JBS Enterprises Pvt Ltd
Tentative L2 - Schedule for carry out civil foundation work for Construction of 400KV Kharghar Padghe line (WRNER package C) under MUML
1 2 3 4 5 6 7
Complet Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23
Sl. No. ACTIVITY Unit total Qty ed Balance
III IV I II III IV I II III IV V I II III IV I II III IV I II III IV I II III IV
week week week week week week week week week week week week week week week week week week week week week week week week week week week
1 Civil foundation activity
a Check survey & pit marking Loc 36 6 30 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
b Excavation Loc 36 4 32 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
c Stub setting Loc 36 1 35 1 2 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
d PCC work Loc 36 1 35 1 1 1 2 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
e TMT bar binding Loc 36 1 35 1 1 1 2 1 1 1 2 2 2 2 2 2 2 2 2 2 4 4
f RCC work Loc 36 0 36 1 1 1 1 2 1 1 2 2 2 2 2 2 2 2 2 2 4 4
g Backfilling Loc 36 0 36 1 1 1 1 2 1 1 2 2 2 2 2 2 2 2 2 2 4 4
Note:
The above Schedule is tentetive & may vary based on actual site condition. Any delay in availability of work front, resolution of ROW, non working condition due to heavy rain/ non supportive climate conditions etc may
extend the completion schedule equivalent to the days in delay.