PROJECT: Construction of Townhouses & Semi-Detached Villas Phase 1B &1C - Al Reem Island, Abu Dhabi, UAE
Employer Reem Hills Sole Properietorship LLC
Employer Project Manager Royal Development Company
Employer Project Manager RAPM Architect Project Management
Engineer AECOM Middle East LLC
Main Contractor M/s. Trojan General Contracting LLC
MEP Contractor M/s. Royal Advance Electromechanical Works LLC
Name : Maruf Ahmad Khan Position: Acting Project Manager - MEP Company: ROYAL ADVANCE ELECTROMECHANICAL
From
Name: Omar Al-Mansouri Position: Projects Director/Project Manager Company: TROJAN
To Name: Suheib Aboamir Position: Resident Engineer (RE) Company: AECOM
Name: Rami Sahawne Position: Project Manager Company: RAPM
cc1 Name: Farris Hannoun Position: Project Manager Company: RDC
Name: Tan Choon Wiew Position: Project Director Company: Q - Properties
NEWSUBMITTAL Reference: RHP1P2-BW-TGC-ZZ-XX-MS-EL-00001
RESUBMITTAL Rev: 01
ADDITIONAL COPIES Date 29-May-24
METHOD STATEMENT SUBMITTAL
Description Issue No. of Sets
METHOD STATEMENT FOR THE INSTALLATION OF UNDER GROUND UPVC DUCT PIPE & ACCESSORIES Issue for Approval 01 Soft Copy
For Trojan General Contracting
Reviewed by : QA/QC Manager Signature : Date : 29-May-2024
Approved by : Project Manager/PD Signature : Date : 29-May-2024
CONSULTANT
Received Date :
Engineers Comments :
Refer the comments highlighted in method statement.
Name: Suheib Aboamir Date & Signature
ENGINEER APPROVAL STATUS :
Approved
Approved As Noted
Revise & Resubmit
Rejected
For Information 10/06/2024
R.E.'s Name : Suheib Aboamir Date & Signature
NB: The approval of the Engineer or the Client does not relieve the Contractor from his responsibility for any corrective
action that is required, if any.
Project: RHP1P2-Townhouses & Semi-detached Villas
SRN. RHP1P2-BW-TGC-ZZ-XX-MS-EL-00001_01
Date: 10-06-2024
ENGINEER’S COMMENTS
HSE Comments: Code “B”
1. Section 8.2 – Reference to approved MSRA for Excavation and Backfilling to be given and compliance
shall be ensured as required.
2. Ensure compliance with relevant requirements of MSDS/COSHH assessment including PPE while
handling chemicals.
3. Ensure storage of UPVC pipes and accessories are being done on levelled ground, at safe height, in
accordance with manufacturer's recommendations.
4. Ensure that safe access/egress is available for all work locations.
5. Ensure compliance with CoP 34.0 of OSHAD SF if UPVC pipes are lowering to the excavations/
trenches using any lifting equipment.
6. The approved Method Statement and Risk Assessment to be briefed to the workers/supervisors prior
to commencing the activities, ensure their understanding and documented.
7. Installation of underground UPVC duct pipes and accessories shall be done by competent operatives
under the supervision of a competent supervisor.
8. The activity to conducted in strict compliance with OSHAD SF & other applicable legislative and other
requirements.
Josy Francis&