Varation 2
Varation 2
I. INTERNAL WORKS
1. CONCRETE WORK
1.1 C-25 concrete on verendah of meeting and offices floor m2
slab 9.00 1,050.00 9,450.00 8.72 8.72 - 9,156.00 9,156.00
1.2 Reinforcement steel bars according to structural drawing.
Price includes cutting, bending, placing in position and
tying wires. - - - -
a) dia. 8mm deformed bar kg 4.68 120.00 561.60 4.68 4.68 - 561.60 561.60
- - - -
5.1 Swinging door size (80x210cm) pcs. 1.00 25,200.00 25,200.00 - - - -
5.2 Partition size (100x150cm) pcs. 3.00 22,500.00 67,500.00 - - - -
Total Carried to Summary….. 92,700.00 - - -
6. SANITARY INSTALLATION
HAND WASH BASINS - - - -
6.1 Supply and fix hand wash basins made of white vitreous No 1.00 15,225.00 15,225.00 - - - -
6.2 china
Supplywith
andlever controlled
fix urinals madecold watervitreous
of white tap, complete with
china type No 2.00 15,225.00 30,450.00 - - - -
plug,
R.A.Lchrome
Ceramics plated chain holder,
or equivalent. P- shall
Price smellinclude
trap with
smell
connection
trap and all pipe and with
necessary all other necessary accessories.
accessories.
Total Carried to Summary….. 45,675.00 - - -
7. FLOOR AND WALL FINISH
7.1 5cm thick cement screed m2 8.50 300.00 2,550.00 - - - -
- - - -
Total Carried to Summary….. 2,550.00 - - -
Total I. 626,736.60 - 331,129.60 331,129.60
K. RENOVATION OF OFFICE
1. Joinery
1.1 Make the wooden door according to approved shop
drawings.
In case of flush compressed doors, make the internal fillers
from white wood with 3cm maximum distance between
fillers, and 3cm minimum width for each one. Make the
architraves using hard wood unless otherwise specified.
Forming fillers as specified in the drawings and make a
tongue through the longitudinal part of the frame with
minimum 1cm length. Doors which their connections
include gaps, shall be rejected.
Supply and fix PVC tile for floor finish. Supply and fix Kerrero fascia board 250x25mm
2 2.70 1
3.50 23.50
18.90 23.50
Ramp 4. FINISHING
1 circular ditch a) To internal wall surface plastering
40.00 1 10.96 door side wall
40.00 2.50
27.40
40.00 ml -3 1.60 DDt w1
1.60
Internal work (7.68)
C-25 concrete -2 0.80 DDt D1
1 4.36 Ground floor slab 2.10
2.00 (3.36)
8.72 -1 1.15 DDt D2
2.10
8.72 m^2 total (2.42)
4 5.50 Office 1, 2 & meeting wall
Rebar summery 2.50
4.68 kg 8mm dia. Deformed rebar 55.00
3 5.62 toilet partition wall
Supply and construct class 'C' 200x200x400 2.30
1 10.96 door side wall 38.78
2.50 -3 0.70 DDt D1
27.40 2.10
-3 1.60 DDt w1 (4.41)
1.60 -3 0.25 DDt w1
(7.68) 1.00
-2 0.80 DDt D1 (0.75)
2.10 1 3.90 toilet door side
(3.36) 2.30
-1 1.15 DDt D2 8.97
2.10 1 3.60 handwash area
(2.42) 2.30
1 10.96 Copping 8.28
0.20 1 1.80
2.19 1.65
2.97
16.14 m^2 total
122.78 m^2 total
Supply and construct class 'C' 150x200x400mm HCB wall
2 5.50 Office 1, 2 & meeting wall
2.50
27.50
supply and fix 8mm thick chipwood ceiling for toilet and verendah
1 16.00 verendah celing
1.00
16.00
1 2.50 toilet celing
5.50
13.75
14.79 ml total
Total length(m)= 0.00 63.50 0.00 0.00 0.00 0.00 0.00 0.00
Kg/ml= 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Sub total Wt(Kg)= 0.00 25.08 0.00 0.00 0.00 0.00 0.00 0.00
Total length(m)= 0.00 791.25 0.00 0.00 0.00 0.00 0.00 0.00
Kg/ml= 0.222 0.395 0.617 0.888 1.209 1.579 2.467 3.552
Sub total Wt(Kg)= 0.00 312.54 0.00 0.00 0.00 0.00 0.00 0.00
E Varation No-1
1.00 Block Work Birr 735,924.09 494,023.97 - 494,023.97
Concret work and Block Birr
2.00 work 340,972.43 262,163.01 - 262,163.01
3.00 External paint Birr 505,441.26 409,894.35 - 409,894.35
SUB TOTAL - E Birr 1,582,337.78 1,166,081.34 - 1,166,081.34 - -
SUB TOTAL - A+B+C+D+E Birr 25,492,542.79 19,284,694.79 10,933,959.06 30,218,653.85 5,475,334.43 29%
Vat 15% 3,823,881.42 2,892,704.22 1,640,093.86 4,532,798.08 821,300.16
Grand total with vat 29,316,424.21 22,177,399.01 12,574,052.91 34,751,451.93 6,296,634.60 29%
SURVICE 01 SUMMERY
CONTRACT EXECUTED AMOUNT
Item DISCRIPTION Remark
UNIT AMOUNT Previous Current Todate
A GENERAL ITEM - -
1.00 Demolishing work Birr 95,000.00 - -
D ADDITIONAL WORK
1.00 ADDITIONAL WORK OREDR Birr 1,187,178.95 175,590.82 175,590.82
A. DEMOLISHING
Demolish and remove WORK
the existing house with made of front
part ribbed metal sheet,CIS shett roof cover constraction and
1.10 handover the wanted material to the client Ls 1.00 20,000.00 20,000.00 1.00 1.00 - 20,000.00 - 20,000.00 - 0%
1.20 Demolish HCBwalls and cartaway unwanted material Ls 1.00 25,000.00 25,000.00 1.00 1.00 - 25,000.00 - 25,000.00 - 0%
1.30 Demolish rc slab and and cart awey an wanted material Ls 1.00 50,000.00 50,000.00 1.00 1.00 - 50,000.00 - 50,000.00 - 0%
- -
Total carried to summary birr 95,000.00 95,000.00 - 95,000.00 - 0%
B. SUB STRUCTURE
1. EXCAVATION & EARTH WORK
Clearing of the site to an average of 20cm from natural
1.10 ground level m2 200.00 20.00 4,000.00 64.35 64.35 135.65 1,287.00 - 1,287.00 2,713.00 -68%
1.20 Bulk excavation not greater than 150cm m3 36.00 120.00 4,320.00 - - 36.00 - - - 4,320.00 -100%
Backfill around foundation with selected excaveted material
1.30 from the site m3 40.50 70.00 2,835.00 - - 40.50 - - - 2,835.00 -100%
Backfill around foundation with selected excaveted material
1.40 from quarry m3 200.00 110.00 22,000.00 - - 200.00 - - - 22,000.00 -100%
1.50 25cm thick basaltic or equvalent stone hardcore wall. m2 230.00 130.00 29,900.00 19.48 19.48 210.53 2,531.75 - 2,531.75 27,368.25 -92%
cartaway surplus execavated material and dispose it away
1.60 from site M3 76.00 70.00 5,320.00 - - 76.00 - - - 5,320.00 -100%
- - - - - - -
Total carried to summary birr 68,375.00 3,818.75 - 3,818.75 64,556.25 -94%
Masonary
Around
1.70 50cm thick stone masonry below ground level m3 5.00 2,300.00 11,500.00 43.36 43.36 (38.36) 99,728.00 - 99,728.00 (88,228.00) 767% external toilet
1.80 Ditto but above ground level m3 2.50 2,300.00 5,750.00 - - 2.50 - - - -100%
Total carried to summary birr 17,250.00 99,728.00 - 99,728.00 (88,228.00) 478%
3. CONCRETE WORK
50mm thick lean concrete in class C-5 with minimum of
2.10 150kg/m3 cement m2 36.00 150.00 5,400.00 34.45 34.45 1.55 5,167.50 - 5,167.50 232.50 -4%
Construct reinforced concrete retaing wall as showen in
2.20 concrete class C-25, with minimum cement 360kg/m3 m3 24.60 3,500.00 86,100.00 - - 24.60 - - - 86,100.00 -100%
2.30 C-25 10cm thick reinforecment concrete floor slab m2 27.00 300.00 8,100.00 19.47 19.47 7.53 5,842.50 - 5,842.50 2,257.50 -28%
2.30 C-20 10cm thick reinforecment concrete for site work m2 200.00 300.00 60,000.00 - - 200.00 - - - 60,000.00 -100%
Reinforcement steel bar according to the structural
drawing.Price shall include cutting , bending and placing in
2.40 position. - - - - - - - -
Dia.8 deformed bar Kg 1,618.35 85.00 137,559.75 357.02 357.02 1,261.33 30,346.76 - 30,346.76 107,212.99 -78%
Dia.10 deformed bar Kg - - - - - - - -
Dia.12 deformed bar Kg 783.22 85.00 66,573.70 - - 783.22 - - - 66,573.70 -100%
Dia.14 deformed bar Kg - - - - - - - -
Dia.16 deformed bar Kg - - - - - - - -
2.50 Provide cut and fixing in postion plywood formwork - - - - - - - -
a) for RC retaining wall m2 129.60 220.00 28,512.00 - - 129.60 - - - 28,512.00 -100%
Total carried to summary birr 392,245.45 41,356.76 - 41,356.76 350,888.69 -89%
B.Super Structure
1.CONCRETE WORK
Reinforced concrete in class C-25 with minimum Ordinary
Portland Cement content of 360kg/m3 filled into form work
and vibrated around reinforcement bar. (Formwork and
1.10 reinforcement measured separately):
a elivation column m3 0.68 15,000.00 10,200.00 10.86 10.86 (10.18) 162,945.00 - 162,945.00 (152,745.00) 1498%
b in beam m3 51.89 12,000.00 622,680.00 67.37 67.37 (15.48) 808,450.50 - 808,450.50 (185,770.50) 30%
1.20 Provid ,cut and fixing in postion plywood formwork - - - - - - - -
a elivation column m2 8.40 450.00 3,780.00 81.36 81.36 (72.96) 36,612.00 - 36,612.00 (32,832.00) 869%
b in beam m2 449.74 450.00 202,383.00 632.82 632.82 (183.08) 284,767.43 - 284,767.43 (82,384.42) 41%
Design
modification
e.g lintel
external toilet
beam concret
Prepared by: page 16 of 41 coping Approved by:
_________________________________ ________________________________
Statement
Executed
CONTRACT
QUANTITY AMOUNT
Item
DISCRIPTION
No.
Exceding Exceding amount Exceding Remark
in %
Unit Qty Rate Amount Previous Current Todate qty Previous Current Todate
Reinforcement steel bar according to the structural drawing.
Price shall include cutting bending and placing in position.
1.30 - - - - - - - -
a Dia.8 deformed bar Kg 1,372.85 95.00 130,420.75 2,475.06 2,475.06 (1,102.21) 235,130.44 - 235,130.44 (104,709.69) 80%
b Dia.24 deformed bar Kg - - - - - - - - Design
c Dia.20 deformed bar Kg - - - - - - - - modification
d Dia.14 deformed bar Kg 1,466.50 95.00 139,317.50 1,742.16 1,742.16 (275.66) 165,505.43 - 165,505.43 (26,187.93) 19% e.g lintel
external toilet
e Dia.16 deformed bar Kg 2,083.81 95.00 197,961.95 2,696.93 2,696.93 (613.12) 256,208.82 - 256,208.82 (58,246.87) 29% beam concret
f Dia.12 deformed bar Kg - coping
Total carried to summary birr 1,306,743.20 1,949,619.62 - 1,949,619.62 (642,876.42) 49%
Block work
20 cm thick Class B m2 493.02 650.00 320,463.00 551.35 551.35 (58.33) 358,378.15 - 358,378.15 (37,915.15) 12%
design
15 cm thick Class B modification
m2 210.00 600.00 126,000.00 279.09 279.09 (69.09) 167,451.60 - 167,451.60 (41,451.60) 33% and re work
-
Total carried to summary birr 446,463.00 525,829.75 - 525,829.75 (79,366.75) 18%
3. ROOFING WORK
Total carried to summary birr 342,984.00 222,150.70 118,658.20 340,808.90 2,175.10 -1%
9.ELICTRICALL INSTALLETION
9.1 Feeder cable and Cable ladder
PVC shaeted PVC insulated power distrbution cabl of
normal voltage
a. 3*6mmsq ml 100.00 200.00 20,000.00 63.00 63.00 37.00 12,600.00 - 12,600.00 7,400.00 -37%
b.4.6mmsq ml 100.00 250.00 25,000.00 70.00 70.00 30.00 17,500.00 - 17,500.00 7,500.00 -30%
c.2*2.5mmsq ml 35.00 120.00 4,200.00 - - 35.00 - - - 4,200.00 -100%
Floor stand Distaction board (DB), made of sheet steel SDB-
GF/SHlockable door consisting No 1.00 40,000.00 40,000.00 - - 1.00 - - - 40,000.00 -100%
1pc MCB of 10A,1PH No 8.00 1,500.00 12,000.00 13.00 13.00 (5.00) 19,500.00 - 19,500.00 (7,500.00) 63%
1pc MCB of 16A,1PH No 10.00 1,500.00 15,000.00 19.00 19.00 (9.00) 28,500.00 - 28,500.00 (13,500.00) 90%
1pc MCB of 50A,3PH No 1.00 3,200.00 3,200.00 8.00 8.00 (7.00) 25,600.00 - 25,600.00 (22,400.00) 700%
1pc MCB of 60A,3PH No 3.00 3,200.00 9,600.00 1.00 1.00 2.00 3,200.00 - 3,200.00 6,400.00 -67%
Distrbution board 8 CB holder No 3.00 3,500.00 10,500.00 - - 3.00 - - - 10,500.00 -100%
Distrbution board 6 CB holder No 4.00 4,000.00 16,000.00 19.00 19.00 (15.00) 76,000.00 - 76,000.00 (60,000.00) 375% Quantity
Distrbution board 4 CB holder No 6.00 4,500.00 27,000.00 - - 6.00 - - - 27,000.00 -100% change
0.60 W2
4.20 m2
1 1.93 along axis 2 (D-E)
0.60 W5
1.16 m2
6.4.Supply and lay Polished, B. for floor and landing , size
chamfered and egranite 40*40*2cm thick
A. For Riser, Size 15*2cm C) landing for external stair
22 1.80 external stair 1 2.10 external stair
1.00 1.80
39.60 ml 3.78 m2
9 1.65 external stair 1 1.00 bank stair
1.00 0.50
14.85 ml 0.50 m2
13 1.00 bank stair 0.50 m2 Total
3.80 ml
21.63 ml Total
9.ELICTRICALL
INSTALLETION
Supply and replace the existing light
fixture with 1*24w LED pilips light
fixture , size should be 30*30cm
1 140
140
140 No Total
1.Block Work
1.1 HCB Wall dimolishing with Cart Away m2 115.00 237.90 27,358.50 184.68 184.68 43,936.32 - 43,936.32
2.1.1 Ground floor soffit, wall burned area M2 395.29 111.60 44115.60634 127.01 127.01 14,174.27 - 14,174.27
2.1.2 First floor soffit plastering M2 44.25 111.60 4938.43907143 44.25 44.25 4,938.44 - 4,938.44
Chiseling 1st and 2nd floor over burden
screed for leveling the surface with the
2.2 existing floor. M2 431.5 36.96 15,947.01 539.61 539.61 19,942.43 - 19,942.43
Chiseling of HCB wall and ceiling slab
for electrical installation of light and
2.3 socket out let. m2 350 25.87 9,054.50 228.75 228.75 5,917.88 - 5,917.88
2.4 Chisel the surface of wall and Ceilling m2 - - - - -
2.4.1 ground floor m2 395.29 32.34 12,782.69 537.36 537.36 17,376.80 - 17,376.80
2.4.2 1st floor m2 513.78 32.34 16,614.36 449.43 449.43 14,533.33 - 14,533.33
Cementitisous water proof for toilet and
2.5 wet areas m2 142 1106.95 157,186.90 95.69 95.69 105,924.05 - 105,924.05
2.6 Fixing of Ceramic Floor tile m2 184 436.59 80,332.93 181.76 181.76 79,355.84 - 79,355.84
TOTAL CARRIED TO SUMMARY (In Birr) …………… 340,972.43 262,163.01 - 262,163.01
3.External paint
3.1 External Quartz paint m2 710 531.16 377,122.42 771.70 771.70 409,894.35 - 409,894.35
3.2 Cont extra Paint For Front area m2 120 1069.32 128,318.84 - - - -
Issue No:
Issue Date:
LxWxH Total Description
Hand & Guard rail
Hand rail work
20.70 stair 1
20.70 ml
8.50 stair 2
8.50 m2
7.90 stair 4 around septic tank
7.90 m2
10.50 external stair 248.87
10.50 m2
47.60 ml length of hand rail work
Guard rail
14.40 stair 3
14.40 ml
10.20 1st floor rear verendah
10.20 ml
15.50 1st floor front verendah
15.50 ml
21.50 2nd floor front verendah
21.50 ml
61.6 ml length of guard rail work
oil paint work
Toilets
Ground floor septic tank toilet
6.00 along axis 1&2 (F-H)
1.00
12 m2
4.60 along axis H''(1-2)
1.00
9.2 m2
12.00 bank toilet
1.10
13.2 m2
16.60 1st floor toilet
1.10
36.52 m2
16.60 2nd floor toilet
1.20
39.84 m2
110.76 m2 area of oil paint work Qty
ANALYSIS SHEET FOR DIRECT UNIT COST
PROJECT: Shashemene Aquired building mentainance LABOUR DAILY OUTPUT: 1.50 m2./day
WORK ITEM: Cladding work EQUIPMENT: 1.50 m2./day
RESULTANT: 5,801 Br/m2
Cladding work
TOTAL QUANTITY OF WORK ITEM: m2
Material Cost (1:01) Labor (1:02) Equipment Cost (1:03)
Cost Per **Indexed Type of Hourly
Type of Material Unit Qty.* Rate Labor by Trade Unit UF Daily Cost No. UF Daily Cost
Unit Daily Cost Equipment Rental