El Mareefa Project

The Scheduling/Leveling Report for the Grand Hospital Project (L-1) indicates that there are 256 activities, with 183 not started, 26 in progress, and 47 completed. There are several warnings including activities without predecessors and successors, as well as out-of-sequence activities. The report highlights 8 critical activities and confirms that scheduling settings allow for automatic updates and the use of expected finish dates.

Uploaded by

Fadi Eshak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as TXT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views2 pages

El Mareefa Project

The Scheduling/Leveling Report for the Grand Hospital Project (L-1) indicates that there are 256 activities, with 183 not started, 26 in progress, and 47 completed. There are several warnings including activities without predecessors and successors, as well as out-of-sequence activities. The report highlights 8 critical activities and confirms that scheduling settings allow for automatic updates and the use of expected finish dates.

Uploaded by

Fadi Eshak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as TXT, PDF, TXT or read online on Scribd
You are on page 1/ 2

Scheduling/Leveling Report - 2021-08-21 11:59:01 - PM.

exe
=========================================================

Default Project..................................................L-1

Projects:
L-1............................................................Grand
Hospital Project baseline

Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............Yes
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar

Advanced
--------
Calculate multiple float paths...................................No

Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................256
# Not Started....................................................183
# In Progress....................................................26
# Completed......................................................47
# Relationships..................................................355
# Activities with Constraint.....................................0

Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Project: L-1 Activity: A1000 Receiving Advanced Payment

Activities without successors....................................1


Project: L-1 Activity: A1020 Project Finish

Out-of-sequence activities.......................................6
Project: L-1 Activity: A1870 Install duct c/w volume damper
Project: L-1 Activity: A1880 Install duct insulation
Project: L-1 Activity: A1890 Install DX Split Unit
Project: L-1 Activity: A3010 Install duct c/w volume damper
Project: L-1 Activity: A3030 Install DX Split Unit
Project: L-1 Activity: A4890 Submit Duct Insulation MIR For
Approval

Activities with Actual Dates > Data Date.........................0

Milestone Activities with invalid relationships..................0

Finish milestone and predecessors have different calendars.......0

Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................256
# Relationships with other projects..............................0
Data Date........................................................12-Dec-20
Earliest Early Start Date........................................12-Dec-20
Latest Early Finish Date.........................................18-Feb-21
Exceptions:
-----------
Critical Activities..............................................8
Project: L-1 Activity: A1020 Project Finish
Project: L-1 Activity: A1150 Testing & Comissioning
Project: L-1 Activity: A1180 Project Hand Over
Project: L-1 Activity: A3840 Submit Fire Pump System
(Electerical & Jockey) Submittal For Approval
Project: L-1 Activity: A4070 Reciving Fire Pump System
(Electerical & Jockey) Submittal Approval
Project: L-1 Activity: A4350 Install Fire Pump
Project: L-1 Activity: A4560 Submit Fire Pump System
(Electerical & Jockey) MIR For Approval
Project: L-1 Activity: A4770 Reciving Fire Pump System
(Electerical & Jockey) MIR Approval

Activities with unsatisfied constraints..........................0

Activities with unsatisfied relationships........................0

Activities with external dates...................................0