VFD Panel Commissioning

The document summarizes the commissioning process for a VFD panel, including general checks of the panel components and wiring, insulation resistance testing, motor information collection, functional tests after charging the panel, no-load and load motor experiments, and sign off. Key steps include verifying wiring and connections, performing insulation resistance tests, collecting motor data, running the drive through ID and no-load runs, checking control logic and signals, and recording motor performance data under no-load and load conditions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
414 views3 pages

VFD Panel Commissioning

The document summarizes the commissioning process for a VFD panel, including general checks of the panel components and wiring, insulation resistance testing, motor information collection, functional tests after charging the panel, no-load and load motor experiments, and sign off. Key steps include verifying wiring and connections, performing insulation resistance tests, collecting motor data, running the drive through ID and no-load runs, checking control logic and signals, and recording motor performance data under no-load and load conditions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

VFD Panel Commissioning

Consumer: Date:
Project: Panel Type:
Model Number: VFD Serial Number:
Motor:
Report Number:

General Checks and Inspections of the Panel

Serial Checkpoints for parameters / General Output /


Number Inspection Result

1 Ensure that both side panels have an earth grid OK NOT OK


and a firm panel earthing.
2 Verify that all Horizontal, Vertical, and Control OK NOT OK
Bus bars are securely fastened.
3 Inspect the Main bus bars at the ACB, MCCB, OK NOT OK
FSU, and VFD terminals for tightness.
4 Check for any open Circuits on all CT secondary OK NOT OK
circuits.
4 Verify that all feeder components' power wires OK NOT OK
and control circuits are tight.
5 Verify the correct voltage. CT/PT terminations (if OK NOT OK
any) at all KWH/MFM/Relays.
6 Check the delivery of the rated control voltage OK NOT OK
according to the drawing.
7 Check that the relays, KWH meters, and control OK NOT OK
equipment have the proper rated Aux voltage.
8 Make sure that the control and power circuits OK NOT OK
have fuses with the appropriate ratings.
9 Check that all feeders' inter-panel and OK NOT OK
marshalling wiring is done in accordance with the
drawing.
10 Before charging, make sure that all control fuses OK NOT OK
and future interlock links have been removed.
11 Before the VFD Panel is charged for the first time, OK NOT OK
make sure the feeder door is closed.
12 Check for any damage caused by transportation OK NOT OK
or erection. (List all damaged goods).
13 Prior to charging the panel, make sure it has OK NOT OK
been well cleaned inside.
Panel / Motor Cable IR Test (Without VFD)

IR R-(Ø)Phases Y-(Ø)Phases B-(Ø)Phases


Details
Phase to Phase (in m-ohm) R-Y= >MΩ Y-B= >MΩ B-R= >MΩ

Phase to Earth (in m-ohm) R-E= MΩ Y-E= MΩ B-E= MΩ

Motor Information

Serial Number: Ampere: A


KW: Voltage: Volts
RPM: Duty:
Frequency: Hz Efficiency (%):

Tests of Functionality after Charging

Serial Checks Control and Power Circuits after Panel Output /


Number Charging Result
1 To prevent IGBT failure, keep the drive firing slowly YES NO
with a DC source over 8 hours.
2 Safely turn on the main voltage and leave the engine OK NOT OK
running while it charges for four hours
3 Before starting the ID Run, enter Correct Motor data OK NOT OK
in 99 groups
4 Do the drive ID run after switching the drive to local YES NO
mode
5 Try the motor with no load, and record all the data OK NOT OK
as shown below
6 Check the Panel, LCS, and DCS for VFD OK NOT OK
On/Off/Raise/Lower operation
7 For the DCS system, verify all DI/DO/AI/AO (4-20 OK NOT OK
mA) Signals in accordance with the drawing
8 Verify any standby or bypass logic that is specified in OK NOT OK
the drawing
Motor Experiment

No Load Experiment

Total Runtime- Min

S. No Current Voltage RPM Frequency KW Remarks

Load Experiment

Total Runtime- Hr

S. No Current Voltage RPM Frequency KW Remarks

Remarks (If Any):

Tested By Test Observed by

Name: Name:
Designation: Designation:
Signature: Signature: