Implementation Timelines and Estimates Week1 Week2 Week3 Week4
Starting Week Day 30-Dec-21 6-Jan-22 13-Jan-22 20-Jan-22
During this phase some of the resources will work with
client’s (from onsite) to determine the exact software and
business requirements. This will be mainly achieved through Requirement
Requirement Gathering
Gathering
workshops and meetings.
In this phase, actual configuration and coding will take place,
based on the requirements received from earlier phase. Most
of these activities will be handled by technical team from Configuration
Configuration &
& Customisations
Customisations
offshore.
During this phase, the developed software and code will be
tested to see if there are any bugs (Issues). The bugs will be
identified and fixed.
The application will be installed at the client premise and the
client will start working on the developed software. Any
issues identified by the clients need to be fixed and tested.
ONSITE Resources
Business Consultant
Consultant
Technical Lead
Onsite total Effort 0 0 0 0
OFFSHORE Resources
Associate Consultants
Software Engineers
Testing Engineer
Offshore Total Effort 0 0 0 0
Total Efforts(Onsite+Offshore) 0 0 0 0
Software License Fees 25000 Pounds
Direct Expenses 6000 Pounds
Airfare 3000
Hotel Expenses 3000
Total project cost= 31000 GBP
Week5 Week6 Week7 Week8
27-Jan-22 3-Feb-22 10-Feb-22 17-Feb-22 End Date-18 Feb
ation
ation &
& Customisations
Customisations
Testing
Testing
Go-Live
Go-Live
Efforts Efforts
(In Person (In person Billing Rate Total
Weeks) Days) Pounds/Day (In Pounds)
0 0 832 0
0 0 525 0
0 0 410 0
0 0 0 0 0 0 0
0 0 250 0
0 0 200 0
0 0 138 0
0 0 0 0 0 0 0
0 0 0 0 0 TOTAL 0