THE ESTIMATION FOR PROPOSED CONSTRUCTION OF R.C.
C ,GROUND FLOOR BUILDING
WORK REQUIRMENTs
• Building Type : Individual Residential Building
• Floor : Ground
• Paints type : Premium
• Main door : Teak wood
• Wood work : Doors and windows,Modular kitchen,wardrobes,crockery unit, tv
Units, all interior works
• Electrical work : all electrical work
• Ceiling : gypsum ceiling
Total site area: 183.33 sq.yards
Total built up area: 1059.89 sq.ft.
Total cost of estimation:21,17,944/-
Rate Amount
S.No Description of Work Nos Length Breadth Depth/Height Qty Unit
Rs-Ps Rs-Ps
1 Earth work Excavation upto 1.5m below Ground level
For footings 12 1.20 1.20 1.20 20.74
For Building basement in Short
direction 3 7.81 0.45 0.60 6.33
In long Direction 4 12.51 0.45 0.60 13.51
For septic tank 1 1.50 1.50 1.80 4.05
Compound wall basement 1 50.53 0.45 0.45 10.23
54.86 Cum 250.00 13713.81
2 Laying of P.C.C of 1:4:8 including labour & materials for completion of work
For footings 12 1.20 1.20 1.20 20.74
Flooring 1 10.80 4.70 0.10 1.08
For building basement in short
direction 3 7.81 0.45 0.10 2.34
In long direction 4 12.51 0.45 0.10 2.25
For septic tank 1 1.50 1.50 0.10 0.23
Compound wall basement 1 50.53 0.45 0.15 3.41
30.05 Cum 4000.00 120186.30
R.C.C 1:1:5:3 for all- round including cost of necessary steel and
3
labour charges
For Footings 12 1.20 1.20 0.30 5.18
Plinth beam
Short direction 3 7.81 0.45 0.30 3.16
Long direction 4 12.51 0.45 0.30 6.76
For columns 12 0.23 0.23 10.80 6.86
Roof beams
In Short direction 4 7.81 0.23 0.30 2.16
In Long direction 3 12.51 0.23 0.30 2.59
Roof slab 1 12.51 7.81 0.13 12.70
Lintel Beams
For Building alround 7 9.00 0.23 0.15 2.17
Sunshades
Window type KW 1 1.20 0.91 0.08 0.09
Window type W2 6 1.30 1.37 0.08 0.85
staircase flights 2 2.00 1.00 0.11 0.44
Landing 1 2.00 0.90 0.11 0.20
Compound wall plinth Beam 1 50.53 0.23 0.30 3.49
Septic tank plate 1 1.00 3.00 0.12 0.36
47.01
Add 5% extra as wastage 2.35
49.36 Cum 13000.00 641620.07
Back Filling With
4 Excavated Earth 1 54.86 Cum 80.00 4388.42
5 Filling with Carted Earth 1 7.81 12.51 0.90 87.93 Cum 600.00 52759.67
6 Weathering proof plastering With C.M 1:5
1 7.81 12.51 97.70
97.70 Sq.mt 500.00 48851.55
7 Pest Control for Entire site 1 LS LS 10000.00
Brick masonry in C.M 1:6 in super structure in using second
class table moulded country bricks
8
For 230 mm thick Wall for external walls
All round building 1 40.64 0.23 3.00 28.04
Inner portions for for 1 30.55 0.12 3.00 10.54
Deductions
Doors--D1 4 1.00 0.12 2.00 0.96
Doors--D2 2 0.75 0.12 2.00 0.36
Window type KW -2 1.20 0.23 0.75 -0.41
Window type W2 -6 1.30 0.23 1.37 -2.46
Compound wall super structure 1 50.53 0.12 1.80 10.91
Septic tank walls 1 3.00 0.23 1.80 1.24
Staircase Steps 20 1.00 0.23 0.15 0.69
Staircase parapet walls 1 2.50 0.12 0.92 0.28
landing parapet walls 1 2.00 0.12 0.92 0.22
Terrace parapet walls 1 20.32 0.12 0.90 2.19
52.57
Add 5% extra as wastage 2.63
55.20 Cum 6000.00 331174.68
Plastering with CM 1:5 of 12.50mm thick for both external and internal walls
9
Alround buIlding 2 40.64 3.00 243.84
Inner partations 2 30.55 3.00 183.30
Deductions
Doors--D1 4 1.00 2.00 8.00
Doors--D2 2 0.75 2.00 3.00
Window type kW -2 1.20 0.75 -1.80
Window type W1 -6 1.30 1.37 -10.69
Compound wall super structure 1 0.75 1.80 1.35
Septic tank walls 1 3.00 1.80 5.40
Staircase Steps 20 1.00 0.15 3.00
Staircase parapet walls 1 2.50 0.92 2.30
landing parapet walls 1 2.00 0.92 1.84
Terrace parapet walls 1 20.32 0.90 18.29
457.83
Add 5% extra as wastage 22.89
961.45 Sq.mt 225.00 216325.62
Ceiling plastering with CM 1:4 of 12.50mm thick same as flooring area
10
Kitchen 1 3.65 2.52 9.20
Master bed room 1 3.65 3.27 11.94
Children Bed room 1 3.58 3.27 11.71
Living 1 3.58 4.32 15.47
dining 1 3.65 2.59 9.45
48.31
Add 5% extra as wastage 2.42
50.72 Sq.mt 250.00 12680.25
Providing & Applying Two caot wall care One coat of Primer & Two coats of
11 Emulsion for Internal & external walls
Qty as per Plastering area 1012.17 Sq.mt 250.00 253042.05
Vetrified flooring over ordinary cement finish by chipping and
12 laying C.M. leveling bed of 50mm thick
Master bed room 1 3.65 3.27 11.94
Skirting 1 13.84 0.31 4.29
childrens bed room 1 3.58 3.27 11.71
Skirting 1 13.70 0.31 4.25
Living 1 3.58 4.32 15.47
Skirting 1 15.80 0.31 4.90
dining 1 3.65 2.59 9.45
Skirting 1 12.48 0.31 3.87
52.54
Add 5% extra as wastage 2.63
55.17 Sq.mt 1000.00 55170.26
Ceramic flooring over ordinary cement finish by chipping and laying C.M.
leveling bed of 50mm thick
13
Kitchen 1 3.65 2.52 9.20
Dadoing 1 6.17 0.61 3.76
12.96
Add 5% extra as wastage 0.65
13.61 Sq.mt 1000.00 13609.79
14 Providing & Fixing of Granite works .
Kitchen platform 1 3.65 0.61 2.23
2.23 Sq.mt 4000.00 8906.00
Provideing & fixing of country wood doors with glazed shutters including cost
of all materials like hold-facts,tower bolts,wind appliances etc,and labour
15 charges
Doors--D1 4 1.00 2.00 8.00
Door -D2 2 0.75 2.00 3.00
11.00 Sq.mt 6000.00 66000.00
Provideing & fixing of country wood Windows with glazed shutters M.S grill
including cost of all materials like hold-facts,tower bolts,wind appliances
16 etc,and labour charges.
Window type KW 1 1.20 0.75 0.90
Window type W1 6 1.30 1.37 10.69
11.59 Sq.mt 6000.00 69516.00
SUB TOTAL 1917944.45
For the Electrification of the
* Entire Building@15% L.S 100000.00
For water supply & sanitary
* arrangement @15% L.S 100000.00
2117944.45
(Rupees Twenty One Lakhs Seventeen Thousand Nine Hundred and Fourty four Only)