Itp For Structural Steel Fabrication Works at Vendor Shop

ITP for Civil and Structural Works

Uploaded by

Vijay Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views3 pages

Itp For Structural Steel Fabrication Works at Vendor Shop

ITP for Civil and Structural Works

Uploaded by

Vijay Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

ITP FOR STRUCTURAL STEEL FABRICATION WORKS AT

VENDOR SHOP

PROJECT: 0.75MTPA EAF REBAR MILL LUDHIANA PUNJAB

Scope of Work: Enabling Works- MS Structural Works

Client M/s. Tata Steel Ltd.


Vendor M/s. Minda Infrastructure LLP

Doc. No. MILLP-TSL-QD-QAP-SW-ITP-002

PREPARED BY
REV. DATE REVIEWED BY APPROVED BY REVIEWED & APPROVED BY TSL
MILLP
Minda Infrastructure LLP Tata Steel Limited

Project: Enabling Works, Ludhiana, Punjab Doc No: MILLP-TSL-QD-QAP-SW-ITP-002

INSPECTION TEST PLAN FOR FABRICATION OF STRUCTURAL STEEL – VENDOR SHOP

Sl.
Activity/Nature of Check/Test MILLP TSL/TPI FORM OF RECORD
No.

A PRE-FABRICATION ACTIVITIES CAT A CAT B CAT C

Availability of calibration certificates of measuring


1 a) WC Rw Rw Rw Calibration Certificates
& instruments/testing equipments

1 b) Field calibration, if any WC S S Calibration Certificates

2 Incoming material inspection WC HP HP HP IMIR

3 Welding Filler Material Approval/Qualification WC S S S

Review of Manufacturers Test Certificates/Other Batch test certificate and


a) WC Rw Rw Rw
documents Inspection reports

b) Sample test at NABL lab WC Rw Rw Rw Lab test report

4 Approval of WPS/PQR WC HP HP HP Approved WPS/PQR

WQT Records and Welder ID


5 WC HP HP HP
Welders performance qualification Card

Sketch showing lay out


6 WC S S S
Layout checking if applicable details

7 Welding equipment and accessories WC S S S ----

8 Preparation and approval of Fabrication drawings WC Rw Rw Rw RFC Drawings

B FABRICATION ACTIVITIES

1 Ensure Materials as per design drawing WC Rw Rw Rw RFC Drawings

2 Check straightness and non-warping of members WC S S --

Dimensional and fit-up checks including provision


3 WC S S --
of slopes for deflection wherever required

4 Visual check of welding WC S S --

5 Any NDT, if applicable WC S S -- Inspection Report

Surface preparation including grinding, for


6 WC S S --
painting and application of primer
Checking paint as per spec, self-life, test
7 WC WC S S Batch test certificates
certification , etc.

Ensure application of specified paint and


8 WC WC S S
thickness, etc.

C INSPECTION & TEST DOCUMENTS

Review Test & Inspection Documents and


1 WC Rw Rw Rw
release note for Dispatch (IRN) ----

LEGEND:

W-WITNESS POINT, HP- HOLD POINT, S-SURVEILLANCE, Rw-REVIEW OF DOCUMENTS, WC-100% Examination by
Contractor

CAT-A- Steel structures pertaining to Canteen building & Time Office structures.

CAT-B- Steel structures pertaining to Unit Pipe racks and other which is not covered in category A, etc.

CAT-C- Steel structures of Non critical racks (drains, branch pipe, offsite pipe rack,etc)Canteen building & Time Office.

Date & Prepared by Checked by


Description Reviewed & Approved by TSL
Revision MILLP MILLP
INSPECTION TEST
PLAN FOR
STRUCTURAL WORKS