0% found this document useful (0 votes)
368 views3 pages

Construction Cost Breakdown

This document contains detailed unit price analyses (DUPAs) for 5 items: 1. Panelboards/Outdoor Circuit Breakers 2. 2.00 sqmm - 5.5 sqmm Bare Copper Wire 3. 15 mm dia.-32 mm dia. Polyvinyl Chloride (PVC) Pipes 4. Lighting Fixture 5. Switches Each DUPA provides information on labor costs including number of personnel, hours worked, hourly rates and amounts as well as equipment costs and total costs.

Uploaded by

Zheby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
368 views3 pages

Construction Cost Breakdown

This document contains detailed unit price analyses (DUPAs) for 5 items: 1. Panelboards/Outdoor Circuit Breakers 2. 2.00 sqmm - 5.5 sqmm Bare Copper Wire 3. 15 mm dia.-32 mm dia. Polyvinyl Chloride (PVC) Pipes 4. Lighting Fixture 5. Switches Each DUPA provides information on labor costs including number of personnel, hours worked, hourly rates and amounts as well as equipment costs and total costs.

Uploaded by

Zheby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

DETAILED UNIT PRICE ANALYSIS (DUPA)

19.1. Panelboards/Outdoor Circuit


Item No./Description :
Breakers
Unit of Measurement : Quantity : 1.00
Output per hour : Units : lot

No. of Person No. of Hours Hourly Rate Amount


Designation
A. Labor
a. Construction Foreman 1 29.73 115.25 3425.91
b. Skilled Laborer 2 29.73 83.32 4953.53
c. Unskilled Laborer 2 29.73 64.22 3818.00

Sub-Total for A 12197.44

No. of Units No. of Hours Hourly Rate Amount


Name and Capacity
B. Equipment
Minor Tools (10% of Labor Cost) 1219.74

Sub-Total for B 1219.74


C. Total (A+B) 13417.19

DETAILED UNIT PRICE ANALYSIS (DUPA)


19.2. 2.00 sqmm - 5.5 sqmm Bare
Item No./Description : 1101(7)
Copper Wire
Unit of Measurement : m Quantity : 840.00
Output per hour : 40 Units : m

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 13.63 115.25 1570.87
b. Skilled Laborer 2 13.63 83.32 2271.32
c. Unskilled Laborer 2 13.63 64.22 1750.65

Sub-Total for A 5592.84

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 559.28

Sub-Total for B 559.28


C. Total (A+B) 6152.12

DETAILED UNIT PRICE ANALYSIS (DUPA)


19.3. 15 mm dia.-32 mm dia.
Item No./Description : 1100(6)
Polyvinyl Chloride (PVC) Pipes
Unit of Measurement : length Quantity : 1.00
Output per hour : 3.534 Units : lot

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 12.50 115.25 1440.40
b. Skilled Laborer 1 12.50 83.32 1041.34
c. Unskilled Laborer 1 12.50 64.22 802.62

Sub-Total for A 3284.36

Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 328.44

Sub-Total for B 328.44


C. Total (A+B) 3612.80

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 1103 19.4. Lighting Fixture
Unit of Measurement : set Quantity : 1.00
Output per hour : 1 Units : lot

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Construction Foreman 1 28.45 115.25 3278.74
b. Skilled Laborer 4 28.45 83.32 9481.47
c. Unskilled Laborer 4 28.45 64.22 7307.97

Sub-Total for A 20068.18

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 2006.82

Sub-Total for B 2006.82


C. Total (A+B) 22075.00

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 1101 19.5. Switches
Unit of Measurement : set Quantity : 1.00
Output per hour : 1 Units : lot

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Skilled Laborer 1 9.52 83.32 793.18
b. Unskilled Laborer 1 9.52 64.22 611.36

Sub-Total for A 1404.54

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 140.45

Sub-Total for B 140.45


C. Total (A+B) 1545.00

DETAILED UNIT PRICE ANALYSIS (DUPA)


19.6. Junction/ Utility/ Pull/ Square
Item No./Description : 1100
Box
Unit of Measurement : pc Quantity : 1.00
Output per hour : 1 Units : lot

Designation No. of Person No. of Hours Hourly Rate Amount


Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Skilled Laborer 1 4.97 83.32 414.05
b. Unskilled Laborer 1 4.97 64.22 319.13

Sub-Total for A 733.19

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 73.32

Sub-Total for B 73.32


C. Total (A+B) 806.50

DETAILED UNIT PRICE ANALYSIS (DUPA)


Item No./Description : 19.7. Grounding
Unit of Measurement : Quantity : 1.00
Output per hour : Units : lot

Designation No. of Person No. of Hours Hourly Rate Amount

A. Labor
a. Skilled Laborer 2 32.95 83.32 5491.47
b. Unskilled Laborer 2 32.95 64.22 4232.62

Sub-Total for A 9724.09

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 972.41

Sub-Total for B 972.41


C. Total (A+B) 10696.50