LOT#3 Equipment Equipment Name FAT Tests SAT Tests

The document lists equipment for LOT#3 and the factory acceptance tests (FAT) and site acceptance tests (SAT) required for each item. Key equipment includes main runners and spares, stator assemblies, stator coils and bars, generator rotors, poles and accessories, turbine shafts, oil tanks and accessories, and speed sensing devices. FATs include tests such as balancing, material analysis, insulation testing, pressure testing, and dimensional verification. SATs focus on functional testing after installation at the site.

Uploaded by

Muhammad Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views2 pages

LOT#3 Equipment Equipment Name FAT Tests SAT Tests

The document lists equipment for LOT#3 and the factory acceptance tests (FAT) and site acceptance tests (SAT) required for each item. Key equipment includes main runners and spares, stator assemblies, stator coils and bars, generator rotors, poles and accessories, turbine shafts, oil tanks and accessories, and speed sensing devices. FATs include tests such as balancing, material analysis, insulation testing, pressure testing, and dimensional verification. SATs focus on functional testing after installation at the site.

Uploaded by

Muhammad Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

LOT#3 Equipment

Equipment Name FAT Tests SAT Tests


Main Runners with 1. Static Balancing and
Spares (03 Nos) MPI of Runners
2. Surface Defects (DPT)
3. UT of runner crown
4. Radiographic Testing
5. Surface Roughness
6. Dimensional Inspection
7. Pressure Tests of head
cover and bottom
cover
8. Steel lamination test
(spiral case and stay
vanes)
9. Material tests and
chemical analysis of
steel
10. Functional Tests
Stator Assembly of 1. Magnetization
Unit#03 2. Stator Core Loss Test
3. Insulation Resistance
Test of Stator
(absorption ratio and
polarization coefficient)
4. DC withstand Voltage
test, leakage test
5. Power Frequency AC
withstand voltage test
Stator Coils & Bars for 1. Dielectric Test
Unit#1 & Unit#2 2. Partial Discharge
Measurement Test
Generator Rotors with 1. NDT of Rotor shaft and
Accessories (03 Nos) shaft coupling bolts
2. Mechanical Tests
3. Cold state DC
resistance test
4. Insulation Resistance
Test
5. Power Frequency AC
withstand voltage test
Poles and Accessories 1. Dielectric Test
for all Units 2. IR Test
Turbine Shaft with 1. Dimensional
Tools of all 3 Units verification
2. Shaft Runout
3. Surface examination
on axial bore.
4. UT
5. Seal Test
Oil Tank and 1. Dimensional
Accessories verification.
2. Leakage check of oil
tank.
3. UT/RT
4. Pressure tests (oil
accumulators)
5. Accessories Functional
tests.
Speed Sensing Devices 1. Functional Tests
and Electrical Cubicles 2. Routine Tests