OWNER TENANT

JUMLAH BILANGAN JANGKA


1
PELANGGAN

KEHENDAK MAKSIMA (kW) 88.4


(bagi setiap unit pelanggan)

SAIZ C.T. 300/5A


D. LOAD PROFILE AND CONSUMPTION DATA, if relevant:-

ESTIMATED MONTHLY
MONTHLY PEAK MD MONTHLY CONSUMPTION
LOAD FACTOR CONSUMPTION
(Kw) (hours / month)
(kWh)
E. DETAILS ON MOTOR LOADS

STARTING STARTING
TYPE OF CONTROL SUB-TRANSIENT REACTANCE / POWER UNDER VOLTAGE
MOTOR SIZE EQUIPMENT LOACKED ROTOR REACTANCE CURRENT FREQUENCY FACTOR SETTING
(A) (nos/hour)

You might also like