L2 Schedule - Copy-1

The document provides a tentative schedule for carrying out civil foundation work for the construction of a 400KV power line. The schedule is broken down into 7 key activities - survey and pit marking, excavation, stub setting, PCC work, TMT bar binding, RCC work, and backfilling. Each activity lists the total quantity of locations (36), what has been completed so far, and the remaining balance to be scheduled over 7 months from April 2023 to October 2023 on a weekly basis. The schedule is noted to be tentative and may vary depending on actual site conditions and delays.

Uploaded by

Akd Deshmukh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views1 page

L2 Schedule - Copy-1

The document provides a tentative schedule for carrying out civil foundation work for the construction of a 400KV power line. The schedule is broken down into 7 key activities - survey and pit marking, excavation, stub setting, PCC work, TMT bar binding, RCC work, and backfilling. Each activity lists the total quantity of locations (36), what has been completed so far, and the remaining balance to be scheduled over 7 months from April 2023 to October 2023 on a weekly basis. The schedule is noted to be tentative and may vary depending on actual site conditions and delays.

Uploaded by

Akd Deshmukh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

JBS Enterprises Pvt Ltd

Tentative L2 - Schedule for carry out civil foundation work for Construction of 400KV Kharghar Padghe line (WRNER package C) under MUML

1 2 3 4 5 6 7
Complet Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23
Sl. No. ACTIVITY Unit total Qty ed Balance
III IV I II III IV I II III IV V I II III IV I II III IV I II III IV I II III IV
week week week week week week week week week week week week week week week week week week week week week week week week week week week

1 Civil foundation activity


a Check survey & pit marking Loc 36 6 30 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
b Excavation Loc 36 4 32 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
c Stub setting Loc 36 1 35 1 2 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
d PCC work Loc 36 1 35 1 1 1 2 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
e TMT bar binding Loc 36 1 35 1 1 1 2 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
f RCC work Loc 36 0 36 1 1 1 1 2 1 1 2 2 2 2 2 2 2 2 2 2 4 4
g Backfilling Loc 36 0 36 1 1 1 1 2 1 1 2 2 2 2 2 2 2 2 2 2 4 4

Note:
The above Schedule is tentetive & may vary based on actual site condition. Any delay in availability of work front, resolution of ROW, non working condition due to heavy rain/ non supportive climate conditions etc may
extend the completion schedule equivalent to the days in delay.