PROJECT MANAGEMENT
MANUAL
PMO-MANUAL
Prepared by:
Reviewed by:
Manual Version: 01
Aug 02, 2022
                                                                          CONTENTS
           Preface...................................................................................................................................................5
           Chapter 1: Project Conceptualization.............................................................................................6
               Survey & Feasibility study.............................................................................................................6
                  The purpose of feasibility studies is to..................................................................................7
               Defining Stake Holders (Engineering Consultant, Consultant for the project Wetting
               Subsidiary etc.................................................................................................................................7
                  A stakeholder map might assess:...........................................................................................8
               SWOT Analysis / Pre-bid Risk Review.........................................................................................9
                  Strength, Weakness, Opportunity, and Threat (SWOT) Analysis.....................................9
               Preparation for detail Project Report (DPR).............................................................................10
                  Contents of a detailed project report.....................................................................................10
               Financial arrangement.................................................................................................................10
               Permissions (if required)............................................................................................................10
           Chapter 2: Project Initiation...........................................................................................................12
               Project Award from BD to Execution Team...............................................................................12
               Organogram / Team Building.....................................................................................................12
                  SOP............................................................................................................................................12
                  PFD............................................................................................................................................13
               Land & Land Development..........................................................................................................14
               Site Development / Site Mobilization.........................................................................................14
           Chapter 3: Project Execution..........................................................................................................15
               Engineering...................................................................................................................................15
               Procurement.................................................................................................................................15
               Supplier Tracking.........................................................................................................................17
PAGE 3 OF 31
               Civil Construction.........................................................................................................................19
               Erection/Installation (Mech/Elec/C & I) Including availing Permanent Power....................20
                  SOP............................................................................................................................................20
                  Process Flow Diagram (PFD)..................................................................................................21
                  Checklist....................................................................................................................................22
               Commissioning & Trial run.........................................................................................................23
                  SOP:...........................................................................................................................................23
                  Process Flow Diagram (PFD) :................................................................................................24
                  Checklist:...................................................................................................................................26
               Client Invoicing.............................................................................................................................26
               Quality...........................................................................................................................................27
               Vendor/Contractor Billing..........................................................................................................27
                  SOP............................................................................................................................................27
                  PFD............................................................................................................................................28
                  Checklist :..................................................................................................................................28
           Chapter4 : Project Closure...............................................................................................................30
               Technical Closure.........................................................................................................................30
               Commercial Closure.....................................................................................................................30
PAGE 4 OF 31
                                                PREFACE
           The main objectives of this Project Management Handbook are to raise understanding
           regarding project management and provide an adaptable guidance for complete project
           Life cycle.
           The project management life cycle consists of four steps: initiating, planning, executing,
           and closing.
           By setting the practical guidance and clear figures for project management, the Project
           Management Handbook can increase the efficiency and quality of project management
           and helps to manage projects effectively.
           Effective project management ensures that the organization is focused and that the right
           work is done correctly and in the most time and cost-effective manner. Communication is
           managed effectively, and specific quality matrix been achieved.
           Project Management Handbook emphasizes what project management is and why it
           exists by defining project management and, later, setting out a selection of project
           management approaches.
           It facilitates project management from a wider perspective and defines a set of approaches
           and concepts to support future projects and the delivery of day-to-day project
           management work.
PAGE 5 OF 31
                       CHAPTER 1: PROJECT CONCEPTUALIZATION
           The project conceptualization phase of the project delivery process is intended
           to give sufficient definition to a proposed project so that a reliable budget
           estimate can be made.
           ……………………………………………..
           Survey & Feasibility study
           Feasibility studies are preliminary studies undertaken in the very early stage of a project.
           They tend to be carried out when a project is large or complex, or where there is some doubt
           or controversy regarding the proposed development. If an environmental impact
           assessment (EIA) is required, this may involve assessments best undertaken as part of
           feasibility studies.
           The purpose of feasibility studies is to
                 i.    Establish whether the project is viable.
                ii.    Help identify feasible options.
               iii.    Assist in the development of other project documentation such as the business
                         case, project execution plan and strategic brief.
           On large or complex projects, there may be a number of different feasibility studies carried
           out, sometimes requiring different skills, and considering issues such as:
                       Planning permission.
                       The likelihood that an environmental impact assessment will be required.
                       Other legal/statutory approvals.
                       Analysis of the budget relative to client requirements.
                       Assessment of the potential to re-use existing facilities or doing nothing      rather
                         than building new facilities.
                       Assessment of any site information provided by the client.
                       Site appraisals, including geotechnical studies, assessment of     any contamination,
                          availability   of services,    uses    of   adjoining land, easements and restrictive
                          covenants, environmental impact, and so on.
                       Considering different solutions to accessing potential sites.
                       Analysis of accommodation that might be included or excluded.
                       Assessment of     the possible juxtaposition of accommodation and preparing
                          basic stacking diagrams.
                       Assessing operational and maintenance issues.
                       Appraisal of servicing strategies.
PAGE 6 OF 31
                   Programmed considerations.
                   Procurement options.
           Defining Stake Holders (Engineering Consultant, Consultant for the project Wetting Subsidiary etc.)
           The term 'stakeholder' refers to anyone that has an interest in a project and can influence its
           success.
           It is important to identify stakeholders in a project as early as possible. They may include the
           following.
                   Members of the client organization (such as user panels, champions and
                      department heads).
                   Other user groups (such as customers, residents, occupants, and visitors).
                   Funders and shareholders.
                   The local authority building regulations, licensing and planning departments.
                   Other statutory authorities and non-statutory consultees.
                   Special interest groups such as heritage organizations and environmental bodies.
                   Suppliers.
                   The emergency services.
                   Statutory undertakers (utilities companies).
                   Insurance and warranty providers.
                   investors
           Stakeholders may not all have the same objectives. It is important therefore to
           identify areas of convergence and areas of difference between them and to manage
           individuals whose expectations are unlikely to be met.
           A first step in considering how to interact with stakeholders can be the preparation of
           a stakeholder map or stakeholder matrix e.g.  A Rough Guide to Stakeholder Mapping
           A stakeholder map might assess:
                   The likely impact of the development on the stakeholder.
                   The issues that they will have an interest in.
                   Their likely position.
                   Their ability to influence the development.
                   Their potential impact on the project.
                   Potential mitigating actions.
           A stakeholder map allows a plan to be developed for how to manage the involvement of
           different stakeholder groups. Clearly, a stakeholder that the project will significantly impact upon, who has a
PAGE 7 OF 31
           strong ability to influence the development and is likely to be against it, will require a great deal of attention.
           This may result in the preparation of a stakeholder management
           plan outlining strategies for stakeholder communication and consultation.
           Where the intention is to involve stakeholders in the development of the project, they should be involved early
           on to allow them to influence key stages such as brief development, rather than just allowing them to comment
           on designs after they have been completed (see the article consultation process for more information).
           Stakeholders can provide useful feedback (and an indication of the likely response to a subsequent planning
           application), however, as they may not be experienced in building projects, and their actions may be beyond the
           control of the client, their involvement requires careful organization, and a clearly understood mandate. Large
           or complex projects may benefit from a professional third-party facilitator to ensure
           that stakeholder involvement is properly managed.
           A variety of communicating methods can be used to help stakeholders properly understand the project (such
           as 3D visualizations), and a variety of consultation methods can be adopted:
                    One to one consultations.
                    Meetings.
                    Focus groups.
                    Questionnaires.
                    Exhibitions and open-days.
                    Workshops.
                    Websites.
                    Printed materials.
                    The use of specialist toolkits and games.
           Stakeholder management should be an ongoing process not a one-off event, and the stakeholder
           map and management plan may need to be updated throughout the life of the project.
           SWOT Analysis / Pre-bid Risk Review
           Strength, Weakness, Opportunity, and Threat (SWOT) Analysis
                  What Is SWOT Analysis?
                  How to Do a SWOT Analysis
                  How to Use a SWOT Analysis
                  SWOT Analysis Example
                  Frequently Asked Questions About SWOT Analysis
                  The Bottom Line
PAGE 8 OF 31
                              Strength                                       Weakness
                                                       SWOT
                           Opportunity                                          Threat
           Preparation for detail Project Report (DPR)
           A detailed project report is extremely important in order to turn the idea of your project into a reality.
           A DPR acts as a ladder towards success to make your project reach great heights. If the project report is
           prepared by putting a tremendous amount of effort into details, you will surely get good results later.
           Contents of a detailed project report
            A detailed project report must include the following information:
              Brief information about the project
              Experience and skills of the people involved in the promotion of the project
              Details and practical results of the industrial concerns of the promoters of the project
              Project finance and sources of financing
              Government approvals
              Raw material requirement
              Details of the requisite securities to be given to various financial organizations
              Other important details of the proffered project idea include information about
                management teams for the project, details about the building, plant, machinery, etc.
           Financial arrangement
           Project finance is the funding (financing) of long-term infrastructure, industrial projects,
           and public services using a non-recourse or limited recourse financial structure. The debt
           and equity used to finance the project are paid back from the cash flow generated by the
           project.
           Project financing is a loan structure that relies primarily on the project's cash flow for
           repayment, with the project's assets, rights, and interests held as secondary collateral.
           Project finance is especially attractive to the private sector because companies can fund
           major projects off-balance sheet (OBS).
PAGE 9 OF 31
           Permissions (if required)
           Statutory & Legal Compliance
                           Environment Permissions
                           CTE, PVC & Plan Approval
                           Utilities (For Construction Purpose)
                           ROW Permissions
                           Other Permissions
                                    i)
                                   ii)    EPF and ESIC Act 1952 & 1948
                                  iii)    Insurance act
                                  iv)     Labor act
                                   v)     Fire & Safety
                                  vi)     Factory Act
                           a) I-DPR
PAGE 10 OF 31
                       CHAPTER 2: PROJECT INITIATION
           Project Award from BD to Execution Team
           Organogram / Team Building
                 An organogram is a graphical representation of an organization’s structure. It’s
                 used to show hierarchical relationships between managers and the people who
                 report to them, as well as departments. An organogram is a useful tool for
                 organizations to both visualize reporting relationships and communicate
                 employees’ names, skills, and contact information.
           SOP
                 Points to be considered while preparing organogram and team building.
                    a) Purpose: -
                       To provide a standard operating procedure for defining Role and Responsibilities of
                       employees in an organization and Departmental Organogram.
                    b) Scope: -
                       The scope of this SOP is applicable defining Role and Responsibilities of employees in
                       all the departments as well as preparation of departmental organogram at [company
                       name].
                    c) Responsibility:
                       Head of Departments:
                       To prepare an organogram for the department as per hierarchical structure.
                       To issue a job responsibility for the work to be assigned to the employee.
                       Employee:
                       To read and understood the job responsibility and accept it. To ensure that training with
                       respect to assigned role is completed before accepting the job responsibility.
                       Human Resource (HR) Department:
                       Approved Job responsibilities of all the employee shall be maintained by HR
                       department in respective employee files.
                       Definitions:
                       Job responsibility or Job description: A job responsibility is a description of
                       duties and tasks to be performed during job role assigned by employer or within
                       the department
           PFD
PAGE 11 OF 31
                                                             Organization chart
                                                                        CMD
                                                                        CEO
                                                               COO
                                                                                            Procuremen
                    PMO                    HR/Admin                         Execution                     Engineering   Audit
                                                                                                 t
                   Planning
                                   Asst. Admin    Asst. HR     Project GM               PR manager
                     Head
                          Sr. Planning
        Planning           Engineer                             Project          Store          Account
        Managrer                                                manager         manager         manager
                              Finance
                                                              Constructio
                                                              n Manager
                                                    Civil      Electrical      Mechanical
                                                  Engineer     Engineer         Engineer
           Land & Land Development
PAGE 12 OF 31
                         i)      Land Procurement
                        ii)    Authority Permission (if any)
                       iii)    PVC (Plot Validation Certificate)
                       iv)     Zoning Certificate
                        v)     Distance Certification
                       vi)     Plan Approval
           Site Development / Site Mobilization
                          i)   Topography Survey & Soil Testing
                         ii)   Area Grading
                       iii)    Fencing / Boundary Wall / Temporary Gates
                        iv)    Construction Power with Internal Networking
                         v)    Construction Water
                        vi)    Temporary Site Office (Porta Cabin / Security Office etc.)
                       vii)    IT related Development
                      viii)    Store Development
                        ix)    Green Area Development
                         x)    Approach Road & Drainage Development
                        xi)    Health & Safety Procurement
                          i)      Insurance (EAR & CAR marine cum transit)
PAGE 13 OF 31
                          CHAPTER 3: PROJECT EXECUTION
           Engineering
                ii) Basic Engineering
                iii) Management of Engineering Deliverables
                iv) Monitoring Scope variation
           Procurement
                v) Civil Contractor
PAGE 14 OF 31
                PFD:
                                                  Tendering
                                              Complete Purchase
                                               Requisition Form
                                              Submit for Approval
                       Amend Order to Meet
                         Requirements        No                     Approved
                                                             Submit Approved
                                                           Purchase Requisition
                                                           form to accounting &
                                                          Request Purchase Order
                                                           Recieve Purchase Order
                                                                     Contact Vendor and
                                                                     give Purchase order
PAGE 15 OF 31
                     vi) E & M Vendor
                     vii)Misc. Vendor
           Supplier Tracking
           PFD:
           MATERIAL MANAGEMENT – MATERIAL RECEIPT
                             Start
PAGE 16 OF 31                                          Coordinate with vendor and
                 Review the material and update
                the gate entry register with vendor   intimate user dept. of expected
                               detail                            delivery.
        Forward Copy of GRN with Documents
              to Operation Team at HO
PAGE 17 OF 31
           Civil Construction
                Receiving of GFC & GA Drawings
                Freezing of Method Statement
                Contractor Mobilization (Labor & Machinery)
                Execution work
PAGE 18 OF 31
                        a) Civil work
                              i.  Excavation
                             ii.  Shuttering & Centering Work
                            iii.  Steel Work
                            iv.   Concreting
                        b) Mechanical work
                        c) Electrical work
           Erection/Installation (Mech/Elec/C & I) Including availing
           Permanent Power
                     Receiving of mechanical Equipment’s
                     Handover from Civil Execution to Erection Team
                     Erection of Mechanical/Electrical/ C&I unit as per approved Drawing
                     Documentation of Erection
           SOP
                a)   Preparation of Design basis
                b)   Completion of alignment sheet, construction Drawing, Equipment layouts etc.
                c)   Preparation of General arrangement Drawing
                d)   Arrangement of power source & prepare requisition of material etc.
                e)   Review detailed technical specification of mechanical, Electrical and C& I equipment’s.
                f)   Carryout Technical evaluation of bids
                g)   Review Contractor documents
                h)   Preparation of platform for erection.
PAGE 19 OF 31
           Process Flow Diagram (PFD)
                                                   Review of Technical
                                                                         Power Source
                                                      Specification
                                                                                            Review of
                                   QA-QC testing
                                                                                        Contractor/Vendor
                                                                                                            Preparation of
                        Planning
                                                                                                              Checklist
                 Input Drawing
                                                               Erection                                          Preaparation of
                                                                                                                    Platform
PAGE 20 OF 31
           Checklist
PAGE 21 OF 31
                 Rev No.        Reason for Revision         Prepared By       Checked By         Approval by
                 Rev 00           New procedure
                 Rev 01     Standardization of procedure
                                                                                       Document Title
                Luthra Group of Company                                      Execution Safety Procedure
                      Document Ref No.                                                Date of Issue :
           Commissioning & Trial run
           SOP:
                    a) Make sure all construction and Erection works related to Mechanical, Electrical, C
                       & I completed in all respect and clearance is available for commissioning.
                    b) Ensure that erection protocols are handed over to client and clearance is available
                       for taking up commissioning.
                    c) Ensure availability of related approved Drawing, Operation & Testing manuals etc.
                    d) Ensure sufficient manpower, special tools & spare parts are necessary for the
                       commissioning.
                    e) Carry out pre-start-up inspection and ensure all temporary erection arrangements
                       are removed.
                    f) Ensure barricading, safety signs etc are arranged as applicable
                    g) Carry out necessary lubrication wherever necessary
                    h) No load trial run and Equipment operation to make vibration and safety device
                       checks and other required operating test and adjustments
                    i) Carry out pre-commissioning activities like Flushing, blowing, chemical cleaning
                       etc.
                    j) Signing off commissioning protocols and release of equipment for service
PAGE 22 OF 31
                                                 Document Title
                Luthra Group of Company   Execution Safety Procedure
                    Document Ref No.            Date of Issue :
           Process Flow Diagram (PFD) :
PAGE 23 OF 31
                                                             Resourse
                                                          arrangment like
                                                            Manpower,
                                                           drawings etc.
                                 Planning
                                                                                Framework of
                                 required
                                                                               Commissioning
                             fuel ,consumbal
                                                                                    Team
                              es Material etc
                                                          Commissioning
                                                                              Development of
                             Development of
                                                                                Checklist &
                             Commissioning
                                                                              commissioning
                               Sequence
                                                                                procedures
                                                             Defining
                                                          commissioning
                                                            schedule
                 Rev No.       Reason for Revision            Prepared By    Checked By         Approval by
                 Rev 00             New PFD
                 Rev 01    Standardization of procedure
                                                                                      Document Title
                Luthra Group of Company                                     Execution Safety Procedure
                      Document Ref No.                                               Date of Issue :
           Checklist:
PAGE 24 OF 31
           Sl.no                       Description                    Y           N                 Remarks
                         All safety equipment are in place and
                1
                         functional
                2        Emergency procedures are known
                         Medical & first aid consideration have
                3
                         been arranged
                         All inspection equipment has been
                4
                         completed
                5        Availability of approved Drawings
                6        Ancillary work completed
                7        Availability Erection Detail Dwg.
                         Operation Philosophy Approval
                8
                         Completed
                         O&M Manual & Commissioning Checklist
                9
                         Approval Completed
                10       Manpower availability
                11       Method statement Freeze
                12       Necessary Spare parts available
                         Define and document requirement at the
                         commencement of each phase and
                13
                         appropriate update throughout the
                         process
                         Verify document compliance as each
                14
                         phase
                    Rev No.           Reason for Revision           Prepared By        Checked By        Approval by
                     Rev 00                  New pr
                     Rev 01      Standardization of procedure
           Client Invoicing
                                    i) Submission of Performa invoice
                                    ii) Submission of Supporting doc’s (If required)
                                    iii) Submit Tax invoice
PAGE 25 OF 31
           Quality
                               1) Bought out item
                                  a. Quality Assurance Plan (QAP)
                                  b. Third Party Inspection (TPI) – if required
                                  c. Incoming material inspection report (IMIR)
                               2) Quality assurance at site
                                  d. Stagewise inspection during construction & Erection
                                  e. Submit inspection report
           Vendor/Contractor Billing
                 SOP
                        Following points should be verify during checking of Contractor billing.
                              Measurement sheet shall certified by site Engineer
                              Invoice Supported by a valid PO/WO.
                              Original Tax Invoice (Format as prescribed by Company).
                              SES & GRN/Delivery Challan available
                              Project Insurance from contractor available and valid
                              PF/ESI Challan/ state compliance, as applicable provided by
                               contractor
                              Cumulative Certified value is not more than the contract price
                              Bill certification in accordance with the terms of the WO/PO
                              Reconciliation statement along with monthly bill
                              The contract sum mentioned the payment certificate is in accordance
                               with PO/WO
                              Taxes charged by the vendor/contractor are as agreed in the PO/WO
                              Advance (s) paid recover as per the term of PO/WO.
                              Whether retention money is deducted as per the PO/Wo
           Note: Payment modality shall be fixed during PO Drafting.
                 PFD
PAGE 26 OF 31
                                Start
                Receive Performa invoice for advance from
                   contractor based on terms of contract
                     Review Performa Invoice and
                          fill payment advice
                     Forward approved payment
                        advice to finance team
              Collect RAS Bill from Contractor on                    Record reason for discrepancy,
            monthly basis with supporting docs. Inc.                 rectify and re submit the bill to
                           labour PF                                        client by contractor
                   Scrutinize Bills for accuracy and
                            completeness                             Prepare material reconciliation
                                                                              statement
                Compare Measurement Sheet with
                work done as claimed by Contractor                        Scanned Invoice with
                                                                      recommended amount to HO
                        Reconcile RA Bill and
                       Compare Measurement                           Review Cross Check by Project
                                Sheet                                 Division & Submit RA Bill to
                                                                          Finance for Payment
                              Discrepanc                                          End
                               y Found
                     Checklist :
           Sl.No                                       Particulars         Yes/No              Remarks
PAGE 27 OF 31
                .                                                          /NA
                1  Invoice supported by a valid PO/WO
                2  Original Tax Invoice
                3  Invoice submitted by vendor/contractor is
                   prescribed by company
             4     GRN/Delivery Challan available
             5     Project Insurance from contractor available and
                   valid
             6     Bank Guarantee/corporate guarantee available and
                   valid
             7     PF/ESI challans/ state compliance, as applicable
                   provided by the contractor
             8     Cumulative certified value is not more than the
                   contract price
             9     Bill certification is in accordance with the terms of
                   the WO/PO
            10     The contract sum mentioned in the payment
                   certificate is in accordance with WO/PO
            11     Taxes charged by the vendor / contractor are as
                   agreed in the PO/WO
            12     Advance(s) paid recovered as per the term of
                   PO/WO
            13     Whether retention money is deducted as per the
                   PO/WO
           Notes if any….
PAGE 28 OF 31
                        CHAPTER4 : PROJECT CLOSURE
           Technical Closure
                      iv) Pre-commissioning & trail Run Doc’s
                      v) Punch Point Closure
                      vi) Completion of Facility
                      vii)PG Test (Performance Guaranty Test)
                      viii)     Operational Handover to Client
           Commercial Closure
                      ix) Contractual Claims Closure
                      x) Vendor PO Closure
                      xi) Completion of Client Billing
PAGE 29 OF 31
           SOP
                                       a.
                                       b.
                                       c. Steel Work
                                       d. RCC Work :-
                                                   1.   Shoring Shuttering arrangement
                                                   2.   Level Marking as per drawing
                                                   3.   Safety Measures
           Method Statement
                    1) Excavation :-
           PFD
PAGE 30 OF 31
                        1) Excavation :-
                                Identify need for   Clearty define       Prepare Site
                                Excavation          work scope           Contractor
                                Person in-charge    Competent Engineer
                                Site visit for      Field Varification   Execute work
                                Inspection          using Checklist      Contractor
                                Supervisor          Supervisor
                                Check the           Completion of
                                excavation each     Work
                                day                                          RFI closure
                                                    Contractotr
                                Engineer
           Check list
PAGE 31 OF 31