Scheduling/Leveling Report - 2021-08-21 11:59:01 - PM.
exe
=========================================================
     Default Project..................................................L-1
      Projects:
            L-1............................................................Grand
Hospital Project baseline
Scheduling/Leveling Settings:
-----------------------------
      General
      -------
      Scheduling ......................................................Yes
      Leveling ........................................................No
      Ignore relationships to and from other projects .................No
      Make open-ended activities critical .............................No
      Use Expected Finish Dates .......................................Yes
      Schedule automatically when a change affects dates ..............Yes
      Level resources during scheduling ...............................No
      Recalculate assignment costs after scheduling ...................No
      When scheduling progressed activities use .......................Retained
Logic
      Calculate start-to-start lag from ...............................Early Start
      Define critical activities as Total Float less than or equal to .0
      Compute Total Float As ..........................................Finish Float
      Calculate float based on finish date of .........................Each project
      Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar
     Advanced
     --------
     Calculate multiple float paths...................................No
Statistics:
-----------
      # Projects.......................................................1
      # Activities.....................................................256
      # Not Started....................................................183
      # In Progress....................................................26
      # Completed......................................................47
      # Relationships..................................................355
      # Activities with Constraint.....................................0
Errors:
-------
Warnings:
---------
      Activities without predecessors..................................1
            Project:    L-1   Activity:  A1000 Receiving Advanced Payment
     Activities without successors....................................1
           Project:    L-1   Activity:  A1020 Project Finish
     Out-of-sequence activities.......................................6
           Project:    L-1   Activity:  A1870 Install duct c/w volume damper
           Project:    L-1   Activity:  A1880 Install duct insulation
           Project:    L-1   Activity:  A1890 Install DX Split Unit
           Project:    L-1   Activity:  A3010 Install duct c/w volume damper
           Project:    L-1   Activity:   A3030 Install DX Split Unit
           Project:    L-1   Activity:   A4890 Submit Duct Insulation MIR For
Approval
     Activities with Actual Dates > Data Date.........................0
     Milestone Activities with invalid relationships..................0
     Finish milestone and predecessors have different calendars.......0
Scheduling/Leveling Results:
----------------------------
      # Projects Scheduled/Leveled.....................................1
      # Activities Scheduled/Leveled...................................256
      # Relationships with other projects..............................0
      Data Date........................................................12-Dec-20
      Earliest Early Start Date........................................12-Dec-20
      Latest Early Finish Date.........................................18-Feb-21
Exceptions:
-----------
      Critical Activities..............................................8
            Project:    L-1   Activity:   A1020 Project Finish
            Project:    L-1   Activity:   A1150 Testing & Comissioning
            Project:    L-1   Activity:   A1180 Project Hand Over
            Project:    L-1   Activity:   A3840 Submit Fire Pump System
(Electerical & Jockey) Submittal For Approval
            Project:    L-1   Activity:   A4070 Reciving Fire Pump System
(Electerical & Jockey) Submittal Approval
            Project:    L-1   Activity:   A4350 Install Fire Pump
            Project:    L-1   Activity:   A4560 Submit Fire Pump System
(Electerical & Jockey) MIR For Approval
            Project:    L-1   Activity:   A4770 Reciving Fire Pump System
(Electerical & Jockey) MIR Approval
     Activities with unsatisfied constraints..........................0
     Activities with unsatisfied relationships........................0
     Activities with external dates...................................0