Engineering & Projects Division
Safety Inspection Checklist for Welding Machine
Issue No- 01 Rev. No.- 00 Date- 10/08/2023 Form No -E&P/Checklist/007/Rev-00
15
16
14
17
Location Projects
Section Vendor
Equipment No. Line Manager
Engineering & Projects Division
Safety Inspection Checklist for Welding Machine
Issue No- 01 Rev. No.- 00 Date- 10/08/2023 Form No -E&P/Checklist/007/Rev-00
Inspection Date
SN. Description
Yes/No Yes/No Yes/No Yes/No
1 Is ON / OFF knob provided? (Check for damage and insulation knob)
2 Is Regulator with indicator provided?
Are Welding cables connected to the welding machine with lugs at
3
the joints?
Any Damage in the insulation of welding cables (Only cable free
4 from repair or splices for a minimum distance of 3.0 m from the
cable end to be used)?
Electrode holder and Ground clamp (earthing holder) are in proper
5
condition or not?
Is Industrial type Plug for power tapping cable of welding machine
6 Provided with earth leakage protective device having rating less
than 100 mA with fault clearing time less than 100 milli seconds?
7 Are Internal live electrical parts of welding machine exposed?
Is separate entry permit/ work permit (hot work) taken where welding
job is to be carried out at height (more than 2 meters) from ground
8
level/in confined space/gaseous hazardous area/ near electrical
installation?
9 Are emergency contact nos. available/displayed near working area?
10 Is Fire extinguisher (DCP) and fire bucket with sand available?
Is Welding Curtain / Screen / Fire blanket/ spatter arrestor
11
available?
Are all necessary PPEs available & used? (Welding Goggles, Leather
12
Gloves etc.)
13 Is Welding area free from debris and flammable materials?
14 Is Double body earthing provided or not?
15 Is VRD (Wes guard) in ON condition and working properly?
Are both cables (Return and power) Parallel runoff and attached to job
(Distance of return path (return clamp) of welding machine from the
16
welding point (welding electrode holder) is allowed maximum 30M of
cable length.)?
17 Is Rubber mat or insulation mat are installed below/ in front?
18 Is Open circuit voltage of welding set less than 90 volts AC / DC.
19 Is welder certified/qualified as per ASME Sec IX?
Is there proper ventilation system in place when the welding is
20
performed in confined space?
Remarks-
Name-
Checked by P. No./ Gate Pass No.-
Signature-