Classification: Internal
ERECTION REPORT
Customer Name Date :
Thermax OC NO Report No:
Equipment Name
Site Location
S.NO DESCRIPTION STATUS
1 Scrubber installation on pedestal as per approved drawing.
2 Anchor bolts installation
3 Outlet exhaust pipe connection completion
Mist eliminator filling works completed as per the level
4 mentioned on the drawing / specification with proper locking
arrangement.
All spray nozzles installed proper orientation as per the
5
drawing.
Man hole closing works with proper fasteners completion
6
status
7 Gas inlet and outlet line works completed status
8 Level transmitter installation
9 Differential pressure transmitter installation
10 Overflow line connection completed
11 Drain line connection completed status
Classification: Internal
12 Dosing line connection status
13 pH pot return connection status
14 Makeup water line connection work status
15 Pump suction line works completion
Platform structural works completion status as per the
16
drawing.
17 Structural painting works status
18 Scrubber painting works status.
THERMAX LTD TCE
NAME
SIGNATURE
DATE
Classification: Internal
N REPORT
:
rt No:
VERIFIED BY VERIFIED BY VERIFIED BY
REMARKS
THERMAX TCE TPSL
Classification: Internal
TCE TP SOLAR
Classification: Internal
VERIFIED BY
S.NO DESCRIPTION STATUS
THERMAX
1 Pump installation completed as per drawing.
2 Motor installation completed as per drawing.
3 Foundation bolts installation status
4 Frame grouting completed.
Pump inlet piping works & valve package
5
installation status as per the P&ID.
Pump outlet piping works & valve package
6
installation status as per the P&ID.
Classification: Internal
VERIFIED BY
REMARKS
TCE / TPSL
Classification: Internal
VERIFIED BY
S.NO DESCRIPTION STATUS
THERMAX
Tank installation on pedestal as per approved
1
drawing.
2 Anchor bolts installation / grouting completion
3 Level gauge installation as per the drawing.
Drain line installation with necessary valves
4
completion till drain pit.
5 Vent line installation with cowl piece.
6 Level transmitter installation as per the drawing.
7 Tank inlet line works completion
8 Tank outlet line works completion
9 Overflow line works completion till pit.
10 Painting / finishing coating completion.
All necessary supports installation with proper
11
painting and anchor fasteners installation.
Classification: Internal
VERIFIED BY
REMARKS
TCE / TPSL
`
Classification: Internal
S.NO DESCRIPTION STATUS
1 Fan baseframe installation
2 Foundation bolts installation
3 Vibration isolator installation
4 Bearing housing, shaft installation
5 Fan casing instalaltion with access door
6 Motor installation
7 Outlet flexible connection installation
8 Inlet flexible bellow installation
9 Actuator dampers installation in inlet / outlet
10 Dampers actuator installation as per drg.
11 Bellows supports installation
12 Necessary GI bolts installation as per drg.
13 Protection guard for all rotated parts
14 Drain plug installation as per drg.
15 Inlet connection completion status with related cluster.
16 Outlet ducting works completion status with chimney.
Classification: Internal
VERIFIED BY VERIFIED BY
REMARKS
THERMAX TCE / TPSL
Classification: Internal
S.NO DESCRIPTION STATUS
10
11
12
13
14
15
16
Classification: Internal
VERIFIED BY VERIFIED BY
REMARKS
THERMAX TCE / TPSL
Classification: Internal
ERECTION REPORT
Client: T P Solar Location:
Thermax OC NO: E306128 Equipment Name:
Report No: Cluster No:
Date: Drawing No:
SCRUBBER CHECKLIST
VERIFIED BY VERIFIED VERIFIED
S.NO DESCRIPTION STATUS THERMAX BY TCE BY TPSL REMARKS
Scrubber installation on pedestal as per
1
approved drawing.
2 Anchor bolts installation
3 Outlet exhaust pipe connection completion
Mist eliminator filling works completed as per the
4 level mentioned on the drawing / specification with
proper locking arrangement.
5 All spray nozzlesper
installed proper orientation as
the drawing.
Man hole closing works with proper fasteners
6 completion status
Gas inlet and outlet line works completed
7 status
8 Level transmitter installation
9 Differential pressure transmitter installation
10 Overflow line connection completed
11 Drain line connection completed status
12 Dosing line connection status
13 pH pot return connection status
14 Makeup water line connection work status
15 Pump suction line works completion
16 Platform structural
works completion status as
per the drawing.
17 Structural painting works status
18 Scrubber painting works status.
THERMAX LTD TCE T P SOLAR
NAME
SIGNATURE & DATE
Classification: Internal
ERECTION REPORT
Client: T P Solar Location:
Thermax OC NO: E306128 Equipment Name:
Report No: Cluster No:
Date: Drawing No:
RECIRCULATION PUMP CHECKLIST
S.NO DESCRIPTION STATUS VERIFIED BY VERIFIED VERIFIED REMARKS
THERMAX BY TCE BY TPSL
1 Pump installation completed as
per drawing.
2 Motor installation completed as
per drawing.
3 Foundation bolts installation
status
4 Frame grouting completed.
Pump inlet piping works & valve
5 package installation status as per
the P&ID.
Pump outlet piping works & valve
6 package installation status as per
the P&ID.
THERMAX LTD TCE T P SOLAR
NAME
SIGNATURE
DATE
Classification: Internal
ERECTION REPORT
Client: T P Solar Location:
Thermax OC NO: E306128 Equipment Name:
Report No: Cluster No:
Date: Drawing No:
CAUSTIC TANK CHECKLIST
VERIFIED BY
S.NO DESCRIPTION STATUS THERMAX VERIFIED BY TCE VERIFIED BY TPSL
1 Tank installation on pedestal as
per approved drawing.
2 Anchor bolts installation /
grouting completion
3 Level gauge installation as per
the drawing.
Drain line installation with
4 necessary valves completion till
drain pit.
5 Vent line installation with cowl
piece.
6 Level transmitter installation as
per the drawing.
7 Tank inlet line works
completion
8 Tank outlet line works
completion
9 Overflow line works completion
till pit.
10 Painting / finishing coating
completion.
All necessary supports
11 installation with proper painting
and anchor fasteners
installation.
THERMAX LTD TCE
Classification: Internal
NAME
SIGNATURE
DATE
Classification: Internal
ERECTION REPORT
CAUSTIC TANK CHECKLIST
REMARKS
T P SOLAR
Classification: Internal
Classification: Internal
ERECTION REPORT
Client: T P Solar Location:
Thermax OC NO: E306128 Equipment Name:
Report No: Cluster No:
Date: Drawing No:
ID FAN CHECKLIST
VERIFIED
VERIFIED VERIFIED BY
S.NO DESCRIPTION STATUS BY REMARKS
BY TCE TPSL
THERMAX
1 Fan baseframe installation
2 Foundation bolts installation
3 Vibration isolator installation
4 Bearing housing, shaft installation
5 Fan casing instalaltion with access door
6 Motor installation
7 Outlet flexible connection installation
8 Inlet flexible bellow installation
9 Actuator dampers installation in inlet /
outlet
10 Dampers actuator installation as per drg.
11 Bellows supports installation
12 Necessary GI bolts installation as per
drg.
13 Protection guard for all rotated parts
14 Drain plug installation as per drg.
15 Inlet connection completion status with
related cluster.
16 Outlet ducting works completion status
with chimney.
THERMAX LTD TCE TP SOLAR
NAME
SIGNATURE
DATE
Classification: Internal
ERECTION REPORT
Client: T P Solar Location:
Thermax OC NO: E306128 Equipment Name:
Report No: Cluster No:
Date: Drawing No:
CAUSTIC DOSING PUMP CHECKLIST
VERIFIED BY VERIFIED BY VERIFIED
S.NO DESCRIPTION STATUS THERMAX TCE BY TPSL REMARKS
1 Pump installation completed as per
drawing.
2 Motor installation completed as per
drawing.
3 Foundation bolts installation status
4 Frame grouting completed.
5 Pump inlet piping works & valve package
installation status as per the P&ID.
Pump outlet piping works & valve
6 package installation status as per the
P&ID.
THERMAX LTD TCE TP SOLAR
NAME
SIGNATURE
DATE
Classification: Internal
ERECTION REPORT
Client: T P Solar Location:
Thermax OC NO: E306128 Equipment Name:
Report No: Cluster No:
Date: Drawing No:
STACK CHECKLIST
S.NO DESCRIPTION STATUS VERIFIED BY VERIFIED VERIFIED REMARKS
THERMAX BY TCE BY TPSL
1 Stack installation on pedestal as per
approved drawing.
2 Grouting completion
3 Stack inlet line works completion
4 Painting / finishing coating completion.
5 All necessary supports installation with
proper painting and fasteners installation.
THERMAX LTD TCE TP SOLAR
NAME
SIGNATURE
DATE
Classification: Internal
S.N DESCRIPTION
Raw water pipe line frequent leakages happening at site, same to be
1
rectified.
Butterfly valve 400 NB damaged to be replaced in the raw water line
2
(Raw water to ETP line)
As per the commissioning report 03 - Raw water to UPW line all the balance
works to be completed
3
(balance clamping works, supports painting installation and proper
fasteners installation)
As per the commissioning report 04 - Utility building to ETP line all the
balance works to be completed.
4
(supports welding work, U clamps installation, supports painting works,
proper fasteners installation works to be completed.)
As per the commissioning report 06 - N2O2 to ETP line all the balance works
to be completed.
5
(supports welding work, U clamps installation, supports painting works to
be completed.)
Balance 36m of pipe line and 2 valves installation to be completed in the
6
raw water line
7 All the excess pipes (983 m) to be handed over to TPSL
8 System handing over and as built drawing to be submitted
Classification: Internal
PRESENT STATUS
Pending.
Pending.
Pending / Incomplete
Pending / Incomplete
Pending / Incomplete S
Pending due to shutdown.
Pending
Pending