Detailed Cost Estimate for Tile Setting
REFERENCE NUMBER: 3161366
ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol
Quantity : 73.03 sq.m.
Description Qty. Unit Unit Price Amount
A. Estimated Direct Cost
a. Materials
24" x 24" porcelain tiles 210 pcs 210.00 44,100.00
Portland Cement 25 bag 260.00 6,500.00
Sand 3.5 cu.m. 1,320.00 4,620.00
Tile grout 28 pack 50.00 1,400.00
TOTAL COST OF MATERIALS 56,620.00
b. labor
2 Mason 6 days 350 4,200.00
1 Labor 6 days 250 1,500.00
TOTAL COST OF LABOR 5,700.00
TOTAL OF A (Estimated Direct Cost) 62,320.00
Plus
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 6,232.00
Profit 4,985.60
TOTAL OF B 11,217.60
Plus
Value Added Tax (VAT) (12% of A & B) 8,824.51
TOTAL COST OF WORK ITEM 82,362.11
Submitted by:
Manuelito F. Varquez, Jr.
Proprietor/Owner
Al Chris Construction
189.77778
69.9
9.9 sq.m.
202.84722
8.375
5.25
73.025
Detailed Cost Estimate for Waterproofing of Concrete Gutter
REFERENCE NUMBER: 3161366
ITB NO. 1505-01 PROCUREMENT OF INFRA ( Proposed Barangay Health Center )
Location of the Contract: Barangay Cogon, Tagbilaran City, Bohol
Quantity : 10.50 sq.m.
Description Qty. Unit Unit Price Amount
A. Estimated Direct Cost
a. Materials
Super Thoroseal Waterproof 7 pcs 803.00 5,621.00
Portland Cement 6 bag 260.00 1,560.00
Sand 0.5 cu.m. 1,320.00 660.00
Paint Brush 4" 2 pcs 110.00 220.00
TOTAL COST OF MATERIALS 8,061.00
b. labor
1 Painter 3 days 350 1,050.00
1 Labor 3 days 250 750.00
TOTAL COST OF LABOR 1,800.00
TOTAL OF A (Estimated Direct Cost) 9,861.00
Plus
B. MARK-UPS
Overhead, Contingencies, Miscellaneous (OCM) 986.10
Profit 788.88
TOTAL OF B 1,774.98
Plus
Value Added Tax (VAT) (12% of A & B) 1,396.32
TOTAL COST OF WORK ITEM 13,032.30
Submitted by:
Manuelito F. Varquez, Jr.
Proprietor/Owner
Al Chris Construction