Erection Report Format

Uploaded by

jubergadkari
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 23

Classification: Internal

ERECTION REPORT

Customer Name Date :


Thermax OC NO Report No:
Equipment Name

Site Location

S.NO DESCRIPTION STATUS

1 Scrubber installation on pedestal as per approved drawing.

2 Anchor bolts installation

3 Outlet exhaust pipe connection completion

Mist eliminator filling works completed as per the level


4 mentioned on the drawing / specification with proper locking
arrangement.

All spray nozzles installed proper orientation as per the


5
drawing.

Man hole closing works with proper fasteners completion


6
status

7 Gas inlet and outlet line works completed status

8 Level transmitter installation

9 Differential pressure transmitter installation

10 Overflow line connection completed

11 Drain line connection completed status


Classification: Internal

12 Dosing line connection status

13 pH pot return connection status

14 Makeup water line connection work status

15 Pump suction line works completion

Platform structural works completion status as per the


16
drawing.

17 Structural painting works status

18 Scrubber painting works status.

THERMAX LTD TCE

NAME

SIGNATURE

DATE
Classification: Internal

N REPORT

:
rt No:

VERIFIED BY VERIFIED BY VERIFIED BY


REMARKS
THERMAX TCE TPSL
Classification: Internal

TCE TP SOLAR
Classification: Internal

VERIFIED BY
S.NO DESCRIPTION STATUS
THERMAX

1 Pump installation completed as per drawing.

2 Motor installation completed as per drawing.

3 Foundation bolts installation status

4 Frame grouting completed.

Pump inlet piping works & valve package


5
installation status as per the P&ID.

Pump outlet piping works & valve package


6
installation status as per the P&ID.
Classification: Internal

VERIFIED BY
REMARKS
TCE / TPSL
Classification: Internal

VERIFIED BY
S.NO DESCRIPTION STATUS
THERMAX
Tank installation on pedestal as per approved
1
drawing.

2 Anchor bolts installation / grouting completion

3 Level gauge installation as per the drawing.

Drain line installation with necessary valves


4
completion till drain pit.

5 Vent line installation with cowl piece.

6 Level transmitter installation as per the drawing.

7 Tank inlet line works completion

8 Tank outlet line works completion

9 Overflow line works completion till pit.

10 Painting / finishing coating completion.

All necessary supports installation with proper


11
painting and anchor fasteners installation.
Classification: Internal

VERIFIED BY
REMARKS
TCE / TPSL

`
Classification: Internal

S.NO DESCRIPTION STATUS

1 Fan baseframe installation

2 Foundation bolts installation

3 Vibration isolator installation

4 Bearing housing, shaft installation

5 Fan casing instalaltion with access door

6 Motor installation

7 Outlet flexible connection installation

8 Inlet flexible bellow installation

9 Actuator dampers installation in inlet / outlet

10 Dampers actuator installation as per drg.

11 Bellows supports installation

12 Necessary GI bolts installation as per drg.

13 Protection guard for all rotated parts

14 Drain plug installation as per drg.

15 Inlet connection completion status with related cluster.

16 Outlet ducting works completion status with chimney.


Classification: Internal

VERIFIED BY VERIFIED BY
REMARKS
THERMAX TCE / TPSL
Classification: Internal

S.NO DESCRIPTION STATUS

10

11

12

13

14

15

16
Classification: Internal

VERIFIED BY VERIFIED BY
REMARKS
THERMAX TCE / TPSL
Classification: Internal

ERECTION REPORT

Client: T P Solar Location:


Thermax OC NO: E306128 Equipment Name:
Report No: Cluster No:
Date: Drawing No:
SCRUBBER CHECKLIST

VERIFIED BY VERIFIED VERIFIED


S.NO DESCRIPTION STATUS THERMAX BY TCE BY TPSL REMARKS

Scrubber installation on pedestal as per


1
approved drawing.

2 Anchor bolts installation

3 Outlet exhaust pipe connection completion

Mist eliminator filling works completed as per the


4 level mentioned on the drawing / specification with
proper locking arrangement.

5 All spray nozzlesper


installed proper orientation as
the drawing.

Man hole closing works with proper fasteners


6 completion status

Gas inlet and outlet line works completed


7 status

8 Level transmitter installation

9 Differential pressure transmitter installation

10 Overflow line connection completed

11 Drain line connection completed status

12 Dosing line connection status

13 pH pot return connection status

14 Makeup water line connection work status

15 Pump suction line works completion

16 Platform structural
works completion status as
per the drawing.

17 Structural painting works status

18 Scrubber painting works status.

THERMAX LTD TCE T P SOLAR


NAME

SIGNATURE & DATE


Classification: Internal

ERECTION REPORT

Client: T P Solar Location:


Thermax OC NO: E306128 Equipment Name:
Report No: Cluster No:
Date: Drawing No:

RECIRCULATION PUMP CHECKLIST

S.NO DESCRIPTION STATUS VERIFIED BY VERIFIED VERIFIED REMARKS


THERMAX BY TCE BY TPSL

1 Pump installation completed as


per drawing.

2 Motor installation completed as


per drawing.

3 Foundation bolts installation


status

4 Frame grouting completed.

Pump inlet piping works & valve


5 package installation status as per
the P&ID.

Pump outlet piping works & valve


6 package installation status as per
the P&ID.

THERMAX LTD TCE T P SOLAR

NAME

SIGNATURE

DATE
Classification: Internal

ERECTION REPORT

Client: T P Solar Location:

Thermax OC NO: E306128 Equipment Name:

Report No: Cluster No:

Date: Drawing No:

CAUSTIC TANK CHECKLIST

VERIFIED BY
S.NO DESCRIPTION STATUS THERMAX VERIFIED BY TCE VERIFIED BY TPSL

1 Tank installation on pedestal as


per approved drawing.

2 Anchor bolts installation /


grouting completion

3 Level gauge installation as per


the drawing.

Drain line installation with


4 necessary valves completion till
drain pit.

5 Vent line installation with cowl


piece.

6 Level transmitter installation as


per the drawing.

7 Tank inlet line works


completion

8 Tank outlet line works


completion

9 Overflow line works completion


till pit.

10 Painting / finishing coating


completion.

All necessary supports


11 installation with proper painting
and anchor fasteners
installation.

THERMAX LTD TCE


Classification: Internal

NAME

SIGNATURE

DATE
Classification: Internal

ERECTION REPORT

CAUSTIC TANK CHECKLIST

REMARKS

T P SOLAR
Classification: Internal
Classification: Internal

ERECTION REPORT

Client: T P Solar Location:

Thermax OC NO: E306128 Equipment Name:

Report No: Cluster No:

Date: Drawing No:

ID FAN CHECKLIST
VERIFIED
VERIFIED VERIFIED BY
S.NO DESCRIPTION STATUS BY REMARKS
BY TCE TPSL
THERMAX

1 Fan baseframe installation

2 Foundation bolts installation

3 Vibration isolator installation

4 Bearing housing, shaft installation

5 Fan casing instalaltion with access door

6 Motor installation

7 Outlet flexible connection installation

8 Inlet flexible bellow installation

9 Actuator dampers installation in inlet /


outlet

10 Dampers actuator installation as per drg.

11 Bellows supports installation

12 Necessary GI bolts installation as per


drg.

13 Protection guard for all rotated parts

14 Drain plug installation as per drg.

15 Inlet connection completion status with


related cluster.

16 Outlet ducting works completion status


with chimney.

THERMAX LTD TCE TP SOLAR

NAME

SIGNATURE

DATE
Classification: Internal

ERECTION REPORT

Client: T P Solar Location:

Thermax OC NO: E306128 Equipment Name:

Report No: Cluster No:

Date: Drawing No:

CAUSTIC DOSING PUMP CHECKLIST

VERIFIED BY VERIFIED BY VERIFIED


S.NO DESCRIPTION STATUS THERMAX TCE BY TPSL REMARKS

1 Pump installation completed as per


drawing.

2 Motor installation completed as per


drawing.

3 Foundation bolts installation status

4 Frame grouting completed.

5 Pump inlet piping works & valve package


installation status as per the P&ID.

Pump outlet piping works & valve


6 package installation status as per the
P&ID.

THERMAX LTD TCE TP SOLAR

NAME

SIGNATURE

DATE
Classification: Internal

ERECTION REPORT

Client: T P Solar Location:

Thermax OC NO: E306128 Equipment Name:

Report No: Cluster No:

Date: Drawing No:

STACK CHECKLIST

S.NO DESCRIPTION STATUS VERIFIED BY VERIFIED VERIFIED REMARKS


THERMAX BY TCE BY TPSL

1 Stack installation on pedestal as per


approved drawing.

2 Grouting completion

3 Stack inlet line works completion

4 Painting / finishing coating completion.

5 All necessary supports installation with


proper painting and fasteners installation.

THERMAX LTD TCE TP SOLAR

NAME

SIGNATURE

DATE
Classification: Internal

S.N DESCRIPTION

Raw water pipe line frequent leakages happening at site, same to be


1
rectified.

Butterfly valve 400 NB damaged to be replaced in the raw water line


2
(Raw water to ETP line)

As per the commissioning report 03 - Raw water to UPW line all the balance
works to be completed
3
(balance clamping works, supports painting installation and proper
fasteners installation)

As per the commissioning report 04 - Utility building to ETP line all the
balance works to be completed.
4
(supports welding work, U clamps installation, supports painting works,
proper fasteners installation works to be completed.)

As per the commissioning report 06 - N2O2 to ETP line all the balance works
to be completed.
5
(supports welding work, U clamps installation, supports painting works to
be completed.)

Balance 36m of pipe line and 2 valves installation to be completed in the


6
raw water line

7 All the excess pipes (983 m) to be handed over to TPSL

8 System handing over and as built drawing to be submitted


Classification: Internal

PRESENT STATUS

Pending.

Pending.

Pending / Incomplete

Pending / Incomplete

Pending / Incomplete S

Pending due to shutdown.

Pending

Pending