DETAILED UNIT PRICE ANALYSIS (DUPA)
19.1. Panelboards/Outdoor Circuit
Item No./Description :
Breakers
Unit of Measurement : Quantity : 1.00
Output per hour : Units : lot
No. of Person No. of Hours Hourly Rate Amount
Designation
A. Labor
a. Construction Foreman 1 29.73 115.25 3425.91
b. Skilled Laborer 2 29.73 83.32 4953.53
c. Unskilled Laborer 2 29.73 64.22 3818.00
Sub-Total for A 12197.44
No. of Units No. of Hours Hourly Rate Amount
Name and Capacity
B. Equipment
Minor Tools (10% of Labor Cost) 1219.74
Sub-Total for B 1219.74
C. Total (A+B) 13417.19
DETAILED UNIT PRICE ANALYSIS (DUPA)
19.2. 2.00 sqmm - 5.5 sqmm Bare
Item No./Description : 1101(7)
Copper Wire
Unit of Measurement : m Quantity : 840.00
Output per hour : 40 Units : m
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor
a. Construction Foreman 1 13.63 115.25 1570.87
b. Skilled Laborer 2 13.63 83.32 2271.32
c. Unskilled Laborer 2 13.63 64.22 1750.65
Sub-Total for A 5592.84
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 559.28
Sub-Total for B 559.28
C. Total (A+B) 6152.12
DETAILED UNIT PRICE ANALYSIS (DUPA)
19.3. 15 mm dia.-32 mm dia.
Item No./Description : 1100(6)
Polyvinyl Chloride (PVC) Pipes
Unit of Measurement : length Quantity : 1.00
Output per hour : 3.534 Units : lot
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor
a. Construction Foreman 1 12.50 115.25 1440.40
b. Skilled Laborer 1 12.50 83.32 1041.34
c. Unskilled Laborer 1 12.50 64.22 802.62
Sub-Total for A 3284.36
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 328.44
Sub-Total for B 328.44
C. Total (A+B) 3612.80
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 1103 19.4. Lighting Fixture
Unit of Measurement : set Quantity : 1.00
Output per hour : 1 Units : lot
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor
a. Construction Foreman 1 28.45 115.25 3278.74
b. Skilled Laborer 4 28.45 83.32 9481.47
c. Unskilled Laborer 4 28.45 64.22 7307.97
Sub-Total for A 20068.18
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 2006.82
Sub-Total for B 2006.82
C. Total (A+B) 22075.00
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 1101 19.5. Switches
Unit of Measurement : set Quantity : 1.00
Output per hour : 1 Units : lot
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor
a. Skilled Laborer 1 9.52 83.32 793.18
b. Unskilled Laborer 1 9.52 64.22 611.36
Sub-Total for A 1404.54
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 140.45
Sub-Total for B 140.45
C. Total (A+B) 1545.00
DETAILED UNIT PRICE ANALYSIS (DUPA)
19.6. Junction/ Utility/ Pull/ Square
Item No./Description : 1100
Box
Unit of Measurement : pc Quantity : 1.00
Output per hour : 1 Units : lot
Designation No. of Person No. of Hours Hourly Rate Amount
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor
a. Skilled Laborer 1 4.97 83.32 414.05
b. Unskilled Laborer 1 4.97 64.22 319.13
Sub-Total for A 733.19
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 73.32
Sub-Total for B 73.32
C. Total (A+B) 806.50
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 19.7. Grounding
Unit of Measurement : Quantity : 1.00
Output per hour : Units : lot
Designation No. of Person No. of Hours Hourly Rate Amount
A. Labor
a. Skilled Laborer 2 32.95 83.32 5491.47
b. Unskilled Laborer 2 32.95 64.22 4232.62
Sub-Total for A 9724.09
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
B. Equipment
Minor Tools (10% of Labor Cost) 972.41
Sub-Total for B 972.41
C. Total (A+B) 10696.50