Q 1)
Sr.No        Particular             No.   Length   Width    Height     Quantity         Remark
     1 UCR Masonry in CM (1:5)
                                                                                  L= (55.6-0.5*11*0.6)
              Footing (F1)          1      52.3     0.6       0.5      15.69 m3    = 52.3
                                                                        15.855    L= (55.6-0.5*11*0.5)
              Footing (F2)          1     52.85     0.5       0.6         m3       = 52.85
                                                                        14.952    L= (55.6-0.5*11*0.4)
              Footing (F3)          1      53.4     0.4      0.7          m3       = 53.4
                                                            Total       46.497
                                                           Quantity       m3
      I st Class Brick Masonry in
      CM (1:4) in Super                                                 51.792
    2 Structure.                    1     53.95     0.3       3.2         m3
               Deductions
              Window(W1)            4       2       0.3       1.5         3.6     W1 = 2 x 1.5 m
              Window(w2)            1      1.5      0.3       1.5       0.675     W2 = 1.5 x 1.5 m
              Ventilation (v)       2       1       0.3       0.6        0.36     V = 1 X 0.6 m
                 Door (D)           2      1.2      0.3       2.1       1.512     D=1.2 x 2.1 m
                Door (D1)           1       1       0.3       2.1        0.63     D1=1 x 2.1 m
                Door (D2)           1      0.9      0.3       2.1       0.567     D2= 0.9 x 2.1m
               Opening (o)          1      1.2      0.3       2.1       0.756     O=1.2 x 2.1 m
                                                             Total
                                                           Deduction    8.1 m3
       Deductions for Lintel
                                                                                  L = 0.15+2+0.15
              Window(W1)            4      2.3      0.3       0.3       0.828     =2.3
                                                                                  L = 0.15+1.5+0.15
              Window(w2)            1      1.8      0.3       0.3       0.162     =1.8
                                                                                  L = 0.15+1+0.15
             Ventilation (v)        2      1.3      0.3       0.3       0.234     =1.3
                                                                                  L = 0.15+1.2+0.15
                Door (D)            2      1.5      0.3       0.3        0.27     =1.5
                                                                                  L = 0.15+1+0.15
               Door (D1)            1      1.3      0.3       0.3       0.117     =1.3
                                                                                  L = 0.15+0.9+0.15
               Door (D2)            1      1.2      0.3       0.3       0.108     =1.2
                                                                                  L = 0.15+1.2+0.15
               Opening (o)          1      1.5      0.3       0.3       0.135     =1.5
                                                             Total
                                                           Deduction   1.854 m3
       Total Quantity of I st
       Class Brick Masonry in                                           41.838
       CM (1:4)                                                           m3
                                                                        16.185
    3 2.5cm thick DPC (1:2:4)       1     53.95     0.3        -          m2
  Net quantity of 12 mm thick
4 internal plaster in CM (1:4)
  Living Room                    1   16.4   -     3.5         57.4
  Kitchen                        1   12.8   -     3.5         44.8
  Bed Room                       1   14.2   -     3.5         49.7
  Bath room                      1    7.4   -     3.5         25.9
  W.C                            1    5.8   -     3.5         20.3
  Passage                        1    11    -     3.5         38.5
                                                 Total
                                                Quantity    236.6 m2
   Deduction
   Window(W1)                    4    2     -      1.5         12
   Window(w2)                    1   1.5    -      1.5        2.25
   Ventilation (v)               2    1     -      0.6         1.2
   Door (D)                      2   1.2    -      2.1        5.04
   Door (D1)                     1    1     -      2.1         2.1
   Door (D2)                     1   0.9    -      2.1        1.89
   Opening (o)                   1   1.2    -      2.1        2.52
                                                  Total
                                                Deduction    27 m2
   Net quantity of 12 mm
   thick internal plaster in
   CM (1:4)                                                 209.6 m2
     Q2)
Sr         Description of            length              Height
                              No.             width(W)            Quantity             Remark
No          Particulate                (L)                (H)
            Earthwork in                                                      L=52.8-(10*0.5*0.9)
1                              1      48.3       0.9      1.4     60.858 m3
             Excavation                                                       L=48.3 m
       P.C.C (1:2:4) for                                                      L=52.8-(10*0.5*0.9)
2                              1      48.3       0.9      0.2     8.694 m3
        foundation bed                                                        L=48.3 m
      D.P.C (2.5 cm thick)                                                    L=52.8-(10*0.5*0.3)
3                              1      51.3       0.3       -      15.39 m2
            in 1:3:6                                                          L=51.3 m
            I. Deduction
              Doors (D)        1      1.2        0.3       -        0.36      D= 1.2x2.1
             Doors (D1)        1       1         0.3       -         0.3      D1=1x2.1
             Doors (D2)        1      0.9        0.3       -        0.27      D2=0.9x2.1 (assume)
            Opening (O)        2      1.2        0.3       -        0.72      O=1.2x2.1
            Final D.P.C
                                                                  13.29 m2
              Quantity
      1st Class Brickwork
        in superstructure                                                     3m height of
4                              1      51.3       0.3       3      46.17 m3
       in cement mortar                                                       superstructure
              (1:4)
           I. Deduction for
               openings
              Doors (D)         1      1.2       0.3      2.1       0.756     D= 1.2x2.1
              Doors (D1)        1       1        0.3      2.1        0.63     D1=1x2.1
              Doors (D2)        1      0.9       0.3      2.1       0.567     D2=0.9x2.1 (assume)
            Window (W1)         2       2        0.3      1.3        1.56     W1=2x1.3
            Window (W2)         3      1.5       0.3      1.3       1.755     W2=1.5x1.3
           Ventilation (V)      2      0.6       0.3      0.4       0.144     V=0.6x0.4
             Opening (O)        2      1.2       0.3      2.1       1.512     O=1.2x2.1
                        Total Deduction for openings
                                                                  6.924 m3
       II. Deduction for                                                          Assuming Height
             lintel                                                               of lintel as 0.3 M
           Doors (D)           1      1.5        0.3      0.3       0.135     D= 1.5
           Doors (D1)          1      1.3        0.3      0.3       0.117     D1=1.3
           Doors (D2)          1      1.2        0.3      0.3       0.108     D2=1.2
        Window (W1)            2      2.3        0.3      0.3       0.414     W1=2.3
        Window (W2)            3      1.8        0.3      0.3       0.486     W2=1.8
        Ventilation (V)        2      0.9        0.3      0.3       0.162     V=0.9
          Opening (O)          2      1.5        0.3      0.3        0.27     O=1.5
      Total Deduction for
                                                                  1.692 m3
             lintel
Final Quantity for
   Brickwork in      37.554 m3
  superstructure