PROJECT: Construction of Townhouses & Semi-Detached Villas Phase 1B &1C - Al Reem Island, Abu Dhabi, UAE
Employer                          Reem Hills Sole Properietorship LLC
Employer Project Manager          Royal Development Company
Employer Project Manager          RAPM Architect Project Management
Engineer                          AECOM Middle East LLC
Main Contractor                   M/s. Trojan General Contracting LLC
MEP Contractor                    M/s. Royal Advance Electromechanical Works LLC
                                  Name : Maruf Ahmad Khan         Position: Acting Project Manager - MEP                    Company: ROYAL ADVANCE ELECTROMECHANICAL
From
                                  Name: Omar Al-Mansouri          Position: Projects Director/Project Manager               Company: TROJAN
To                                Name: Suheib Aboamir            Position: Resident Engineer (RE)                          Company: AECOM
                                  Name: Rami Sahawne              Position: Project Manager                                 Company: RAPM
cc1                               Name: Farris Hannoun            Position: Project Manager                                 Company: RDC
                                  Name: Tan Choon Wiew            Position: Project Director                                Company: Q - Properties
       NEWSUBMITTAL                                                                                                            Reference: RHP1P2-BW-TGC-ZZ-XX-MS-EL-00001
       RESUBMITTAL                                                                                                               Rev:     01
         ADDITIONAL COPIES                                                                                                       Date     29-May-24
                                                                     METHOD STATEMENT SUBMITTAL
                                                       Description                                                                      Issue                        No. of Sets
   METHOD STATEMENT FOR THE INSTALLATION OF UNDER GROUND UPVC DUCT PIPE & ACCESSORIES                                             Issue for Approval                 01 Soft Copy
                                                                               For Trojan General Contracting
Reviewed by : QA/QC Manager                      Signature :                            Date : 29-May-2024
Approved by : Project Manager/PD                 Signature :                            Date : 29-May-2024
                                                                                        CONSULTANT
Received Date :
Engineers Comments :
      Refer the comments highlighted in method statement.
Name: Suheib Aboamir                                                                                                           Date & Signature
ENGINEER APPROVAL STATUS :
                                   Approved
                                   Approved As Noted
                                   Revise & Resubmit
                                   Rejected
                                   For Information                                                                                              10/06/2024
R.E.'s Name : Suheib Aboamir                                                                                                                      Date & Signature
NB: The approval of the Engineer or the Client does not relieve the Contractor from his responsibility for any corrective
    action that is required, if any.
 Project:           RHP1P2-Townhouses & Semi-detached Villas
 SRN.               RHP1P2-BW-TGC-ZZ-XX-MS-EL-00001_01
 Date:              10-06-2024
                               ENGINEER’S COMMENTS
HSE Comments: Code “B”
    1. Section 8.2 – Reference to approved MSRA for Excavation and Backfilling to be given and compliance
       shall be ensured as required.
    2. Ensure compliance with relevant requirements of MSDS/COSHH assessment including PPE while
       handling chemicals.
    3. Ensure storage of UPVC pipes and accessories are being done on levelled ground, at safe height, in
       accordance with manufacturer's recommendations.
    4. Ensure that safe access/egress is available for all work locations.
    5. Ensure compliance with CoP 34.0 of OSHAD SF if UPVC pipes are lowering to the excavations/
       trenches using any lifting equipment.
    6. The approved Method Statement and Risk Assessment to be briefed to the workers/supervisors prior
       to commencing the activities, ensure their understanding and documented.
    7. Installation of underground UPVC duct pipes and accessories shall be done by competent operatives
       under the supervision of a competent supervisor.
    8. The activity to conducted in strict compliance with OSHAD SF & other applicable legislative and other
       requirements.
Josy Francis&